FRONT END ENGINEERING DESIGN 2
(FEED 2)
ONSHORE PIPELINE
SENIPAH - RU V BALIKPAPAN
TITLE DOCUMENT NUMBER REV PAGE
TABLE OF CONTENTS
1. INTRODUCTION ............................................................................................................ 5
1.1 General ............................................................................................................... 5
2. OBJECTIVE ................................................................................................................... 6
3. DEFINITIONS ................................................................................................................. 6
4. REQUISITION FOR EQUIPMENT .................................................................................. 6
5. ABBREVIATIONS .......................................................................................................... 7
6. SCOPE OF WORK & SUPPLY ...................................................................................... 7
7. INSPECTION AND TESTING ......................................................................................... 9
8. DOCUMENTATION ........................................................................................................ 9
8.1 General ............................................................................................................... 9
8.2 Schedule ............................................................................................................ 9
8.3 Procedure of Documentation ........................................................................... 9
9. PREPARATION FOR SHIPMENT ................................................................................ 10
10. QUALITY CONTROL PLAN ......................................................................................... 10
11. PROJECT MANAGEMENT AND ADMINISTRATION .................................................. 11
12. COMPANY PERSONNEL / REPRESENTATIVES ....................................................... 12
12.1 Services to COMPANY .................................................................................... 12
12.2 Third Party Certification .................................................................................. 12
13. GUARANTEE ............................................................................................................... 12
14. APLICABLE DOCUMENT ............................................................................................ 13
FRONT END ENGINEERING DESIGN 2
(FEED 2)
ONSHORE PIPELINE
SENIPAH - RU V BALIKPAPAN
TITLE DOCUMENT NUMBER REV PAGE
1. INTRODUCTION
1.1 General
PT Pertamina Gas (Pertagas) plan to deliver gas from Senipah KP7.2 (tap off from 42”
pipeline) that is operated by PertaminaHulu Mahakam to PT PERTAMINA (Persero)
Refinery Unit (RU V) Balikpapan, East Kalimantan, to fulfill the gas demand at Refinery
Unit (RU V) Balikpapan as part of the RDMP program.
The Onshore Pipeline Senipah – RU V Balikpapan scope will comprise of development
of mini facility in Senipah and RU V Balikpapan area consist of gas metering, pigging
facilities, utilities and an onshore gas pipeline
2. OBJECTIVE
This document defines the requirements to engineering design, the specifications and
associated documentation applicable to the engineering, fabrication, procurement,
supply and delivery of the Diesel Oil Storage Tank.
3. DEFINITIONS
COMPANY PT. PERTAMINA GAS (PERTAGAS), the ultimate end user
and owner.
CONSULTANT The party selected by PERTAGAS to perform the FEED 2
(Front End Engineering Design 2) specified by PERTAGAS.
CONTRACTOR The party that carries out all or part of the detailed design,
engineering, procurement, construction, installation and
commissioning.
VENDOR The party, which manufactures and / or supplies the equipment
and services to perform the duties specified by the
CONTRACTOR.
MANUFACTURER Party which manufactures equipment/materials specified and
ordered by CONTRACTOR.
4. REQUISITION FOR EQUIPMENT
TOTAL 2
FRONT END ENGINEERING DESIGN 2
(FEED 2)
ONSHORE PIPELINE
SENIPAH - RU V BALIKPAPAN
TITLE DOCUMENT NUMBER REV PAGE
5. ABBREVIATIONS
API American Petroleum Institute
ASME American Society of Mechanical Engineers
FEED 2 Front End Engineering Design 2
GA General Arrangement
ITP Inspection and Test Plan
MIGAS Indonesia Certification Authority
NDT Non-Destructive Test
NDE Non-Destructive Examination
PQR Procedure Qualification Report
RU Refinery Unit
WPS Welding Procedure Specification
WQT Welder Qualification Test
6. SCOPE OF WORK & SUPPLY
Design, procurements, fabrication, fully tested as required in specifications and
datasheet reference in this requisition.
6.1 Scope of Supply
All materials required but not limited to below, shall be in the scope of VENDOR :
Plates (shell, top, and bottom).
Nozzles .
Lifting lugs.
Davit / hinge support for manhole.
Support / stiffener (internal and external), if required.
Bolts & Nuts (internal and external).
Gaskets.
Earting Lugs.
Name plate & bracket.
Surface preparation / painting.
Temporary skid and wooden box for transportation.
FRONT END ENGINEERING DESIGN 2
(FEED 2)
ONSHORE PIPELINE
SENIPAH - RU V BALIKPAPAN
TITLE DOCUMENT NUMBER REV PAGE
Item
Document No. Description
No.
A Mechanical Documents
B Other Documents
(*): Latest revision of the document at the time of Purchase Order issue shall be followed