Professional Documents
Culture Documents
https://doi.org/10.1038/s41560-022-01041-6
Electrifying 600 million people in sub-Saharan Africa will require substantial investments. Integrated electrification models
inform key policy decisions and electricity access investments in many countries. While current electrification models apply
sophisticated geospatial methods, they often make simplistic assumptions about financing conditions. Here we establish cost
of capital values, reflecting country and electrification mode (that is, grid extension, minigrids and stand-alone systems), and
specific risks faced by investors and integrate them into an open source electrification model. We find that the cost of capital
for off-grid electrification is much higher than currently assumed, up to 32.2%. Accounting for finance shifts approximately
240 million people from minigrids to stand-alone systems in our main scenario, suggesting a more cost-effective electrifica-
tion mode mix than previously suggested. In turn, electrification models based on uniform cost of capital assumptions increase
the per kWh cost of electricity by 20%, on average. Upscaling and mainstreaming off-grid finance can lower electrification
cost substantially.
A
s of 2018, an estimated 600 million people in sub-Saharan Spatial Electrification Tool (OnSSET)1,6,7,11,22 (Methods provide a
Africa did not have access to electricity1. Because electri- detailed model description). The model derives least-cost path-
fication has been identified as a key factor in eradicating ways to 100% electrification of sub-Saharan Africa by 2030 with an
poverty2, the United Nations Sustainable Development Goal (SDG) intermediate target of 50% in 2025 (Methods). We first quantify the
7 has set a goal to ‘ensure universal access to affordable, reliable, cost of capital for different electrification modes for all sub-Saharan
sustainable and modern energy services’ by 20303. Historically, African countries (Methods provide electrification-mode specifica-
electrification has happened through grid extension. More recently, tions). Second, we define four financing scenarios reflecting differ-
the emergence of off-grid solar-powered minigrids (MGs) and ent possible sources of capital and maturities of the off-grid finance
stand-alone systems (SASs) has created new electrification modes sector (Table 1). Third, we apply the model (Table 2 lists model
for rural regions, where most of the continent’s un-electrified popu- inputs), to the financing scenarios in two defined grid-extension
lation lives1,4,5. The diversity of electrification modes (grid extension, pathways that typically rely on government intervention for grid
MGs and SASs) and the rapid cost declines of the off-grid modes extension: an extended-area grid pathway where electrification of
has spurred the need for planning based on integrated geospatial a cluster is solely based on the least-cost electrification mode opti-
electrification models, which inform electrification choices based mization through grid extension, MG or SAS, and an existing-area
on cost criteria, typically the levelized cost of electricity (LCOE). grid pathway where grid extension beyond already electrified grid
These models have reached relatively high levels of sophistication areas is halted in the model, while off-grid options are allowed. This
and have become prominent in the academic and grey literature1,6–12 second model is to account for the limited success in extending the
and policy design13–15. While the LCOE of different electrifica- grid in sub-Saharan Africa. We analyse results for all of sub-Saharan
tion modes is typically derived from a detailed representation of Africa and deep dive into focus countries, the Democratic Republic
equipment cost, the established models do not consider the cost of of the Congo (DRC), Ethiopia, Nigeria and Zimbabwe, to highlight
capital, specifically. They assume a standard discount rate across the differing effects of the representative financing cost assump-
all electrification modes and geographies (typically around 8%) tions. Finally, we derive implications for electrification researchers,
(refs. 6–8,16) with a few studies assessing sensitivity to this rate assump- international organizations and national policymakers.
tion but without differentiating between electrification modes7,9,17,18.
To compare the LCOE of different electrification modes in a real Cost of capital for electrification
world setting, however, the cost of capital needs to be taken into In most sub-Saharan African countries, grid extension is primarily
account19. A uniform discount rate of 8% does not reflect the actual financed by the public sector (that is, from tax revenues or sovereign
financing situation and might introduce substantial bias20,21. debt)4,20, while MGs and SASs are primarily financed by the private
Here we estimate representative cost of capital and implement sector (that is, from privately owned companies)20,23. For public
them in a geospatial electrification model that assigns least-cost elec- finance, the cost of capital varies widely across countries20,24 but rep-
trification modes to population clusters across sub-Saharan Africa. resents the sovereign risk of lending to a government. For private
More specifically, we differentiate cost of capital by country and elec- finance, investors typically finance off-grid companies at a premium
trification mode and thereby extend the widely used Open Source above the sovereign risk, which increases the cost of capital23,25.
1
Energy and Technology Policy Group, ETH, Zurich, Switzerland. 2Kigali Collaborative Research Centre (KCRC), Kigali, Rwanda. 3UCL Institute for Innovation
and Public Purpose (IIPP), London, UK. 4Golisano Institute for Sustainability, Rochester Institute of Technology, Rochester, NY, USA. 5Institute of Science,
Technology and Policy, ETH, Zurich, Switzerland. 6Climate Finance and Policy Group, ETH, Zurich, Switzerland. ✉e-mail: churchill.agutu@gess.ethz.ch;
florian.egli@gess.ethz.ch; tobiasschmidt@ethz.ch; bjarne.steffen@gess.ethz.ch
Table 1 | Description of financing scenarios. Methods provide details on scenario description and the derivation of country- and
mode-specific costs of capital
Scenario Description Financing sources
Grid extension MGs SASs
Uniform • Standard assumption in the literature Not specified Not specified Not specified
• Cost of capital is uniform (8%) across countries and
electrification modes
Public sector financing • Electrification is solely financed by the government Public sector Public sector Public sector
• Cost of capital is country specific and identical across
electrification modes
Niche (status quo) financing • Status quo financing where the off-grid electricity Public sector Private sector (debt Private sector (debt
sector is nascent (small caps, limited liquidity, low debt share 0%) share 50%)
shares)
• Cost of capital is country- and mode-specific
Mainstream financing • Potential future mainstream financing after the off-grid Public sector Private sector (debt Private sector (debt
electricity sector has matured (larger caps, more share 40%) share 75%)
liquidity, higher debt shares)
• Cost of capital is country- and mode-specific
Equatorial Guinea
Togo
Cameroon
Guinea-Bissau
Sao Tome & Principe
Rwanda
Gabon
Tanzania
Uganda
Madagascar
Eswatini
Comoros
Angola
Kenya
Nigeria
Benin
Ethiopia
Senegal MG & SAS public-sector
financing
Côte d'Ivoire MG mainstream
financing (premium)
Namibia
SAS mainstream
South Africa financing (premium)
MG niche financing
Mauritius (additional premium)
Botswana SAS niche financing
(additional premium)
0 5 8 10 15 20 25 30 35
Cost of capital (%)
Fig. 1 | Cost of capital estimates for the different financing scenarios and for the different electrification modes. The differences between the countries
are based on the country default spreads (reflecting country-specific investment risk52), while the differences between the electrification modes are based
on variations in the debt share (Methods). The differences between the financing scenarios are based on different sources of capital and on different
maturities of the off-grid finance sector. The dotted line reflects the cost of capital for the uniform financing scenario.
14 14 7 10 36
80 80
New connections 2030 (%)
60 60 56 55 51
31
40 76 80 78 40
75
20 20
34 34 34 34
0 0
Uniform Public Niche Mainstream Uniform Public Niche Mainstream
c d
350 350
300 300
43 45
244 64
250 228 228 232 250
149
49
200 42 44 48 200
23
50 47 33
150 150 212 210
190
Fig. 2 | Results showing the newly connected populations and total investments between 2018 and 2030 based electrification mode for the defined
electrification pathways and financing scenario. a, Total new connections per electrification mode for the extended-area grid pathway (columns) and
ratio of MGs to SASs for each financing scenario (pies). b, Total new connections per electrification mode for the existing-area pathway (columns) and
ratio of MGs to SASs for each financing scenario (pies). c, Total investments needed to finance the extended-area grid pathway. d, Total investments
needed to finance the existing-area grid pathway. Values have been rounded to the nearest integer; the same operation is carried out for all numbers to
ensure consistency. Numbers in the bars show the percentage of new connections (a,b) and the total investment (c,d) for each electrification mode.
Africa’s un-electrified population1, have failed to reach their grid Energy Agency of US$21 billion per annum1. The total investment
infrastructure development plans to date. The existing-area grid cost is approximately 30% higher for the existing-area pathway.
pathway, therefore, represents the other extreme where current Third, the status quo (niche financing) departs from the uniform
grid infrastructure remains as is—grid extension is possible only or public scenario substantially, resulting in a higher share of SASs
for grid-electrified clusters and electrification of fully un-electrified and a lower share of MGs. The results depicted in column three of
clusters is entirely left to the off-grid electricity sector. Note that Fig. 2b,d show off-grid electrification shares of two-thirds, distrib-
both scenarios are extremes, with the reality likely lying somewhere uted almost equally among MGs and SASs (46–54%). Fourth, mov-
in between. ing from the niche to the mainstream scenario (compared with
We observe four high-level points for both electrification path- Table 1) results in electrification shares more similar to the uni-
ways across the different financing scenarios. First, the public sec- form scenario, albeit with higher SAS shares (plus 5 pp) and lower
tor scenario closely mirrors the uniform scenario concerning new MG shares (minus 5 pp). This result illustrates the large potential
connections and investment cost. This is because a uniform cost effect of mainstreaming off-grid electrification finance on selec-
of capital of 8% is close to the weighted average of the public cost tion of MG.
of finance for sub-Saharan African governments (compared with An analysis of the extended-area grid pathway, specifically
Fig. 1). Hence, using a uniform cost of capital produces reasonable (Fig. 2a), shows that in the niche-financing scenario, the share of
electrification mix estimates for sub-Saharan Africa overall if one MGs drops by 7 pp relative to the uniform scenario. MGs and SASs
assumes that the public sector finances all electrification. Second, have a smaller contribution to the total new connections, account-
the estimated total investment cost across scenarios (2018 US$) ing for 20% of the total new connections (compared with 24%
is approximately US$228 billion for the extended-area grid path- in the uniform scenario). Most connections switch from MGs to
way, which is equivalent to roughly US$19 billion per annum dur- grid extension in the extended-area grid pathway. This is mainly
ing 2018–2030, in line with past estimates from the International because high-density population clusters enable economies of scale
Extended-area grid
pathway
c d
Existing-area grid
pathway
Grid extension
MGs
SASs
Water bodies
Countries with no data
0 500 1,000 km
Fig. 3 | Map of sub-Saharan Africa comparing financing scenarios for the defined electrification pathways. a, Uniform scenario extended-area grid
pathway. b, Niche-financing scenario extended-area grid pathway. c, Uniform scenario existing-area pathway. d, Niche financing scenario existing-area
pathway.
for grid extension. We also observe that the investment cost for the reduced. Further, the share of SASs for these scenarios is not high
extended-area grid pathway (Fig. 2c) increases by 7% or US$16 bil- enough that it would increase total investment costs as can be seen
lion due to the increased need for grid infrastructure compared for the niche scenario.
with the uniform scenario. Increased grid infrastructure requires
high up-front investments, which increase the total investment cost. Geographical effects
The results from the existing-area pathway (Fig. 2b,d) show Figure 3 provides a granular view on the geographic location of new
the importance of accounting for representative cost of capital connections by electrification mode. The map shows the total new
values when analysing private sector financed off-grid electrifica- connections in 2030 for the uniform and niche-financing scenarios
tion modes even more clearly. MGs and SASs contribute to 67% and both grid-extension pathways. We observe the largest changes
of new connections in the existing-area pathway for the uniform in the share of MGs between scenarios in North Africa, West Africa
and public scenarios (Fig. 2b). In these scenarios, a larger portion and Madagascar for the extended-area grid pathway (Fig. 3a,b). In
of off-grid electricity connections would be directed towards MGs the existing-area grid pathway, large changes are observed in West
compared with SASs. In the niche scenario, MGs show a substantial Africa and Central and Southern Africa (Fig. 3c,d). The largest
decline contributing to 46% of the newly connected off-grid elec- declines in the share of MGs for the extended-area grid pathway
trification modes compared with the uniform scenario where they range between 24 pp and 42 pp for Sudan, Madagascar, Burkina Faso
account for 85%. Note that the observed grid investment costs in and Chad. For the existing-area grid pathway, MG share decreases
the existing-area grid pathway are the result of grid densification, are much larger, ranging between 44 pp and 58 pp in Mauritania,
that is, population densities in clusters already connected to the grid Eswatini, Senegal, Lesotho and Chad.
increase, which necessitates investment in the existing grid infra- Further, the assessment of the total investment needed to reach
structure to satisfy demand. 100% electrification reveals large country differences in the invest-
In the mainstream scenario, the total new MG connections ment per household between countries (Table 3). We focus on a
contribute to 77% of the total new off-grid connections in the single scenario (niche, status quo) because we see little variation
existing-area grid pathway (Fig. 2b). We also see in the existing-area in the total investment costs across the financing scenarios for the
pathway that maturity of the sector can help foster deployment of electrification pathways (compared with Fig. 2c,d).
MGs, which account for 51% of the total electrification mix in 2030 Table 3 shows that the required investment per household for
for the mainstream financing scenario. This is relatively similar most countries ranges between US$1,000 and US$1,850, with South
to the public sector financing scenario (55%). However, the total Sudan having the highest per household investment cost. Three
investment cost for the mainstream financing scenario is the lowest countries feature investment needs lower than US$1,000 per house-
across financing scenarios at only US$299 billion. This is mainly hold. To set these numbers in context, about 40% of the sub-Saharan
because the share of MGs is lower compared with the public and African population lived below the World Bank’s US$1.90 per day
uniform scenario. Therefore, the distribution grid-infrastructure extreme poverty line in 201838. These numbers also stress the large
costs (which increase the up-front investment cost for MGs) are variance between countries. Importantly, designing policies such as
31
48 46
54 51
43 73
80 36 38
78
50 70
10 45
29
3
42 42 42 41 41 41
25 25 25
17 17 17
0
Uniform Niche Mainstream Uniform Niche Mainstream Uniform Niche Mainstream Uniform Niche Mainstream
e f g h
1.50 1.50 1.50 1.50
0 0 0 0
Uniform Niche Mainstream Uniform Niche Mainstream Uniform Niche Mainstream Uniform Niche Mainstream
Fig. 4 | a–h, Proportion of new connections for clusters to be electrified in 2030 in DRC (a), Ethiopia (b), Nigeria (c) and Zimbabwe (d), and the distribution
of LCOE for clusters to be electrified in 2030 in DRC (e), Ethiopia (f), Nigeria (g) and Zimbabwe (h). For this analysis, 5% of the outliers are neglected. The
colours on both types of plot correspond to the electrification mode. The numbers on the stacked bar plots (a–d) represent the percentage of total new
connections in 2030 by electrification mode.
costly technology adjustments27. International organizations can This variance could be investigated in future research, particularly
consider incentivizing the adoption of a harmonized international with the notion of trade-offs in 100% electrification targets in mind
standard such as the World Bank’s Lighting Global Quality Standard as the opportunity cost of ‘going the last mile’ may be large given
(in the case of SASs)45. competing investment needs in other sectors such as agriculture,
Regarding the limitations of our analysis, first, it is worth not- education or healthcare47.
ing that our approach does not capture the variance of risks within
countries, which can be high in sub-Saharan Africa18,46. Future Methods
research should uncover within-country variance to provide even This study intends to determine the influence of the cost of capital on least-cost
more granular electrification policy advice. Second, the model tar- geospatial electrification-model outcomes. We defined four financing scenarios
gets 100% tier 3 electrification irrespective of demand or ability to and estimated country- and mode-specific cost of capital values for each scenario.
pay. In reality, however, most private sector investors will simply not We then applied the estimated cost of capital values to OnSSET, an open source
integrated electrification model7 (Supplementary information).
invest in assets electrifying the lowest-income customer segments
without government incentive. Hence, the aggregate numbers may Estimation of cost of capital. Countries and electrification modes differ in the
be overly optimistic concerning the ability to attract capital. We note extent to which they can tap into debt finance (which is cheaper than equity
however, that to reach universal electrification by 2030, additional because equity bears the first losses48), the cost of the debt (interest rates) and the
cost of equity (or expected return on equity) for the remainder of the investment.
subsidies for low-income households would likely be required.
Therefore the amount of debt that investors can access as part of their financing,
Given the likely correlation of institutional quality and household the cost of debt and the cost of equity need to be quantified to determine the cost
income, SASs may be even more suited to electrify low-income of capital. The basic expression of this overall cost of capital is the WACC19. For
regions because this electrification mode is less reliant on gover- this analysis, we follow a standard notation (equation (1)) and estimate the cost of
nance structures20. Future research should include demand analyses equity, the cost of debt and the debt share separately49.
and the effect of targeted demand subsidies in optimal electrifica- (
E
) (
D
)
tion planning. Moreover, companies may adapt their business mod- WACC = × Ke,i + × Kd,i (1)
V V
els to different demand environments and size systems accordingly.
These business model choices (for example, sale, lease-to-own, Ke,i and Kd,i are the cost of equity and the cost of debt, respectively, for investments
pay-as-you-go) may have an influence on the ability of a company in a specific country i. E, D and V denote total equity, debt and capital; the debt
share equals DV . For simplification, this ‘vanilla WACC’ does not account for the
to raise capital and on its cost of capital. In addition, the sizing country-specific tax rate due to the uncertainty about which entities would be liable
of the system, in turn (for example, choice of electrification tier) to pay tax, especially for grid extension. We demonstrate in a sensitivity analysis
influences the electrification mode choice with lower tiers favour- for a representative set of clusters that the effect of including tax on the LCOE is
ing SASs and higher tiers favouring MGs or grid extension. Future comparably small (Supplementary Fig. 1).
research could look into these questions in comparative company A higher debt share indicates lower investment risk because it translates in less
equity being able to cover first losses49. We use this relationship and implement
case studies. Third, and related to this, our results have also shown electrification mode-specific risk premiums by applying mode-specific debt shares
vast differences in per household investment costs across coun- for MGs and SASs. For SASs, we use debt shares from the ten largest off-grid
tries (Table 3) and vast LCOE differences within countries (Fig. 4). electrification companies in developing countries by disclosed financing between
For the cost of debt calculation, rf is based on the five-year US treasury bond lm is the investment cost for an electrification mode in year m, O&Mm are
yield in 201951 and the CRpi represents each country’s default spread52. The data the operation and maintenance costs, Fm are fuel costs, Sm is the salvage value
were averaged over a period of five years (2015–2019), which is the longest period (the value of the energy system at the end of its useful life), Em is the electricity
for which data are available for most of the countries. Further, this period also generated, r the discount rate and n is the lifetime of the electrification mode in
excludes effects from the financial crisis. The Dp value is set to 1.2% based on a years. For grid extension, the LCOE equals the sum of the average national grid
literature estimate50. LCOE (based on an estimated country generation capacity mix for 2030) and the
The cost of equity reflects an investor’s expected returns for investing in a added LCOE of transmission and distribution infrastructure. The LCOE for MGs
company. It was calculated using equation (3): and SASs account for the generation capacity costs, distribution infrastructure
costs (in the case of MGs), O&M costs and the fuel costs of the energy systems.
Ke,i = rf + ERpi + Ip + SCp (3) OnSSET has been used for analysis by the World Bank11 and the International
Energy Agency1. While there are possible geospatial electrification modelling
where ERpi is the equity risk premium, which varies by country (i) and accounts alternatives to OnSSET—Reference Electrification Model (REM)9, IMAGE-TIMER
for the return that investors require as compensation for the risk they are taking on model61, or the Network planner62—OnSSET is chosen because the code is open
an investment in a publicly listed company in this particular country. In addition, source, it uses publicly available data and it provides renewable energy technology
companies in the off-grid electricity sector are still nascent. Investors, therefore, options, which are representative of the current off-grid electrification landscape in
cannot easily liquidate their assets53. To reflect this, we add an illiquidity premium sub-Saharan Africa.
(Ip) to the equity risk premium. Finally, off-grid electricity companies are also still We modified the source code to implement country- and electrification
relatively small and so often have higher risk and higher returns compared with mode-specific costs-of-capital values (referred to in the model as the discount
companies with large market capitalization54. This is because investors in small rate). For this analysis, a cluster in the model refers to an area of land occupied by
companies encounter higher search and monitoring costs, less transparency and a households, while the cluster density refers to the population within a particular
poorer track record55. We reflect this with a small cap premium (SCp). cluster divided by the area of the cluster. The cluster density is one criterion
We average data on equity risk premium52 over five years, too (2015–2019). The used in the selection of countries for the deep dive analysis (Supplementary
illiquidity premium (3.6%) was determined by calculating the average markup on Table 1). The extended-area grid pathway was implemented by running the
the cost of equity due to illiquidity across three different studies56–58, and the small model as is implemented on the Global Electrification Platform11. For the
market-cap premium is set to 3.8% based on a literature estimate55. existing-area pathway, we adjusted a model parameter to prevent extension of
We are aware of the fact that our approach of assuming additive risk premia the existing-area network. For this analysis, OnSSET calculates the LCOE for
and drawing on literature estimates partly from regions outside of sub-Saharan different electrification modes in two target years—2025 (50% of the population
Africa is only a first approximation of country- and mode-specific cost of capital. electrified) and 2030 (100% of the population electrified). We omit fossil
Given the scarcity of financial data, however, we consider the approach appropriate fuel-powered options from this analysis for three reasons: firstly, a review of
for the purpose of our study as it reasonably well approximates the differences literature34,41,63,64 and discussions with off-grid electricity sector experts showed
between countries, modes and financing scenarios. that current business models for most off-grid companies deploy renewable
As a further reality test and validation, we triangulated the resulting cost of energy technology due to the remoteness of the rural regions and the associated
capital values using estimates from the literature for developing countries, where high cost of transporting fuel to meet energy requirements. SASs (used to power
available (Kenya23, Malawi59 and Cambodia60), and through interviews with experts households) are now exclusively powered by solar PV plus batteries. Secondly,
working in electrification finance, which confirmed that our results are reasonable analyses comparing renewables to fossil fuel-powered options have already been
approximations (Supplementary Table 5). extensively studied in literature6,7,23,65,66. Thirdly, our analysis aims to explore the
viability of low-carbon technology options in the move towards meeting the
Definition of financing scenarios. We defined three financing scenarios (in SDGs. While all energy options would make it possible to meet SDG 7 (energy),
addition to the uniform scenario) with the intention of depicting possible financing the inclusion of fossil fuel-powered options would mean that SDG 13 (climate
options to reach 100% electrification in sub-Saharan Africa. Table 1 in the main action) may not be reached. This is because the model outcomes would largely
text illustrates the breakdown for each component and each financing scenario support deployment of diesel-powered systems over renewables because of the
(Supplementary Table 4 provides an illustration of calculations for all scenarios). higher capital cost of renewables. The assumptions for the different electrification
For the public sector financing scenario, the public sector is the investor in all options are illustrated in Table 2.
electrification modes. We assume that all investment is financed by increasing The end-year target demand per household is based on the World Bank’s
sovereign debt and define the corresponding cost of capital as the sum of a risk-free multi-tier framework67. The multi-tier framework provides a standardized measure
rate rf and the country-specific additional risk. for household electricity demand using a spectrum of tiers ranging from 1 to 5.
For the niche-financing scenario, the investor in grid extension is the public sector Each tier represents a set of energy services based on defined energy attributes
and so the public cost of capital (above) is applied. Off-grid electrification is financed resulting in a total amount of energy measured in kWh per household67. The target
by the private sector. In this case, the cost of debt is equal to equation (2) and the demand tier is set to tier 3 for both urban and rural areas across all countries.
cost of equity is equal to equation (3). The average debt share of the ten largest SAS This is because detailed electricity-demand forecasts at the household level are
companies is 50% (Supplementary Table 2), while the debt share for MG is 0%. unavailable for all countries in sub-Saharan Africa. Tier 3 level energy services
For the mainstream financing scenario, grid extension is still financed by the offer a minimum of approximately 365 kWh annually per household67,68. While
public sector and remains unchanged. Off-grid electrification is financed by the in practice, newly connected households tend to consume tier 1 and 2 level
private sector, however, it is now assumed to be mature. We therefore amend services69,70—these tiers do not typically support productive loads such as water
the cost of equity for MGs and SASs by removing the illiquidity premium and pumps and refrigerators68,71—our analysis intends to allow for this possibility.
the small market-cap premium from equation (3). Further, as financial markets Further, regions electrified through grid extension experience variations in energy
mature, debt shares tend to increase. We reflect this by assuming that all MG and services, for example, grid reliability37, and so are not bound by demand tiers.
SAS investments can attract the debt levels that current market leaders are able to Nevertheless, despite this assumption, we would expect to see the same effect of the
attract. In this case, we use the debt shares of the market leaders among the ten cost of capital across the different tiers; the main factor that would influence the
largest off-grid companies34 (75% for SASs) and 40% for MGs based on interviews outcome would be the population-cluster density. Increasing the tier would favour
with experts in the off-grid electricity sector. grid extension or MGs given more clusters will have higher energy requirements.