You are on page 1of 12

Energy Economics 91 (2020) 104890

Contents lists available at ScienceDirect

Energy Economics

journal homepage: www.elsevier.com/locate/eneeco

Economic viability and regulation effects of infrastructure investments


for inter-regional electricity transmission and trade in China
Jin-Hua Xu a, Bo-Wen Yi b,⁎, Ying Fan b
a
Center for Energy and Environmental Policy Research, Institutes of Science and Development, Chinese Academy of Sciences, Beijing 100190, China
b
School of Economics & Management, Beihang University, Beijing 100191, China

a r t i c l e i n f o a b s t r a c t

Article history: The transition of energy structure to renewable energy is a social and systematic engineering that requires com-
Received 2 August 2019 plex regional power interconnection as a support. Thus, an assessment of the economic viability of infrastructure
Received in revised form 7 May 2020 investments for supporting such transmission expansion is crucial. This study presents a multi-regional power
Accepted 28 July 2020
system optimization model to evaluate the potential economic benefits of infrastructure investments for the na-
Available online 07 August 2020
tional inter-regional electricity network in China under various scenarios in the context of low-carbon transfor-
Keywords:
mation. Key factors influencing economic benefits are analyzed specifically and regulation barriers associated
Economic benefits with inter-regional electricity trade are given particular attention. The results show that approximately 140
Regulation barriers Giga Watt (GW) of infrastructure construction for the inter-regional electricity trade network is economically vi-
Electricity trade able during the planning horizon. These new interconnections would lead to 250–440 billion RMB of economic
Optimization model benefits. Regional electricity trade barriers caused by imperfect market mechanisms have a negative impact on
the economic benefits of transmission infrastructure investments, although they promote scale and utilization ef-
ficiency in the power sector of electricity-importing regions. Improving the national grid coordination mecha-
nism to break the grid isolation between the State Grid Corporation of China and the China Southern Power
Grid is crucial, because a large number of transmission lines connecting these two national-level power grids
are economically viable.
© 2020 Elsevier B.V. All rights reserved.

1. Introduction length of the UHV line, both complete and under construction, totals
32,000 km (CSG, 2017; SGCC, 2017). However, the construction of the
Renewable energy is a key area in achieving low-carbon transforma- inter-regional electricity network is still below expectation due to the
tion. However, China's energy resources and electricity load show re- uncertainty of economic viability and obvious institutional barriers be-
verse distribution, along with a regional imbalance between electricity tween different provinces, although much literatures revealed positive
supply and demand, which has led to serious curtailment issues (Yi results in both economic and environmental aspects (Chen et al.,
et al., 2019). The interconnection of the regional electricity market is 2014; Guo et al., 2016, 2017; Li et al., 2016). As demonstrated by the
considered a secure, sustainable, and cost-effective way to resolve European electricity system, despite clear benefits, interconnection pro-
these issues (Ahmed et al., 2017). Electricity is a relatively peculiar com- jects are difficult to achieve in practice (Dutton and Lockwood, 2017).
modity, as its trade entirely relies on transmission lines. Inter-regional One reason for this difficulty is that the economic benefits of inter-
electricity transmission can facilitate electricity trade and help effi- connection depend on changing network architectures and technology
ciently integrate energy sources. Thus, the rapid expansion of the mixes (Rosellon, 2003). The decision of whether to invest in inter-
inter-regional electricity network is crucial to China's energy landscape regional electricity transmission, and to what extent, needs to be con-
over the next two decades. sidered in the context of the national power transmission network.
Currently, Chinese government is giving a high priority to inter- From a systematic perspective, a transmission line investment may be
regional electricity transmission by ultra-high voltage (UHV) technol- uneconomical, even if a single line investment assessment shows it to
ogy in order to promote renewable energy development (Wang et al., be economically feasible. Meanwhile, the future spatial distribution of
2014). Until 2017, 16 UHV lines had been built by the State Grid Corpo- low-carbon technologies and the fluctuating feature of renewable en-
ration of China (SGCC) and the China Southern Power Grid (CSG); the ergy complicate the assessment of economic benefits.
Regulation barriers also affect the economic benefits of interconnec-
⁎ Corresponding author. tion, including local government protection, inter-provincial barrier and
E-mail address: ybw2018@buaa.edu.cn (B.-W. Yi). isolation of power grid between the SGCC and the CSG. There is no fully

https://doi.org/10.1016/j.eneco.2020.104890
0140-9883/© 2020 Elsevier B.V. All rights reserved.
2 J.-H. Xu et al. / Energy Economics 91 (2020) 104890

competitive national electricity market in China. Inter-provincial elec- long-term investment decision framework based on China's re-
tricity trade is primarily dominated by local governments who have source endowment and power grid structure. It allows for examining
the authority to determine the trading price and volume. Many prov- the impacts of various investment options for electricity generation
inces have instituted restrictions on external electricity to protect the and transmission, as well as the effects of various electricity dispatch
local power generation companies. In addition, the isolation of power decisions and network topologies. Second, the economic viability of
grid between the CSG and the SGCC hampers economically viable infra- infrastructure investments for inter-regional electricity transmis-
structure investments. These two national power grid companies man- sion network is specifically evaluated from a systematic perspective.
age regional power grid construction and are more concerned with the Two types of regulation effects are added into the model to reflect
planning of their own jurisdictions.1 The lack of a national coordination the impact of non-economic factors on interconnections. Finally,
mechanism for the power grid means almost no electricity trade hap- several cases are analyzed to evaluate the investment risks and ex-
pens between CSG and SGCC, which seriously affects the rationality of amine the sensitivity of the model to various assumptions. This
inter-regional electricity transmission patterns. study answers two questions: (1) what is the economically viable
Generally speaking, grid investment is highly capital-intensive, usually scale of investment in China's inter-regional transmission network
costing several billion USD, and once built, it creates a “lock-in” effect on and how will it change with the evolution of network structure?
the power grid topology for decades, as highlighted by Huppmann and And (2) what is the impact of regulation barriers due to imperfect
Egerer (2015), and Chao and Wilson (2020). With the deepening of market mechanism on the economic viability of transmission line in-
China's electricity market reform, value-based transmission expansion vestments and inter-regional electricity exchange patterns? Based
mechanism will be gradually formed. Thus, an assessment of the potential on the answers, policy recommendations are provided for govern-
economic benefits of the national electricity interconnection under mar- ment to optimize China's mid-term and long-term inter-regional
ket competition is crucial prior to making investment decisions. Such an power grid development.
assessment can also help us understand the economic feasibility of This paper is organized as follows. Section 2 provides a description of
China's low-carbon transformation and recognize the coordination be- the detailed modeling. Datasets and scenario designs are presented in
tween electricity network expansion and national low-carbon transfor- Section 3. Section 4 shows the economic benefits of infrastructure in-
mation strategy (Su and Ang, 2017). vestments for the inter-regional power network, and discusses the re-
Many studies have concentrated on the economic benefits of invest- lated regulation effects. Section 5 summarizes the findings and offers
ment in electric power industry at both the generation side (Li et al., recommendations.
2015; Pan et al., 2019) and the demand side (Hu et al., 2011; Yuan
et al., 2014), while few studies have focused on the transmission side. 2. Methodology
Timilsina and Toman (2016) quantified the benefits of cross-border
electricity trade in South Asia through an optimization model. Li et al. 2.1. Economic viability and regulation effects
(2016) investigated the impact of inter-regional electricity grid on the
energy transformation in China. Li and Chang (2015) established a sys- A stylized two-node electricity trade system is presented first as a ref-
temic approach in evaluating the electricity infrastructure investment in erence for our empirical analysis (see Fig. 1). Two regions (A and B) are
Association of Southeast Asian Nations (ASEAN) and found that there is characterized by long run marginal cost curves (MCA and MCB) and de-
still room for improvement in the current Greater Mekong Sub-region mands (DA and DB). To simplify, we assume that the long run marginal
program. cost of each region is monotonically increasing, but the cost in region B
For methodology, vast literatures used the power generation expan- is clearly higher than that in region A. The price elasticity of demand is as-
sion planning (GEP) model to analyze the power generation and trans- sumed to be zero, and the electricity transmission cost is assumed to be z
mission investment planning (Gujba et al., 2010; Yuan et al., 2014; $/MW. The horizontal axis represents electricity supply or demand in
Chang and Li, 2015; Cheng et al., 2015b; Hanson et al., 2016). However, MW, while the vertical axis represents marginal cost in $/MW.
they are difficult to incorporate the intermittent and seasonal features If the difference between MCA and MCB is greater than z, this means
of renewable energy, which are typically addressed by hourly-based that the additional transmission capacity is economically viable. In this
unit commitment (UC) models (Delarue et al., 2009; Weigt et al., situation, region A will produce more electricity and transfer it to region
2013; Davidson et al., 2016; Holladay and LaRiviere, 2017). These fea- B at a lower marginal cost. The optimal transmission capacity is u MW,
tures of renewable energy will require thermal power units to adapt, which is determined at the point where the difference in marginal
leading to additional costs related to power dispatch, which will further cost between region A and B is equal to the transmission cost. The equi-
impact the economic benefits of electricity exchange (Weijde and librium electricity supply volumes are DA + u in region A and DB−u in
Hobbs, 2012). Few studies, generally focusing on the European power region B, respectively. Electricity trade generates net cost savings,
system, have integrated short-term power dispatch decisions into a which are the economic benefits of transmission investment, and are
long-term GEP framework to evaluate the economic benefits of regional depicted as the two gray shaded areas in the left part of Fig. 1.
power interconnections (Koltsaklis and Georgiadis, 2015; Abrell and The regulation effects mentioned in Section 1 are mainly reflected in
Rausch, 2016; Scholz et al., 2017; Allard et al., 2020). the constraints on transmission capacity between regions. If the limited
The existing literatures show important findings regarding the en- capacity u* is less than the optimal capacity u, the electricity transfer
ergy and environmental impacts of electricity interconnections in volumes and the economic benefits brought by this transfer will change.
China; however, an obvious study gap exists in quantitatively estimat- The new equilibrium electricity supply volumes are DA + u* in region A
ing the potential economic benefits of inter-regional electricity inter- and DB−u* in region B, respectively. The economic benefit losses (BL)
connection under value-based transmission expansion mechanism. are depicted as the two orange shaded areas in the right part of Fig. 1,
Moreover, the impact of the regulation barriers related to inter- which are calculated by Eq. (1).
regional electricity trade on the economy of transmission investment Z Z
DB −u DA þu
is often overlooked. BL ¼ MC B − MC A −z  ðu−uÞ ð1Þ
This study first presents a Chinese multi-regional power system op- DB −u DA þu
timization model to simulate the expansion of both power generation
and transmission. It integrates short-term power dispatch into the The purpose of this simple example is to illustrate the economic viabil-
ity and regulation effects of inter-regional electricity transmission invest-
1
CSG includes the Northeast power grid, North power grid, Northwest power grid, East ment. However, there are multiple nodes in reality, which makes the
power grid, and Central power grid, while SGCC includes the Southern power grid. above assessment more complicated. Inter-regional transmission network
J.-H. Xu et al. / Energy Economics 91 (2020) 104890 3

Fig. 1. Economic benefits and optimal capacity of electricity trade.

structure will change regional marginal cost, and further affect the eco- of power transmission lines, and the hourly start-up and shut-down ca-
nomic viability and corresponding benefits of electricity transmission pacities of fossil-based technologies. The main outputs consist of the
investment. Therefore, it is necessary to comprehensively evaluate the macro evolution pathway and micro utilization efficiency of both
economic benefits and regulation effects of inter-regional electricity trans- power generation and transmission technologies. In addition, indirect
mission from a holistic viewpoint. economic factors, such as environmental benefits and economy-wide
impacts, are not considered in the cost function.
2.2. Model description  
min C X G ; X Tr ; P; PT; SU; SD ð2Þ
From Section 2.1, we find that the differences between regional long
run marginal cost and corresponding transmission cost are the most More explanations for parameters and variables, and detailed math-
important factors in examining the economic viability of transmission ematical equations, including objective function and constraints, are
investments. However, the accounting of these costs is not simply due presented in Appendix A.
to the natural characteristics of electricity generation and transmission.
The short-term features of electricity must be considered, such as real- 2.3. Model characteristics
time matching, ramping, and renewable energy fluctuations, although
this study focuses more on the long-term investments. In addition, the Future inter-regional electricity flow patterns depend on many fac-
structure of inter-regional power network also affects the tradeoff be- tors, including regional resource endowments, power demand changes,
tween each kind of cost. renewable energy development, and the evolution of power generation
Therefore, this study uses a multi-regional power system technologies. These dynamic changes in electricity flows significantly
optimization model to examine the Chinese power sector, integrating affect the economic benefits of infrastructure investments for electricity
short-term power dispatch into the long-term investment decision networks. Our model reflects such factors.
framework. An illustrative structure of this model is presented in
Fig. 2. At the macro level, it simulates the yearly investment decisions 2.3.1. Cross-regional heterogeneity
for both power generation and transmission technologies. At the One of the main advantages of our model is its ability to describe
micro level, it simulates the hourly power dispatch, including ramping cross-regional heterogeneity. Unlike the stylized two-node model pre-
limits and start-up decisions, to reflect the intermittent and seasonal sented in Section 2.1, our model divides China into 10 regions as pre-
characteristics of renewable energy. sented in Table 1, and each region is assumed to be a node. Considering
This model is a large-scale linear programming solved by the CPLEX the power transmission between nodes, the power supply and demand
algorithm based on GAMS software. The objective function of this opti- of each node match in real time on the hourly dimension, as shown in
mization problem is to minimize the total system costs during the plan- Eq. (A.17). Kirchhoff's current law is respected, while the voltage law is
ning horizon, as shown in Eq. (2). The decision variables include the not included.
yearly new built capacity, and hourly power output of power generation To clearly define which transmission lines are included in the scope
technologies, the yearly new built capacity, and hourly power transfer of this study, we must first explain the regional divisions. China's power

Fig. 2. An illustrative structure of the model.


4 J.-H. Xu et al. / Energy Economics 91 (2020) 104890

Table 1
Regional division in this study.

Regional symbol Provinces, municipalities and autonomous regions included Regional power grids Jurisdiction

Northeast Liaoning, Jilin, Heilongjiang, East Inner Mongolia Northeast power grid SGCC
North Beijing, Tianjin, Hebei, Shandong North power grid SGCC
Jinmengxi Shanxi, West Inner Mongolia North power grid SGCC
Northwest Gansu, Qinghai, Ningxia, Shaanxi Northwest power grid SGCC
Xinjiang Xinjiang Northwest power grid SGCC
East Zhejiang, Shanghai, Jiangsu, Fujian, Anhui East power grid SGCC
Center Hubei, Hunan, Jiangxi, Chongqing, Henan Central power grid SGCC
Sichuan Sichuan Central power grid SGCC
South Guangxi, Yunnan, Guizhou Southern power grid CSG
Guangdong Guangdong Southern power grid CSG

grid consists of six parts, the North, Northeast, Northwest, East, Central, detailed mathematical equations about the dynamic change of
and Southern power grids. The first five regional power grids are technology capacity are presented in Appendix A.
governed by SGCC, while the last is controlled by CSG. The resource en-
dowments in various provinces within one grid vary widely. Thus, this
study further divides the six power grids into 10 regions according to re- 3. Data and scenarios
source endowment and geographical position (see Table 1).
Electricity transfer needs to be based on transmission lines, includ- 3.1. Data inputs
ing historical lines as well as new lines decided by this model. Inter-
regional network connection is assumed to adopt ultra-high voltage The volume of data needed for this kind of model is substantial.
direct current (UHVDC) technology (Yi et al., 2016). The ultra-high volt- The key datasets include power demand profiles, generation mix of
age alternating current (UHVAC) is excluded because its advantages in technologies, economic parameters for both power generation and
building a larger synchronous power grid are beyond the scope of our transmission technologies, and meteorological data for renewable
model. The investment of UHVDC consists of fixed costs and variable energy. The description of these data categories and their sources
costs, as shown in Eq. (A.7). Heterogeneity and transmission congestion are presented in the Supplementary material (Cheng et al., 2015a,
within one node are also beyond the scope of this study. 2015b; CEPYEB, 2015; IEA, 2018; Kalnay et al., 1996; Koltsaklis
and Georgiadis, 2015; Lai and Hong, 2007; Li et al., 2016; Lv et al.,
2013; Shu et al., 2005; Tang and Dong, 2012; Wei et al., 2010; Yi
2.3.2. Time step and time coverage et al., 2016, 2017; Zhu and Genton, 2012).
Another advantage of our model relates to time step and time Based on the regional division, we collect information on all existing
coverage. 2 Temporal resolution is a key characteristic. Bottom-up inter-regional power transmission lines through 2017 (see Fig. 3). The
models have a relatively high temporal resolution, generally focus- total transmission capacity is 179 GW. The UHV line is the main carrier
ing on hourly equilibrium.3 However, due to computational limita- of inter-regional power due to its low loss rate and long-distance poten-
tions, large-scale electricity system models adopt the typical day tial (Hui et al., 2017). Jinmengxi is the most important electricity-
method to reduce temporal resolution and coverage (Lienert and exporting region, followed by the Northwest, South, and Sichuan. The
Lochner, 2012; Koltsaklis and Georgiadis, 2015; Merrick, 2016). North, East, and Guangdong are the primary electricity-importing re-
Our model considers six typical days of 24 one-hour periods. Thus, gions. The Jinmengxi-North, Sichuan-East, and South-Guangdong trans-
a one-year period consists of 144 temporal steps. The planning hori- mission patterns play a significant role in the transfer of electricity.
zon is 2015–2030.
The connection between the macro temporal level and micro tem-
poral level is reflected in capacity constraints. The power generation ex-
pansion module determines the available capacity for technologies at
the beginning of each year. The power dispatch and transmission for
each temporal step during 1 year are limited by this available capacity.
Specifically, the capacity constraint for power dispatch is shown in
Eq. (A.16). For renewable energy technologies, the available capacity
depends not only on the installed capacity in this year, but also on the
hourly capacity factor. For fossil fuel technologies, the capacity factor
does not need to be considered. The capacity constraint for power trans-
mission at each hour is shown in Eq. (A.18).

2.3.3. Multiple technologies


Multiple power generation technologies are considered in our
model. Conventional technologies include gas-fired power, ultra-
supercritical coal-fired power (USC), combined heat and power
(CHP), and other coal-fired power. Clean technologies include nu-
clear power, hydropower, onshore wind, offshore wind, biomass,
solar photovoltaic (PV), and concentrating solar power (CSP). The

2
Time coverage is the number of time steps covered in each model run (Pfluger, 2014).
3
Bottom-up models are characterized by detailed technology representation. Technol-
ogy adoption is considered a rational decision-making process (Fleiter, 2011). Our model Fig. 3. Existing inter-regional power transmission network until 2017. Sources: Yi et al.
belongs to this category. (2016); CSG (2017); SGCC (2017).
J.-H. Xu et al. / Energy Economics 91 (2020) 104890 5

3.2. Scenario design Table 3


Total system costs during the planning horizon in different scenarios.

Four scenarios, namely REF, BAU, ETB, and FRC, are constructed to Scenario Total system Total costs in the Net cost Percentage
assess the regulation effects of infrastructure investments for inter- costs (Billion REF scenario savings of savings
regional electricity network (see Table 2). Two types of regulation RMB) (Billion RMB) (Billion (%)
RMB)
effects are considered in this study. The first is the inter-regional elec-
tricity trade barrier caused by the imperfect electricity market mecha- BAU 29,790.5 30,146.1 355.6 1.18
ETB 29,820.0 30,146.1 326.1 1.08
nism in China. The second is the lack of a national coordination
FRC 29,514.0 30,146.1 632.1 2.10
mechanism for the power grid, leading to grid isolation between CSG
and SGCC.
The REF (Reference) scenario is intended as a benchmark, in which
no new transmission line is developed during the planning horizon. 4. Results and discussion
The capacity of the inter-regional transmission network in this scenario
has been shown in Fig. 3. 4.1. Economic efficiency
In the BAU (Business As Usual) scenario, the future transmission net-
work is determined endogenously by the model, but we assume the 4.1.1. Total system cost savings
separation of the power grid between CSG and SGCC exists; therefore, Table 3 presents the total system costs for each scenario over the
no new transmission line is developed to connect CSG and SGCC during planning horizon. The comparisons between each scenario reveal
the planning horizon. Regional electricity trade barriers are not consid- three key findings. First, infrastructure development of inter-regional
ered in this scenario. Inter-regional electricity flow is unrestricted as power transmission produces economic benefits, as the net savings to
long as there is sufficient transmission capacity. total system costs are positive. Such development would produce
Based on the BAU scenario, we further consider regional electricity 355.6, 326.1, and 632.1 billion RMB in net savings in the BAU, ETB, and
trade barriers in the ETB (Electricity Trade Barriers) scenario, aiming FRC scenarios, respectively, or approximately 1.18%, 1.08%, and 2.10%
to identify their impact on the economic benefits of electricity intercon- of total electricity supply costs.4 Second, net savings in the ETB scenario
nections. In this study, trade barriers are modeled as the maximum per- are 8.3% lower than in the BAU scenario, indicating regional electricity
centage of regional annual power demand that can be met by electricity trade barriers do limit the economic benefits of transmission infrastruc-
trade with other regions (λpip) referring to Li and Chang (2015), as ture investment. Third, net savings in the BAU scenario are much lower
shown in Eq. (3). More explanations for parameters and variables are than the FRC scenario, which shows there is room for improvement to
presented in Appendix A. Based on the net imported electricity of the the current interconnections.
North region (including Beijing, Tianjin, Hebei, and Shandong) in
2015, the maximum percentage is assumed to be 20%. This region has 4.1.2. Cost decomposition
a large number of lines that connect with other regions, which reflects The cumulative changes in various types of costs, resulting from
the actual proportion of inter-regional electricity trade (CEPYEB, 2016). inter-regional electricity cooperation and trade, relative to the REF sce-
nario, are depicted in Fig. 4. The total cost savings are primarily due to
X  TI  X
P i;t;h −P TO
i;t;h ≤ Di;t;h  λpip ð3Þ savings in investment, O&M, and fuel costs of power generation,
h h which fall by 192.0, 247.5, and 153.2 billion RMB, respectively, in the
BAU scenario. At the same time, there is a net increase in investment
The FRC (Full Regional Connections) scenario considers full regional and O&M costs for the expansion of power transmission, but the abso-
connections with unrestricted electricity flow. New transmission lines lute amount is less than the total savings. Regional electricity trade in-
are developed to link CSG and SGCC during the planning horizon. A creases electricity generation in resource-rich areas such as the
comparison between the FRC and BAU scenarios demonstrates how Northwest and Jinmengxi, resulting in savings. On the one hand, the ca-
the lack of national coordination mechanisms for the power grid affects pacity factor of renewable energy in these regions is higher, which re-
future electricity trade patterns. duces the investment cost to achieve the same renewable energy
In addition to economic considerations, inter-regional electricity target. On the other hand, lower coal prices in resource-rich areas result
trade should promote the consumption of renewable energy. A high in lower fuel costs for the entire power system.
proportion of renewable energy will be integrated into the power sector The investment costs for power transmission in the ETB and BAU
over the next decade, which will necessitate significant transmission in- scenarios are 104.6 and 84.5 billion RMB lower than the FRC scenario,
frastructure expansions and upgrades. In order to simulate these new indicating that incomplete regional interconnections and electricity
flow patterns, two policy targets are assumed in our model under all trade barriers hinder investment in the inter-regional electricity net-
scenarios. The first, which incorporates the U.S.-China Joint Announce- work. For this reason, the savings in investment and fuel costs of
ment on Climate Change, assumes that the share of non-fossil energy power generation produced by inter-regional electricity trade decrease
in total primary energy will exceed 20% in 2030 (Duan et al., 2018), as significantly in the ETB and BAU scenarios.
shown in Eq. (A.20). The second sets the share of non-hydro renewable
energy in power generation above 17% in 2030, relying on the numbers 4.2. Inter-regional electricity trade pattern
used by Yi et al. (2017), as shown in Eq. (A.19).
4.2.1. Inter-regional transmission capacity
Table 2 Fig. 5 shows the inter-regional power transmission infrastructure ca-
Scenarios for inter-regional electricity system. pacity through 2030 under different scenarios. It reveals that 141.1 GW
Scenario Transmission network Connection between CSG Electricity trade of interconnection is economically viable during the planning horizon
expansion and SGCC barriers under the BAU scenario. This transmission network primarily consists of
REF N N N
the lines connecting Jinmengxi-East, Jinmengxi-Center, Northwest-
BAU Y N N Center, Sichuan-East, Sichuan-Center, Xinjiang-Center, and Northeast-
ETB Y N Y North. The comparison, shown in Fig. 5, reveals three differences between
FRC Y Y N
4
Notes: “Y” represents yes, while “N” represents no. All costs in this study are 2014 constant price.
6 J.-H. Xu et al. / Energy Economics 91 (2020) 104890

Fig. 4. Changes in cumulative costs compared with the REF scenario.

the historical network and the future pattern of infrastructure construc- GW during the planning horizon, which is 20.3 GW less than the BAU sce-
tion. First, there will be few new transmission lines connecting to the nario. This reduction is primarily due to the lines connecting Jinmengxi-
North or Guangdong regions. Second, the interconnections from the Center, Northwest-East, Northwest-Center, and Xinjiang-Center.
Northwest and Jinmengxi regions to other regions will increase signifi- The economically viable transmission capacity under the FRC sce-
cantly. Third, a large number of transmission lines will be connected to nario is 166.7 GW during the planning horizon, which is 25.6 GW
the Center region. more than the BAU scenario. The connection between CSG and SGCC
Electricity trade barriers limit the economic benefits of electricity in- suggests a large number of transmission lines will be built from the
terconnection, leading to a reduction in total inter-regional transmission Northwest, Jinmengxi, and Sichuan regions to Guangdong rather than
capacity. The economically viable capacity in the ETB scenario is 120.8 the East and Center regions. This is because the marginal generation

Fig. 5. Inter-regional connection capacity by 2030 (GW).


J.-H. Xu et al. / Energy Economics 91 (2020) 104890 7

Fig. 6. Inter-regional electricity flows in 2030 (TWh). Notes: Red numbers represent the electricity transfer amount of individual transmission line and blue numbers represent the regional
net electricity transfer amount.

cost in Guangdong is higher than other regions. At the same time, no Northwest, Jinmengxi, and Xinjiang. The transfer of hydropower by the
new transmission line will be built within CSG due to the interconnec- Sichuan and South regions is not affected. Restricted electricity flows
tion between SGCC and Guangdong. also lead to a lower utilization rate of existing transmission lines. For ex-
ample, electricity exports from the Northwest and Xinjiang come from
4.2.2. Inter-regional electricity flow both renewable energy and thermal power, which makes the annual uti-
Fig. 6 shows the inter-regional electricity flows in 2030 under different lization rate of lines connecting Xinjiang-Center and Northwest-Center
scenarios. There is a significant increase in net electricity flows under the relatively high, reaching more than 60% in the BAU scenario, while it
BAU scenario, reaching 1282 TWh in 2030, 1.73 times as much as under falls to approximately 50% in the ETB scenario.
the REF scenario. The significant difference in various regional net electric- There is little change in the total amount of electricity trade between
ity transfer amounts reflects the future electricity trade pattern. The the FRC and BAU scenarios, although the economically viable capacity in
electricity-exporting regions are Jinmengxi, Northwest, Sichuan, South, the FRC scenario is higher. However, the pattern of electricity trade does
and Xinjiang, while the electricity-importing regions are East, Center, change. The Northwest, Jinmengxi, and Sichuan grids will export a por-
North, and Guangdong. Especially in the Center region, net electricity im- tion of electricity to the Guangdong region rather than the Center and
ports under the BAU scenario are approximately 5.5 times higher than East. The net electricity import to Guangdong under full regional con-
the REF scenario. Meanwhile, power supply and demand in the Northeast nection increases by 206 TWh in 2030. In other words, the connection
are almost balanced, with only a small amount of electricity being trans- between CSG and SGCC has no significant effect on electricity exports
ferred to the North region. The direction of electricity flow could change by the resource-rich areas, but affects electricity imports by the
hourly between certain regions, depending on the difference in marginal resource-poor areas. The utilization rate of the transmission lines from
generation costs. SGCC to Guangdong is mostly above 50%, and the utilization rate of in-
Net inter-regional electricity flows under the ETB scenario reach 1080 ternal lines of CSG has not been reduced. The main affected lines are
TWh in 2030, which is 15.8% less than the BAU scenario. The Center region Sichuan-East and Sichuan-Center. Due to the high share of hydropower
is the most heavily affected by electricity trade barriers, followed by the in Sichuan, the utilization rate of its export lines is relatively low, which
East region. The reduction in import demand in these two regions causes is close to 50% in the BAU scenario, but reduces to approximately 40% in
a decrease in electricity exports by certain resource-rich areas such as the the FRC scenario.
8 J.-H. Xu et al. / Energy Economics 91 (2020) 104890

Institutional barriers have a greater effect on the utilization effi-


ciency of regional power sectors than on scale, because utilization effi-
ciency can reflect the profitability of both new and existing thermal
power plants. Electricity trade barriers decrease utilization efficiency
in the Jinmengxi, Northwest, and Xinjiang regions, although they mark-
edly improve efficiency in the Center region. Meanwhile, utilization ef-
ficiency in two regions covered by CSG falls significantly under full
regional interconnection; the operation hours of thermal power plants
in the South and Guangdong regions decrease by 902 h and 1566 h re-
spectively, compared with the BAU scenario.

4.4. Risk analysis

Transmission capacity expansions under the market mechanism is


highly uncertain, which will significantly increase the risk of investment.
It can be seen from Section 2.1 that the scale of transmission expansion is
mainly affected by two factors: cost and benefit. The cost of transmission
investment is closely related to the discount rate. Meanwhile, inter-
Fig. 7. Regional total power generation capacity until 2030. regional electricity import restrictions caused by mechanism barriers
may also affect the utilization rate of lines and thus reduce the economy
of investment. The benefit of transmission investment mainly comes
4.3. Impact on regional power sectors
from the difference between regional power generation cost. Among
them, thermal power generation is generally affected by the fluctuation
4.3.1. Scale of regional power sectors
of coal prices. While the variable cost of renewable energy is very low.
We use the total power generation capacity to represent the scale of
Their generation cost mainly comes from the one-time investment at
regional power sectors, as shown in Fig. 7. The power sector scale in cer-
the beginning of construction, and the future decline trend of investment
tain regions varies significantly in the presence of inter-regional elec-
cost is highly uncertain. Therefore, this study evaluates the investment
tricity trade, although nationwide total capacity barely changes. We
risk of transmission line from four aspects, namely discount rates, maxi-
find that electricity trade improves the power sector scale in resource-
mum proportion of imports, coal prices, and renewable energy costs. In
rich areas such as Jinmengxi, Northwest, and Sichuan, while it depresses
addition, more sensitivity analyses about power demand and discount
the scale in resource-poor areas like Center and East.
rates are presented in the supplementary material.
The impact of institutional barriers is most evident where the inter-
connection between CSG and SGCC will depress the power sector scale
4.4.1. Discount rates
in Guangdong significantly. The total installed capacity in Guangdong
Discount rates reflect the expected return on investment. A rela-
decreases by more than 30 GW under full regional connection. Local
tively high discount rate is generally chosen to represent risks to trans-
governments are generally reluctant to assume such losses, which
mission line investments, including market risks, technical risks, and
may indicate that there will be resistance to connecting the regional
political risks. This study assumes a 10% discount rate for power trans-
power grids operated by CSG and SGCC.
mission technologies (Yi et al., 2016). To analyze the change in eco-
nomic benefits under different discount rates, we set it to vary from
4.3.2. Utilization efficiency of regional power sectors 5% to 20% (see Table 4).
Inter-regional electricity trade not only changes the scale of the re- The economic benefits of electricity interconnections are closely re-
gional power sector, but also affects utilization efficiency. In Fig. 8, we lated to the choice of discount rate. Here, it varies from 252.1 to 439.5
use the annual average operation hours of all thermal power plants, in- billion RMB, with a discount rate between 5%–20%. When a low dis-
cluding gas-fired power, USC, CHP, and other coal-fired power, to repre- count rate (5%) is offered, the increase in electricity flow is less than ca-
sent utilization efficiency. pacity, because more new lines will be built and utilized, leading to a
reduction in the utilization rate of existing lines. When a high discount
rate (20%) is offered, the changes in the optimal electricity flow patterns
are not significant.

4.4.2. Maximum proportion of electricity imports


We assume the maximum percentage of regional power demand
that can be met by electricity trade is 20% in the ETB scenario. Although
this percentage is based on the current numbers, it is still subjective. It
reflects the degree of regulated barriers, which may make the actual uti-
lization rate of transmission lines lower than expected and thus increase
the risk of investment. We set the maximum percentage of electricity
imports to vary from 10% to 25%, so that we might explore the effects

Table 4
Results under different discount rates.

Discount rate 5% 10% (BAU) 15% 20%

New transmission capacity (GW) 185.6 141.1 122.2 109.4


Net electricity flow in 2030 (TWh) 1476 1282 1226 1170
Total system costs (Billion RMB) 29,649.2 29,790.5 29,906.2 30,000.5
Net cost savings (Billion RMB) 439.5 355.6 295.8 252.1
Fig. 8. Operation hours of thermal power plant in 2030.
J.-H. Xu et al. / Energy Economics 91 (2020) 104890 9

Table 5
Results under different electricity import proportion.

Maximum proportion of electricity import 10% 15% 20% (ETB) 25% 100% (BAU)

New transmission capacity (GW) 85.1 100.0 120.8 139.2 141.1


Net electricity flow in 2030 (TWh) 579 829 1080 1257 1282
Total system costs (Billion RMB) 30,077.3 29,894.0 29,820.0 29,796.4 29,790.5
Net cost savings (Billion RMB) 68.8 252.1 326.1 349.7 355.6

Table 6
Results under different coal prices.

Annual growth rate of coal prices 0% 1% 2% (BAU) 3% 4%

New transmission capacity (GW) 128.9 135.0 141.1 151.9 165.1


Net electricity flow in 2030 (TWh) 1197 1223 1282 1338 1446
Total system costs (Billion RMB) 27,503.3 28,590.4 29,790.5 31,113.0 32,565.5
Net cost savings (Billion RMB) 340.3 346.1 355.6 372.8 404.7

Table 7 renewable energy. Changes in regional cost differences are relatively


Results under different renewable energy costs.
small so that the optimal equilibrium point of transmission invest-
Changes in renewable costs in 2030 +10% BAU −10% −20% ment has not changed significantly.
New transmission capacity (GW) 142.0 141.1 137.0 136.1
Net electricity flow in 2030 (TWh) 1285 1282 1266 1268 5. Conclusions
Total system costs (Billion RMB) 30,020.7 29,790.5 29,548.4 29,298.3
Net cost savings (Billion RMB) 352.2 355.6 360.4 363.5
This paper assesses the potential economic benefits of infrastructure
investments for the national inter-regional electricity network in China
until 2030, and analyzes the regulation effects associated with these in-
of different levels of trade barriers on the economic benefits of intercon- vestments on the economic benefits of interconnections. It presents a
nections (see Table 5). multi-regional power system optimization model, which integrates
Electricity trade barriers have a negative impact on the economic short-term power dispatch into the long-term investment decision
benefits of transmission infrastructure investments, because energy framework.
resources are not sufficiently integrated to meet the total national Our results show that approximately 140 GW of infrastructure con-
power demand. This impact becomes more obvious with the serious- struction for the inter-regional electricity trade network is economically
ness of barriers. The economic benefits under the 25% case are very viable during 2015–2030. The total transmission capacity increases
similar to the BAU scenario (in which there are no trade barriers), in- by 80% in 2030 compared with the base year. The network would
dicating that regional electricity import ratios will be mostly within incorporate lines connecting Jinmengxi-East, Jinmengxi-Center,
25% before 2030. Regulated barriers have a relatively high impact on Northwest-Center, Sichuan-East, Sichuan-Center, Xinjiang-Center, and
the investment risk, which also reflect the value of a clear long-term Northeast-North, leading to 250–440 billion RMB of economic benefits.
mechanism design. Our analysis highlights the key regulation effects facing the imple-
mentation of regional electricity interconnections. China's electricity
4.4.3. Coal prices market is still in its infancy. Regional electricity trade barriers caused
Coal is the most-consumed energy source in China's power sector. by imperfect market mechanisms have a negative impact on the eco-
Changes in coal prices affect the cost of coal-fired power units, and fur- nomic benefits of transmission infrastructure investments, although
ther affect the benefit of transmission line investment. Here, we exam- they promote scale and utilization efficiency in the power sector of
ine the sensitivity of coal prices by setting the annual growth rate to electricity-importing regions. Trade barriers lead to decreased net ex-
vary from 0% to 4% over the planning horizon (see Table 6). ports of electricity from the Jinmengxi, Northwest, and Xinjiang regions
Increased coal prices will lead to greater total system costs, but there to the Center region. The percentage of local power demand that is
is little change in the economic benefits of electricity interconnections. allowed to be met through electricity trade should be higher than 25%
However, it would increase the price of electricity generation in before 2030 to avoid the economic losses caused by the imperfect elec-
resource-poor areas, such as the Center and Guangdong regions, as tricity market.
coal remains the main source of power there. This would produce a By improving the national grid coordination mechanism and elimi-
slight increase in total inter-regional electricity flows. The risk brought nating the grid isolation between the State Grid Corporation of China
by coal price to power transmission investment is relatively limited, (SGCC) and the China Southern Power Grid (CSG), several transmission
and high price will be more conducive to transmission capacity lines can be built, providing approximately 280 billion RMB of economic
expansion. benefits during 2015–2030. The Northwest, Jinmengxi, and Sichuan re-
gions will export a portion of electricity to Guangdong instead of to the
4.4.4. Renewable energy costs Center and East. However, the establishment of such a coordination
There are many uncertainties about the downward trend in the mechanism will encounter certain obstacles. First, large-scale electricity
cost of renewable energy investment, which highly depends on the imports from SGCC will weaken electricity transmission within CSG.
level of technological progress. We set the investment cost of various Second, such changes in electricity trade patterns will negatively affect
types of renewable energy in 2030 to change at the BAU level by the scale and utilization efficiency of the regional power sector covered
+10%, −10%, and −20%. And the cost of investment varies propor- by CSG, resulting in an uneven distribution of economic benefits among
tionately in other years. From the results of Table 7, it can be seen regions.
that the optimal scale of transmission expansion and interconnec- The results of this study suggest several topics for further re-
tion pattern have little relationship with the investment cost of search. First, our model calculates the optimal power generation
10 J.-H. Xu et al. / Energy Economics 91 (2020) 104890
!
and transmission portfolios for all regions from a social planner per- XXX
C CO2
t ¼ pCO2
t  P i;n;t;h  en  θn −At ðA:6Þ
spective, but investment decisions are not made by one individual. It i n h
would also be meaningful to analyze the game between the State
!
Grid Corporation of China and the China Southern Power Grid, or XX X
t   Tr 
to explore the distribution of gains brought by electricity trade be- C TInv
t ¼ cFTInv
t 0 þ c VTInv
t 0  di; j  X i; j;t 0  ∂ ðA:7Þ
i j t 0 ¼t−Tþ1
tween regions. Second, nonlinear constraints resulting from
Kirchhoff's voltage law can be included into the model. Extending XX
the formulation to include alternating current transmission network C tTO&M ¼ Z Tr TO&M
i; j;t  ci; j ðA:8Þ
i j
as well as flowgate constrains enables us to analyze the economy of
UHVDC and UHVAC between different regions.

A.2. Constraints
Author contributions
This model is subject to the following constraints.
All authors conceived the research. Bo-Wen Yi constructed the
model; Jin-Hua Xu provided the data; Ying Fan performed the analysis; X
t
Z Gi;n;t ¼ X Gi;n;t 0 ðA:9Þ
Bo-Wen Yi wrote the paper; All authors contributed to the interpreta-
t 0 ¼t−T n þ1
tion of the findings.
X
t
Z Tr
i; j;t ¼ X Tr
i; j;t 0 ðA:10Þ
Declaration of Competing Interest
t 0 ¼t−Tþ1

The authors declared that we do not have any commercial or asso- X Gi;n;t ≤ X Max ðA:11Þ
i;n
ciative interest that represents a conflict of interest in connection with
the work submitted.
U i;n;t;h ¼ U i;n;t;h−1 þ SU i;n;t;h −SDi;n;t;h ðA:12Þ

Acknowledgements U i;n;t;h  P min max


n ≤P i;n;t;h ≤U i;n;t;h  P n ðA:13Þ
 
This work is supported by the National Key Research and Develop- P i;n;t;hþ1 −P i;n;t;h ≤ U i;n;t;hþ1 −SU i;n;t;hþ1  ΔP up
n þ SU i;n;t;hþ1
min min
ment Program of China under Grant No. 2017YFE0101800, the National  P n −SDi;n;t;hþ1  P n ðA:14Þ
Natural Science Foundation of China under Grant No. 71950008, No.
71690245, and No. 71673266. The authors appreciate the weekly joint  
P i;n;t;h −P i;n;t;hþ1 ≤ U i;n;t;hþ1 −SU i;n;t;hþ1  ΔP down
n þ SDi;n;t;hþ1
seminars at CEEP in Beihang SEM, from where the earlier draft of the pa-  P min min
n −SU i;n;t;hþ1  P n ðA:15Þ
per got improved. The authors are very grateful to Ms. Xiulian Liu, who
always gives them enough help and advices.
U i;n;t;h ≤ Z Gi;n;t  vGn  f i;n;h ðA:16Þ

Appendix A. Model description X X


j≠i
Di;t;h ¼ P TI TO
i;t;h −P i;t;h þ P i;n;t;h ¼ PT j;i;t;h
n j
A.1. Objective function
  X j≠i
 1−l j;i − PT i; j;t;h
The objective function is to minimize the accumulated total system
X j
costs from the perspective of social planner. The total system costs (C) þ P i;n;t;h ðA:17Þ
include the investment cost (CInv t ), O&M cost (Ct
O&M
), fuel cost (CFuel
t ), n
start-up cost (CStartup
t ), CO2 emissions cost (CCO2
t ) of power generation
technologies, and the investment cost (CTInv t ), O&M cost (CTO&M t ) of PT i; j;t;h ≤ Z Tr
i; j;t  v
Tr
ðA:18Þ
power transmission technologies, as shown in Eq. (A.1). The specific XXX XXX
cost calculations are shown in Eqs. (A.2)–(A.8). P i;nhr;2030;h ≥ P i;n;2030;h  λRps ðA:19Þ
X  Inv  i nhr h i n h
min C ¼ C t þ C O&M
t þ C Fuel
t þ C Startup
t þ C CO2
t þ C TInv
t þ C tTO&M XXX
t P i;nff ;2030;h ≥ EPe
2030  λ
Pe
ðA:20Þ
ðA:1Þ i nff h

!
XX X
t
X G ; X Tr ; U; SU; SD; P; PT ≥ 0 ∀i; n; t; h ðA:21Þ
C Inv
t ¼ cInv
n;t 0  X Gi;n;t 0  ∂n ðA:2Þ
i n t 0 ¼t−T n þ1
Eqs. (A.9) and (A.10) show the calculations of the total capacity for
XX each power generation and transmission technology. Eq. (A.11) limits
C O&M
t ¼ Z Gi;n;t  cO&M
n;t ðA:3Þ
i n the annual construction speed of power generation technology.
Eq. (A.12) represents the dynamics of commitment states for fossil
XXX
C Fuel ¼ P i;n;t;h  en  pFuel ðA:4Þ fuel technologies. Eq. (A.13) is the maximum and minimum power out-
t i;n;t
i n h put constraints for the committed capacities. Eqs. (A.14) and (A.15) are
XXX the ramping up and ramping down constraints for fossil fuel technolo-
C Startup
t ¼ SU i;n;t;h  cStartup
n ðA:5Þ gies. Eq. (A.16) limits the available capacity at each hour, which is a con-
i n h nection between the power dispatch module and the power generation
expansion module. Eq. (A.17) shows the real-time matching of power
supply and demand considering inter-regional power interconnections.
Eq. (A.18) limits the available transmission capacity at each hour.
J.-H. Xu et al. / Energy Economics 91 (2020) 104890 11

Table A.1 A.3. Nomenclatures


The indexes.

Indexes Specifications See Tables A.1–A.3.


i, j Region
t, t’ Year Appendix B. Supplementary data
h Hour
n Power generation technology Supplementary material: Datasets and sensitivity analysis for key
nhr Non-hydro renewable energy generation
parameters are provided in detail in the Supplementary material at-
nff Non-fossil fuel generation
tached to this article. Datasets include power demand, key technical
and economic parameters, existing generation mix, and renewable en-
ergy meteorological data. It also involves the sensitivity analysis of
Table A.2 power demand and discount rates of power generation technologies.
The decision variables.

Variables Specifications [Units] References


XGi,n,t New built capacity of power generation technology n in region i in year Abrell, J., Rausch, S., 2016. Cross-country electricity trade, renewable energy and
t [MW] European transmission infrastructure policy. J. Environ. Econ. Manag. 79, 87–113.
XTr
i,j,t New built capacity of power transmission technology from region i to j Ahmed, T., Mekhilef, S., Shah, R., et al., 2017. Investigation into transmission options for
in year t [MW] cross-border power trading in ASEAN power grid. Energy Policy 108, 91–101.
Ui,n,t,h Capacity of technology n in region i which is committed at hour h in Allard, S., Mima, S., Debusschere, V., et al., 2020. European transmission grid expansion as
year t [MW] a flexibility option in a scenario of large scale variable renewable energies integration.
SUi,n,t,h Capacity of technology n in region i which starts up at hour h in year Energy Econ. 87, 104733.
t[MW] Chang, Y., Li, Y., 2015. Renewable energy and policy options in an integrated ASEAN elec-
SDi,n,t,h Capacity of technology n in region i which shuts down at hour h in year tricity market: quantitative assessments and policy implications. Energy Policy 85,
t [MW] 39–49.
Pi,n,t,h Power output of technology n in region i at hour h in year t [MWh] Chao, H., Wilson, R., 2020. Coordination of electricity transmission and generation invest-
PTi,j,t,h Power transmitted from region i to j at hour h in year t [MWh] ments. Energy Econ. 86, 104623.
PTI
i,t,h Total power transmitted to region i at hour h in year t [MWh] Chen, Q., Kang, C., Ming, H., et al., 2014. Assessing the low-carbon effects of inter-regional
PTO Total power transmitted from region i at hour h in year t [MWh] energy delivery in China’s electricity sector. Renew. Sust. Energ. Rev. 32, 671–683.
i,t,h
G
Zi,n,t Total capacity of power generation technology n in region i in year Cheng, L., Feng, Y., Wang, N., et al., 2015a. Load characteristics analysis and peak margin
t[MW] calculation of Beijing-Tianjin-northern Hebei power grid. North China Elec. Pow. 11,
1–5 (in Chinese).
ZTr
i,j,t Total capacity of power transmission technology from region i to j in
Cheng, R., Xu, Z., Liu, P., et al., 2015b. A multi-region optimization planning model for
year t [MW]
China’s power sector. Appl. Energy 137, 413–426.
China Electric Power Yearbook Editorial Board (CEPYEB), 2015. China electric power year-
book 2015. China Electric Power Press, Beijing (in Chinese).
China Electric Power Yearbook Editorial Board (CEPYEB). China electric power yearbook
Table A.3 2016. China Electric Power Press, Beijing (in Chinese).
The parameters. China Southern Power Grid (CSG), 2017. Ultra-high voltage direct current project. Avail-
able from: http://eng.csg.cn/Science_Innovation/UHVDC/201512/t20151209_
Parameters Specifications [Units] 109562.html.
cInv Unit investment cost of technology n in year t [RMB/MW] Davidson, M.R., Zhang, D., Xiong, W., et al., 2016. Modelling the potential for wind energy
n,t
integration on China’s coal-heavy electricity grid. Nat. Energy 1, 16086.
∂n Present annuity coefficient at a given discount rate
Delarue, E.D., Luickx, P.J., D’haeseleer, W.D., 2009. The actual effect of wind power on
cO&M
n,t Unit O&M cost of technology n in year t [RMB/MW]
overall electricity generation costs and CO2 emissions. Energy Convers. Manag. 50
en Energy consumption per unit of electricity of technology n [t/MWh]
(6), 1450–1456.
cStartup
n Unit start-up costs for technology n [RMB/time/MW]
Duan, H., Mo, J., Fan, Y., et al., 2018. Achieving China’s energy and climate policy targets in
PCO2
t CO2 price in year t [RMB/t-CO2]
2030 under multiple uncertainties. Energy Econ. 70, 45–60.
θn Unit CO2 emission of the fuel used by technology n [t-CO2/t]
Dutton, J., Lockwood, M., 2017. Ideas, institutions and interests in the politics of cross-
At CO2 cap in year t [t-CO2] border electricity interconnection: Greenlink, Britain and Ireland. Energ. Policy 106,
cFTInv
t Unit fix investment cost of power transmission technology in year 375–385.
t[RMB/MW] Fleiter, T., Worrell, E., Eichhammer, W., 2011. Barriers to energy efficiency in industrial
cVTInv
t Unit variable investment cost of power transmission technology in bottom-up energy demand models—a review. Renew. Sust. Energ. Rev. 15 (6),
year t [RMB/km/MW] 3099–3111.
di,j Distance between region i and j [km] Gujba, H., Mulugetta, Y., Azapagic, A., 2010. Environmental and economic appraisal of
TO&M
ci,j Unit O&M cost of power transmission from region i to j [RMB/MW] power generation capacity expansion plan in Nigeria. Energy Policy 38 (10),
XMax
i,n Maximum expansion allowed within 1 year for technology n in 5636–5652.
region i [MW] Guo, Z., Ma, L., Liu, P., et al., 2016. A multi-regional modeling and optimization approach
PMax
n Maximum power output rates of technology n [%] to China’s power generation and transmission planning. Energy 116, 1348–1359.
PMin
n Minimum power output rates of technology n [%] Guo, Z., Ma, L., Liu, P., et al., 2017. A long-term multi-region load-dispatch model based on
ΔPup n Maximum ramping up capability of technology n [%] grid structures for the optimal planning of China’s power sector. Comput. Chem. Eng.
ΔPdown
n Maximum ramping down capability of technology n [%] 102, 52–63.
vnG
Available generation capacity rate of technology n [%] Hanson, D., Schmalzer, D., Nichols, C., et al., 2016. The impact of meeting a tight CO2 per-
fi,n,h Capacity factor for renewable energy technology n in region i at hour formance standard on the electric power sector. Energy Econ. 60, 476–485.
h [%] Holladay, J.S., LaRiviere, J., 2017. The impact of cheap natural gas on marginal emissions
li,j Transmission loss between region i and j [%] from electricity generation and implications for energy policy. J. Environ. Econ.
Manag. 85, 205–227.
vTr Available transmission capacity rate [%]
Hu, Z., Yuan, J., Hu, Z., 2011. Study on China’s low carbon development in an economy–
λRps Target of the share of non-hydro renewable energy in total power
energy–electricity–environment framework. Energ. Policy 39 (5), 2596–2605.
generation in 2030 [%]
Hui, J., Cai, W., Wang, C., et al., 2017. Analyzing the penetration barriers of clean genera-
EPe Total primary energy consumption [MWh]
tion technologies in China’s power sector using a multi-region optimization model.
λPe Target of the share of non-fossil energy in total primary energy in
Appl. Energy 185, 1809–1820.
2030 [%]
Huppmann, D., Egerer, J., 2015. National-strategic investment in European power trans-
mission capacity. Eur. J. Oper. Res. 247, 191–203.
International Energy Agency (IEA), 2018. World Energy Outlook. p. 2018.
Eqs. (A.19) and (A.20) are policy target constraints. Eq. (A.21) guaran- Kalnay, et al., 1996. The NCEP/NCAR 40-year reanalysis project. Bull. Amer. Meteor. Soc.
77, 437–470.
tees that the decision variables are non-negative.
Koltsaklis, N.E., Georgiadis, M.C., 2015. A multi-period, multi-regional generation expan-
sion planning model incorporating unit commitment constraints. Appl. Energy 158,
310–331.
12 J.-H. Xu et al. / Energy Economics 91 (2020) 104890

Lai, M., Hong, B., 2007. The influences of the air conditioning load on the daily load char- State Grid Corporation of China (SGCC), 2017. The project approval of state grid of China.
acteristics of Central China power grid. Elect. Pow. Technol. Economics 19 (3), 30–33 Available from: http://www.sgcc.com.cn/ywlm/index.shtml.
(in Chinese). Su, B., Ang, B.W., 2017. Multiplicative structural decomposition analysis of aggregate em-
Li, Y., Chang, Y., 2015. Infrastructure investments for power trade and transmission in bodied energy and emission intensities. Energy Econ. 65, 137–147.
ASEAN+ 2: costs, benefits, long-term contracts and prioritized developments. Energy Tang, B., Dong, Z., 2012. Analysis on load characteristics of China southern power grid in
Econ. 51, 484–492. 11th five year plan. Electric Power 45 (10), 30–35 (in Chinese).
Li, Y., Lukszo, Z., Weijnen, M., 2015. The implications of CO2 price for China’s power sector Timilsina, G.R., Toman, M., 2016. Potential gains from expanding regional electricity trade
decarbonization. Appl. Energy 146, 53–64. in South Asia. Energy Econ. 60, 6–14.
Li, Y., Lukszo, Z., Weijnen, M., 2016. The impact of inter-regional transmission grid expan- Wang, C., Ye, M., Cai, W., 2014. The value of a clear, long-term climate policy agenda: a
sion on China’s power sector decarbonization. Appl. Energy 183, 853–873. case study of China’s power sector using a multi-region optimization model. Appl.
Lienert, M., Lochner, S., 2012. The importance of market interdependencies in modeling Energy 125, 276–288.
energy system–the case of the European electricity generation market. Electr. Wei, L., Zhang, L., Jiang, N., et al., 2010. Analysis of load characteristics for Northwest China
Power Energy Syst. 34, 99–113. power grid. Pow. Syst. Clean Energ. 26 (7), 57–62 (in Chinese).
Lv, Q., Wang, W., Han, S., et al., 2013. A new evaluation method for wind power curtail- Weigt, H., Ellerman, D., Delarue, E., 2013. CO2 abatement from renewables in the German
ment based on analysis of system regulation capability. Pow. Syst. Technol. 37 (7), electricity sector: does a CO2 price help? Energy Econ. 40, 149–158.
1887–1894 (in Chinese). Weijde, A.H., Hobbs, B.F., 2012. The economics of planning electricity transmission to ac-
Merrick, J.H., 2016. On representation of temporal variability in electricity capacity plan- commodate renewables: using two-stage optimisation to evaluate flexibility and the
ning models. Energy Econ. 59, 261–274. cost of disregarding uncertainty. Energy Econ. 34 (6), 2089–2101.
Pan, Y., Yao, X., Wang, X., et al., 2019. Policy uncertainties: what investment choice for Yi, B., Xu, J., Fan, Y., 2016. Inter-regional power grid planning up to 2030 in China consid-
solar panel producers? Energy Econ. 78, 454–467. ering renewable energy development and regional pollutant control: a multi-region
Pfluger, B., 2014. Assessment of Least-Cost Pathways for Decarbonising Europe’s Power bottom-up optimization model. Appl. Energy 184, 641–658.
Supply: A Model-Based Long-Term Scenario Analysis Accounting for the Characteris- Yi, B., Xu, J., Fan, Y., 2017. Optimal pathway and impact of achieving the mid-long term
tics of Renewable Energies. KIT Scientific Publishing, Karlsruhe, Germany. renewable energy standard in China. J. Syst. Eng. 32 (3), 313–324 (in Chinese).
Rosellon, J., 2003. Different approaches towards electricity transmission expansion. Rev. Yi, B., Xu, J., Fan, Y., 2019. Coordination of policy goals between renewable portfolio stan-
Netw. Econ. 2 (3), 1–32. dards and carbon caps: a quantitative assessment in China. Appl. Energy 237, 25–35.
Scholz, Y., Gils, H.C., Pietzcher, R.C., 2017. Application of a high-detail energy system Yuan, J., Xu, Y., Kang, J., et al., 2014. Nonlinear integrated resource strategic planning
model to derive power sector characteristics at high wind and solar shares. Energy model and case study in China’s power sector planning. Energy 67, 27–40.
Econ. 64, 568–582. Zhu, X., Genton, M., 2012. Short-term wind speed forecasting for power system opera-
Shu, J., Zhang, J., Zheng, Y., 2005. Discussion on rational scale of pumped storage power tions. Int. Stat. Rev. 80 (1), 2–23.
station in East China power grid in 2010. Water Resour. Pow. 23 (5), 54–57 (in
Chinese).

You might also like