You are on page 1of 1

MEB4343 Asset Performance Assessment & Maintenance May 2023

Assignment Semester

Individual Assignment 4 Due date:


14/07/2023

A total of 5 agitator vessels (FIGURE Q1) are installed in the chemical plant at Chemical
Industries Sdn Bhd which manufactures ‘speciality’ chemical that is corrosive in nature.
Below are the materials used for the construction of the agitator system:
• Shell, body and support of vessel: SA-240 304
• Nozzle necks & pipe: SA-312 TP304
• Flanges: SA-182 F304
• Fittings: SA-403 WP304
• Gaskets: Spiral wound with 316 (both outer and inner rings)
• Shaft: A276-316L

Based on 3 years record of the reliability and asset management team, all 5 of the agitator
vessels suffer bending of the agitator shaft and has been classified as a ‘bad actor’.

FIGURE Q1

With appropriate illustrations, perform root cause analysis (RCA) using 5-whys technique,
explain your findings in point form and 1 major recommendation. There is a page limit of 1
page for this assignment submission.

[10 marks]

ONLY handwritten & hand-sketched (scanned) and submitted scripts would be


graded.

Typed scripts would be considered non-submission.

You might also like