1 FFT-Turnaround 2023 674h 1/18/2023 7:00 2/15/2023 9:00
2 Turnaround Milestones 240h 1/18/2023 7:00 1/28/2023 7:00
3 Ammonia Unit 674h 1/18/2023 7:00 2/15/2023 9:00
4 Shutdown 30h 1/18/2023 7:00 1/19/2023 13:00
5 Maintenance Phase 674h 1/18/2023 7:00 2/15/2023 9:00
6 Machinery 674h 1/18/2023 7:00 2/15/2023 9:00
7 101J Overhauling and Diapharagm Machining 674h 1/18/2023 7:00 2/15/2023 9:00
8 1101J Pre-prepration (Pre-Shutdown Jobs) 49h 1/18/2023 7:00 1/20/2023 8:00
9 1101JHP-Overhailing & Diaphragm Machining 612h 1/19/2023 17:00 2/14/2023 5:00
10 101JHP- Metalock Machining Works(Mandatory) 480h 1/22/2023 3:00 2/11/2023 3:00
11 101JHP- Box-Up 74h 2/11/2023 3:00 2/14/2023 5:00
12 1101JLP- Overhailing & Diaphragm Machining 605h 1/19/2023 17:00 2/13/2023 22:00
13 101JLP- Machining Works 529h 1/22/2023 21:00 2/13/2023 22:00
14 Lube Oil System Inspection / Cleaning 548h 1/22/2023 21:00 2/14/2023 17:00
15 101J Commissioning 28h 2/14/2023 5:00 2/15/2023 9:00
16 105J - Ammonia Compressor Maintenance 434h 1/18/2023 7:00 2/5/2023 9:00
17 105JT Overhauling 200h 1/19/2023 13:00 2/5/2023 9:00
18 105JT- Commissioning 14h 2/4/2023 7:00 2/5/2023 9:00
19 105JLP / HP Bearings Inspection 0h
20 1101JBT- Overhauling of Gearbox 196h 1/18/2023 7:00 1/26/2023 11:00
21 Equipment 272h 1/18/2023 7:00 1/29/2023 15:00
22 102E- Internal Inspection 270h 1/18/2023 7:00 1/29/2023 13:00
23 102E- Bed 1 158h 1/21/2023 23:00 1/28/2023 13:00
24 102E- Bed 2 146h 1/21/2023 21:00 1/27/2023 23:00
25 102E- Bed 3 134h 1/21/2023 19:00 1/27/2023 9:00
26 102E- Bed 4 126h 1/21/2023 17:00 1/26/2023 23:00
27 102E- Bed 5 82h 1/21/2023 15:00 1/25/2023 1:00
28 Demister Pad Cleaning 200h 1/21/2023 1:00 1/29/2023 9:00
29 101E- Internal Inspection 170h 1/18/2023 7:00 1/25/2023 9:00
30 101E - Bed 1 59h 1/21/2023 14:00 1/24/2023 1:00
31 101E - Bed 2 55h 1/21/2023 12:00 1/23/2023 19:00
32 101E - Bed 3 59h 1/21/2023 10:00 1/23/2023 21:00
33 101E - Bed 4 63h 1/21/2023 8:00 1/23/2023 23:00
34 101E - Demister Pad Cleaning 111h 1/20/2023 14:00 1/25/2023 5:00
35 1101JLP- Intergrals Coolers Cleaning 254h 1/18/2023 7:00 1/28/2023 21:00
36 101CJ- Cleaning and Pressure Testing 272h 1/18/2023 7:00 1/29/2023 15:00
37 1111C- External Cleaning and Pressure Testing 149h 1/18/2023 7:00 1/24/2023 12:00
38 1105CA-External Cleaning and Pressure Testing 149h 1/18/2023 7:00 1/24/2023 12:00
39 1105CB-External Cleaning and Pressure Testing 149h 1/18/2023 7:00 1/24/2023 12:00
40 105JCA - Cleaning & Pressure Testing 78h 1/18/2023 7:00 1/21/2023 13:00
41 105JCB - Cleaning & Pressure Testing 98h 1/18/2023 7:00 1/22/2023 9:00
42 101JCA- Cleaning & Pressure Testing 87h 1/18/2023 7:00 1/21/2023 22:00
43 101JCB- Cleaning & Pressure Testing 105h 1/18/2023 7:00 1/22/2023 16:00
44 1139C- Mechanical Cleaning & Pressure Testing 146h 1/18/2023 7:00 1/24/2023 9:00
45 109C- Cleaning & Pressure Testing 110h 1/18/2023 7:00 1/22/2023 21:00
46 103C- Eddy Current Inspection 230h 1/18/2023 7:00 1/27/2023 21:00
47 1104C - Eddy Cuurent Inspection & Bundle cleaning if required 178h 1/18/2023 7:00 1/25/2023 17:00
48 1136C- Cleaning With Jetting & Pressure Testing 112h 1/18/2023 7:00 1/22/2023 23:00
49 1158F- Internal Inspection & Dimester Pad Removal 140h 1/18/2023 7:00 1/24/2023 3:00
50 102B- Internal Inspection 126h 1/18/2023 7:00 1/23/2023 13:00
51 103B- Internal Inspection 93h 1/18/2023 7:00 1/22/2023 4:00
52 105F- Internal Inspection after Dimister Pad Removal 81h 1/18/2023 7:00 1/21/2023 16:00
53 106F - Internal Inspection 125h 1/18/2023 7:00 1/23/2023 12:00
54 107F- Internal Inspection 111h 1/18/2023 7:00 1/22/2023 22:00
55 108F- Internal Inspection 94h 1/18/2023 7:00 1/22/2023 5:00
56 109F- Internal Inspection 86h 1/18/2023 7:00 1/21/2023 21:00
57 110F- Internal Inspection 85h 1/18/2023 7:00 1/21/2023 20:00
58 111F- Internal Inspection 85h 1/18/2023 7:00 1/21/2023 20:00
59 112F- Internal Inspection 85h 1/18/2023 7:00 1/21/2023 20:00
60 113F- Internal Inspection 79h 1/18/2023 7:00 1/21/2023 14:00
61 1101F- Internal Inspection & Repair 68h 1/18/2023 7:00 1/21/2023 3:00
62 1101C- Internal Inspection & Refractory Repair 206h 1/18/2023 7:00 1/26/2023 21:00
63 1139F- Internal Inspection 64h 1/18/2023 7:00 1/20/2023 23:00
64 115F- Internal Inspection 62h 1/18/2023 7:00 1/20/2023 21:00
65 102F- Internal Inspection & Repair 101h 1/18/2023 7:00 1/22/2023 12:00
66 1107D- Inspection of Tranfr Line & Thickness Gauging 26h 1/18/2023 7:00 1/19/2023 9:00
67 115C- Cleaning & Eddy Current Testing 130h 1/18/2023 7:00 1/23/2023 17:00
68 127CA- Cleaning & Press. Testing 71h 1/18/2023 7:00 1/21/2023 6:00
69 127CB- Cleaning & Press. Testing 71h 1/18/2023 7:00 1/21/2023 6:00
70 107C1- Cleaning & Press. Testing 82h 1/18/2023 7:00 1/21/2023 17:00
71 107C2- Cleaning & Press. Testing 82h 1/18/2023 7:00 1/21/2023 17:00
72 110C1A- Cleaning & Flange Facing 168h 1/18/2023 7:00 1/25/2023 7:00
73 110C1B- Cleaning & Flange Facing 168h 1/18/2023 7:00 1/25/2023 7:00
74 110C2A- Cleaning & Flange Facing 168h 1/18/2023 7:00 1/25/2023 7:00
75 110C2B- Cleaning & Flange Facing 168h 1/18/2023 7:00 1/25/2023 7:00
76 Workshop 4h 1/18/2023 7:00 1/18/2023 11:00
77 101BAUX- Inspection & Repair of Recractory 4h 1/18/2023 7:00 1/18/2023 11:00
78 101BCON- Refractory Inspection & Repair 4h 1/18/2023 7:00 1/18/2023 11:00
79 101BRAD- Rfractory Inspection & Repair 4h 1/18/2023 7:00 1/18/2023 11:00
80 101BSUP- Refractory Inspection & Repair 4h 1/18/2023 7:00 1/18/2023 11:00
81 103D- Target Bricks Replacement 4h 1/18/2023 7:00 1/18/2023 11:00
82 Process 435h 1/18/2023 7:00 2/5/2023 10:00
83 101B- Primary Reformer Catalyst Repl. 435h 1/18/2023 7:00 2/5/2023 10:00
84 Radiant Section 399h 1/19/2023 19:00 2/5/2023 10:00
85 Top Work 399h 1/19/2023 19:00 2/5/2023 10:00
86 Inside Work 397h 1/19/2023 21:00 2/5/2023 10:00
87 Convection Section 84h 1/18/2023 7:00 1/21/2023 19:00
88 Auxialry Section 100h 1/18/2023 7:00 1/22/2023 11:00
89 103D- Top 3-5 ft Catalyst Skimming 361h 1/18/2023 7:00 2/2/2023 8:00
90 104D- HTS Catalyst Replacement 249h 1/18/2023 7:00 1/28/2023 16:00
91 Start-up 45h 1/18/2023 7:00 1/20/2023 3:30
92 Urea Unit 417h 1/18/2023 7:00 2/4/2023 16:00
93 Shutdown 74h 1/18/2023 7:00 1/21/2023 9:00
94 Maintenance Phase 417h 1/18/2023 7:00 2/4/2023 16:00
95 Equipment 340h 1/18/2023 7:00 2/1/2023 11:00
96 E2163- Replacment of Tube Bundle 76h 1/18/2023 7:00 1/21/2023 11:00
97 E2172- Eddy Current Inspection 70h 1/18/2023 7:00 1/21/2023 5:00
98 V2181 - Internal Inspection 92h 1/18/2023 7:00 1/22/2023 3:00
99 V2172- Leaky gaskey repl. & internal inspection 147h 1/18/2023 7:00 1/24/2023 10:00
100 V2182- Interanl Inspection & corroded end top repl. 340h 1/18/2023 7:00 2/1/2023 11:00
101 V2171- Repl. of Old Vessel With New One 265h 1/18/2023 7:00 1/29/2023 8:00
102 P2202D- Discharge Bottle Leakage Remedy (TR) Revivial 208h 1/18/2023 7:00 1/26/2023 23:00
103 P231- Repl. of Leaky Discharge line 4h 1/18/2023 7:00 1/18/2023 11:00
104 TK201- Internal Inspection 156h 1/18/2023 7:00 1/24/2023 19:00
105 TK209- Internal Inspection 76h 1/18/2023 7:00 1/21/2023 11:00
106 TK210- Internal Inspection 76h 1/18/2023 7:00 1/21/2023 11:00
107 V206- - Preliminary Inspection of Trays 288h 1/18/2023 7:00 1/30/2023 7:00
108 V207- - Internal Inspection 126h 1/18/2023 7:00 1/23/2023 13:00
109 V2201B- Head Gasket Repl. & Thickness Monitoring 253h 1/18/2023 7:00 1/28/2023 20:00
110 V212- Internal Inspection & Repair 228h 1/18/2023 7:00 1/27/2023 19:00
111 V2161- Internal Inspection & Repair 180h 1/18/2023 7:00 1/25/2023 19:00
112 V2162- Internal Inspection of Trays 207h 1/18/2023 7:00 1/26/2023 22:00
113 V2163- Internal Inspection & Repair 207h 1/18/2023 7:00 1/26/2023 22:00
114 E214A- Cleaning, Pressure Testing & Flange Facing 36h 1/18/2023 7:00 1/19/2023 19:00
115 E214B- Cleaning, Pressure Testing & Flange Facing 36h 1/18/2023 7:00 1/19/2023 19:00
116 E214C- Cleaning, Pressure Testing & Flange Facing 36h 1/18/2023 7:00 1/19/2023 19:00
117 E214D- Cleaning, Pressure Testing & Flange Facing 36h 1/18/2023 7:00 1/19/2023 19:00
118 E212E- Cleaning, Pressure Testing & Flange Facing 36h 1/18/2023 7:00 1/19/2023 19:00
119 E212F- Cleaning, Pressure Testing & Flange Facing 36h 1/18/2023 7:00 1/19/2023 19:00
120 E230- Cleaning, Pressure Testing & Flange Facing 12h 1/18/2023 7:00 1/18/2023 19:00
121 Machinery 275h 1/18/2023 7:00 1/29/2023 18:00
122 C201A - Fluid End Overhauling 266h 1/18/2023 7:00 1/29/2023 9:00
123 C201B - Fluid End Overhauling 275h 1/18/2023 7:00 1/29/2023 18:00
124 P201A- Ammonia Pump Maintenance 78h 1/18/2023 7:00 1/21/2023 13:00
125 P201B- Ammonia Pump Maintenance 202h 1/18/2023 7:00 1/26/2023 17:00
126 P201C- Ammonia Pump Maintenance 152h 1/18/2023 7:00 1/24/2023 15:00
127 Electrical 192h 1/18/2023 7:00 1/26/2023 7:00
128 MC2111 - Overhauling of 11KVA Motor 192h 1/18/2023 7:00 1/26/2023 7:00
129 Instrument 46h 1/18/2023 7:00 1/21/2023 17:00
130 C2111 - PLC Panel Replacement 46h 1/18/2023 7:00 1/21/2023 17:00
131 Workshop 417h 1/18/2023 7:00 2/4/2023 16:00
132 T200- Prill Tower Internal Civil Inspection/ Repair 417h 1/18/2023 7:00 2/4/2023 16:00
133 Start-up 14h 1/18/2023 7:00 1/18/2023 21:00
134 Utility 466h 1/18/2023 7:00 2/6/2023 17:00
135 Shutdown 23h 1/18/2023 17:00 1/19/2023 16:00
136 Maintenance Phase 432h 1/18/2023 7:00 2/5/2023 7:00
137 Equipment 157h 1/18/2023 7:00 1/24/2023 20:00
138 452U- Installation of New Tank Degassifier 6h 1/18/2023 7:00 1/18/2023 13:00
139 B401A- Internal Inspection & Repair 60h 1/18/2023 7:00 1/20/2023 19:00
140 Steam Drum 6h 1/18/2023 7:00 1/18/2023 13:00
141 Mud Drum 6h 1/18/2023 7:00 1/18/2023 13:00
142 Convection Section 10h 1/18/2023 7:00 1/18/2023 17:00
143 Radiant Section 24h 1/18/2023 7:00 1/19/2023 7:00
144 Super Heater 10h 1/18/2023 7:00 1/18/2023 17:00
145 Pressure Testing of Boiler 8h 1/18/2023 7:00 1/18/2023 15:00
146 B401B- Internal Inspection & Repair 4h 1/18/2023 7:00 1/18/2023 11:00
147 Steam Drum 0h
148 Mud Drum 0h
149 Convection Section 0h
150 Radiant Section 0h
151 Super Heater 0h
152 Pressure Testing of Boiler 0h
153 454U1- Resign Repl. & Internal Inspction Mix Bed A 157h 1/18/2023 7:00 1/24/2023 20:00
154 454U2- Resign Repl. & Internal Inspction Mix Bed B 157h 1/18/2023 7:00 1/24/2023 20:00
155 HRSG- Internl Inspection of Steam Drum & Mud Drum & Burners 52h 1/18/2023 7:00 1/20/2023 11:00
156 Steam Drum Inspection 16h 1/18/2023 7:00 1/18/2023 23:00
157 Mud Drum Inspection 19h 1/18/2023 7:00 1/19/2023 2:00
158 SuperHeater Inspection 52h 1/18/2023 7:00 1/20/2023 11:00
159 Internal Inspection of Stack, Economizer, Evaporator 22h 1/18/2023 7:00 1/19/2023 5:00
160 Sulphuric Acid Daytank- Internal Inspection of Vessel 11h 1/18/2023 7:00 1/18/2023 18:00
161 V411- Internal Inspection of Caustic Soda Tank 98h 1/18/2023 7:00 1/22/2023 9:00
162 TK407- Repairing of Wek Areas 4h 1/18/2023 7:00 1/18/2023 11:00
163 Process 0h
164 Machinery 408h 1/18/2023 7:00 2/4/2023 7:00
165 TG401B- Overhauling of Turbine 408h 1/18/2023 7:00 2/4/2023 7:00
166 TG401A- Complete Train Bearing Inspection 175h 1/18/2023 7:00 1/25/2023 14:00
167 Electrical 83h 1/18/2023 7:00 1/21/2023 18:00
168 TG401A- Replacement of AVR Panel 83h 1/18/2023 7:00 1/21/2023 18:00
169 Instrument 45h 1/18/2023 7:00 1/21/2023 16:00
170 HRSG PLC Panel Reaplacement 45h 1/18/2023 7:00 1/21/2023 16:00
171 Workshop 4h 1/18/2023 7:00 1/18/2023 11:00
1/18/2023 7:00 1/18/2023 11:00
172 CT401- Repl. of Spray Nozzles & Wooden Structure Inspection & Repair 4h
173 TK407- Tank Base Plate & Shell Painting 4h 1/18/2023 7:00 1/18/2023 11:00
174 Projects 252h 1/25/2023 19:00 2/5/2023 7:00
175 Gas Turbine Filters assembly Upgradation 252h 1/25/2023 19:00 2/5/2023 7:00
176 Total Power Shutdown 360h 1/18/2023 7:00 2/2/2023 7:00
177 Cooling Tower Basin Cleaning 72h 1/28/2023 7:00 1/31/2023 7:00
178 11kV Switchgear Preventive Maintenance + Inspection 36h 1/28/2023 7:00 1/31/2023 7:00
179 P411A - Overhauling of Pump 122h 1/18/2023 7:00 1/23/2023 9:00
180 P411B - Overhauling of Pump 122h 1/18/2023 7:00 1/23/2023 9:00
181 P411C - Overhauling of Pump 122h 1/18/2023 7:00 1/23/2023 9:00
182 PM of 11kV OCB's: 24h 1/28/2023 7:00 1/29/2023 7:00
183 PM of Distribution Transformers 60h 1/28/2023 7:00 2/2/2023 7:00
184 Transformer Oil Dehydration 60h 1/28/2023 7:00 2/2/2023 7:00
185 SS-1 Transformer Replacement 24h 1/28/2023 7:00 1/30/2023 7:00
186 Stack Battery Charger Repl. & Commissioning 8h 1/30/2023 7:00 1/30/2023 15:00
187 SS-1 LT Panels & MCC's PM 12h 1/31/2023 7:00 2/1/2023 7:00
188 SS-2 LT Panels & MCC's PM 24h 2/1/2023 7:00 2/2/2023 7:00
189 Start-up 466h 1/18/2023 7:00 2/6/2023 17:00
190 Bagging & Shipping 312h 1/18/2023 7:00 1/31/2023 7:00
191 Maintenance Phase 312h 1/18/2023 7:00 1/31/2023 7:00
192 Machinery 312h 1/18/2023 7:00 1/31/2023 7:00
193 EL302- Replace Bucket Elevation Chain 312h 1/18/2023 7:00 1/31/2023 7:00
194 Instrument 83h 1/18/2023 7:00 1/21/2023 18:00
195 BF301C- Bagging Machine Controller Repl. 83h 1/18/2023 7:00 1/21/2023 18:00