SEC BUILDTECH PVT. LTD.

PRW BILL BAMNIKHERA


CONTRACTOR NAME :- Kailsah
RA BILL :- 01
BILLING PERIODS :- Upto 31 Oct '21 DATE :- 31-Oct-21
Cumulative Bill Upto Previous Bill This Bill
Item
Material/Service Description Unit Rate
No
Qty. Amount (INR) Qty. Amount (INR) Qty. Amount (INR)
Palwal Box Drain
Providing and supplying labour for casting of Cast-In-Situ RCC Box
Drain as per drawing and design including leveling, dressing, PCC, R/F
1 steel cutting bending and binding as per BBS, Suttering providing and RMT 850 183.60 156060.00 0.00 0 183.60 156060.00
fixing, concreting and curing (Shuttering supporting, Binding Wire, All
Tools & Tackels, Concrete Vibrator etc by Contractor)
2 Supply Labour - Skilled for 8 Hours Per Day 450 0.00 0.00 0.00 0 0.00 0.00
3 Supply Labour - Unskilled for 8 Hours Per Day 350 0.00 0.00 0.00 0 0.00 0.00
Total 156060.00 0.00 156060.00
Deductions:
TDS 1% 1561 0 1561
SECURITY @5% 7803 0 7803
Debit for Fooding & Advance
Total Deduction 9364 0 9364
Less Adv:-

Net Pay Amount 146696.40 0.00 146696.40

Signature of PRW (Accepted) Signature of Billing Engg. Signature of P.M./G.M.


SEC BUILDTECH PVT. LTD.
Providing and supplying labour for casting of Cast-In-Situ Drain with Cover Slab as per drawing and design including leveling,
dressing, PCC, R/F steel cutting bending and binding as per BBS, Suttering providing and fixing, concreting and curing
(Shuttering supporting, Binding Wire, All Tools & Tackels, Concrete Vibrator etc by Contractor) Single Reinforcement with
cast-in-citu/pre-cast Cover Slab.

Chainage
S.No. Side Description Unit Length Quantity Bill No. Remarks
From To
1 68+528 68+559 LHS Construction of drain RMT 31.300 31.300 1
2 68+721 68+742 LHS Construction of drain RMT 21.000 21.000 1
3 68+786 68+832 LHS Construction of drain RMT 46.000 46.000 1
4 68+889 68+908 LHS Construction of drain RMT 19.300 19.300 1
5 68+941 68+966 LHS Construction of drain RMT 24.300 24.300 1
6 68+966 69+005 LHS Construction of drain RMT 39.000 39.000 1
7 68+742 68+744 LHS Construction of drain RMT 2.700 2.700 1

Total Qty Upto Date 183.60


Upto Previous 0.00
For This Bill 183.60

Accepted by : Prepared by : Checked By :

Kailash Sunil
(Labour Cont.) (Quantity Surveyor) (Project Manager)