You are on page 1of 3

TRANSMISSION AND DISTRIBUTION

Designing power factor correction


equipment for economic returns
by Dale Pudney, High Voltage Technology SA

The market for power factor correction (PFC) equipment in South Africa has been driven by the electricity tariffs related to power factor and
reactive energy. As a result, the market for industrial and mining PFC has been very quiet, but this is expected to change suddenly as Eskom
plans to implement a "low power factor" charge from July 2011.

The proposed charges are expected


to send a strong signal for customers
to improve their power factor with
compensation equipment and Eskom
expects that the payback period for most
customers will be less than one year.

Eskom network under stress


South African distribution systems are
currently stressed due to high loads and
limited capacity, with the result that Eskom
struggles to maintain the voltage at many
of their nodes. Because the tariffs have not
encouraged customer based PFC, Eskom Fig. 1: Load profile of a single shift operation.
has had to install its own reactive power
compensation equipment to strengthen
its networks and maintain voltage stability.

At the same time, many large industrial


and mining customers have PFC that was
installed in the late 90s (when Eskom was
changing from the kW to kVA maximum
demand and Megaflex time of use tariffs).
Much of this PFC is out of service due to
a lack of maintenance, changing loads
that make the PFC unsuited for the current
demand and general lack of attention due
the lack of financial incentives. If this PFC
had been available for service, it would
have assisted Eskom to relieve some of
the network stresses.

If customers were to install PFC on their


own networks, this would have the effect
of reducing the current drawn from the
supply and hence reduce the volt drop
losses on the supply system. By reducing
the total apparent power (MVA), the new
generation capacity required is also Fig. 2: Harmonic amplification.
reduced – hence getting customers to
install their own PFC is a demand side
management (DSM) initiative to reduce all load conditions, there is normally only  The switching philosophy
the amount of additional generation that a limited quantum of financial incentive
 The risk of unacceptable amplification
Eskom requires. Therefore PFC can also available in the tariff. Therefore, there
of critical harmonics
be considered a “green technology ” by are a number of PFC design principles
reducing the carbon footprint of industrial that are used to “optimise” the cost of  The risk of introducing switching
installations. the PFC installation with relation to the transients
available savings. Some of the key design
Most customers tend to buy PFC on a
Law of diminishing returns dimensions include:
fully turnkey basis, including all the design
While the costs can increase exponentially  The target power factor dimensions mentioned above, because it
to correct the power factor to near unity at  The number of steps required requires and experienced eye to design a

energize - November 2010 - Page 29


TRANSMISSION AND DISTRIBUTION

Average power factor <0,85 0,85 – 0,90 0,90 – 0,96 >=0,96 technically acceptable due to the risk of
amplifying critical harmonics. Therefore,
c/kvarh 5,51 3,94 2,36 0,39
the PFC needs to be installed as a detuned
Table 1: possible tariffs. capacitor bank (with filter reactors in
series) to avoid unacceptable harmonic
amplification, even amplification of
Maximum demand 6163 kVA @ Note that the two-step option, while “background” harmonics present on the
pf=0,795 being more expensive is also only plain supply system.
Monthly energy usage 1 821 496 kWh capacitor banks with only current limiting
Detuned capacitor banks are normally
reactors. The one-step option includes
Average power factor 0,811 “tuned” close the critical harmonics, to,
for filter reactors, which will assist to avoid say a 5th harmonic filter, as this will also
Excess reactive power 726 892 kvarh harmonic resonance as well as switching have the benefit of also filtering out these
Table 2: Key data from load profile. transients which current limiting reactors harmonics. Most harmonic filter banks are
are not effective at. installed to avoid unacceptable harmonic
resonance rather than to actually filter out
It is interesting to note that the actual
high harmonic levels.
capacitors are about 8% of the cost of a
PFC system that is both technically feasible
two step bank and about 12% of the cost A further advantage of PFC installed as
and economically optimised between the
of a one step bank. harmonic filter banks is that the series
capital costs and available savings.
reactors are relatively large (orders of
The advantage of the two step arrangement magnitude larger than current limiting
New tariff targets 0,96 power factor
is that it can track the reactive power reactors) and therefore have a significant
Eskom have not yet released what the low profile better, switching in either the 2 Mvar damping effect on switching transients
power factor charges will be, but they are or 1 Mvar steps or both to make 3 Mvar. that can be associated with switching
expected to be calculated as follows: This does result in more frequent switching, plain capacitor banks. These switching
 Measure the total kWh and kvah during but the power factor is higher for longer transients, if not damped, can have a
portions of the profile. There is however very detrimental effect on sensitive electronic
all billing intervals for the month's billing
little difference in the amount of savings. equipment, spurious tripping of household
cycle to determine the average power
earth leakage protection and other
factor for the month The different options do have a big problems unwanted in modern power
 Measure the kW and kVA during each difference in the payback periods, with systems.
30 min billing interval to determine the two step option taking 32,5 months
the excess kvarh (as per previous to pay for itself compared to 27,5 months Control the capacitor banks aligned to the
calculation) for the one step option. These differences objectives
 The rate of in c/kvar is then determined become more pronounced with further Low voltage capacitor banks are normally
from the average power factor steps compared to larger bank sizes. Each switched to target high power factor. On
(calculated from total kWh and kvarh installation needs to be designed for its medium and high voltage PFC, this is not
in the month) from each point of supply own unique costs and available savings. the best option, because of the lower
during the month, with the tariffs shown number of steps.
Detuned capacitor banks are often
in table 1 possible for large power users
required to avoid harmonic resonance The objective of installing PFC is to
(>1MVA):
generate the reactive power close to
La r g e c a p a c i t o r b a n k s c a n c a u s e
Fig. 1 shows a single shift load profile. This where it is needed and thereby reduce the
harmonic resonance due to the interaction
example has been used to illustrate some amount of reactive power required from
with the source inductance. Customer
of the points in this article. the supply authority. This in turn reduces the
loads do not need to have harmonic
line losses and total generation required by
Table 2 shows some of the key data from sources in them for harmonic resonance
Eskom, which is why they reward customers
the load profile: to be a problem as there are always
for having a good power factor. But the
harmonics naturally present on the
Based on the tariff outlined above, this objective is to reduce reactive power
system, caused by other customers on
customer would incur an additional low and not to have a high power factor for
the interconnected network. Fig. 2 shows
power factor charge of about R40 000 its own sake.
the typical harmonic amplification plot
per month due to low average power
due to parallel resonance. Therefore, it is appropriate to control
factor. We will use this charge to determine
medium voltage PFC by reactive power
what savings might be achieved with the The rule of thumb calculation of the demand from the supply rather than to
installation of PFC. resonance point is f n = √MVA/PFC where target a high power factor – the PFC
MVA is the fault level in MVA and PFC is output is in terms of reactive power and
Reduce the number of steps for lowest
the capacitor size in Mvar. To be safe, the the objective is to reduce reactive power
capital cost
resonance point should be above about 8 demand from the supply.
With modern capacitor banks, the fixed and avoid other critical harmonics. It is not
costs required for each step dominate safe to try and avoid the critical harmonics The result is that the supply power factor
the total costs, while the actual cost of the (5th, 7th, 11th, 13th, etc.) by positioning the can go leading in times of lower load.
capacitors can be a small portion of the resonance point between them, due to the While most customers' supply agreements
costs. The following are budget prices for “width” of the resonance curve. require them not to go leading, technically
this is not a problem unless the voltage
two different configurations at 11kV:
In a typical 11kV supply, 3 Mvar of PFC rise becomes excessive from ver y far
 2 step 3 Mvar (2Mvar + 1 Mvar) plain would need to be installed as a detuned leading supplies that drive transformers
capacitor bank – R1300 capacitor banks. Hence as well as being into saturation. Fig. 3 shows our customers'
 1 step 3 Mvar detuned capacitor bank more expensive, a 2 Mvar + 1 Mvar load profile with 3 Mvar of PFC installed as
(5th harmonic filter) – R1100 2-step arrangement would typically not be a single step.

energize - November 2010 - Page 30


TRANSMISSION AND DISTRIBUTION

Fig. 3: PFC switching forecast.

Optimise the savings vs. capital cost of the considerations that are involved superior solution for each application – an
relationship with designing PFC that is optimised for untrained eye might be too dependent
maximum economic returns, designing on computer simulations and miss critical
As can be seen, the supply does go
leading at some times by up to about optimised PFC is more like an art than a aspects that have a major impact on the
1 Mvar, which is fully acceptable. science. The sheer number of different design optimisation.
options that need to be evaluated can
Designing optimised power factor become excessive. Contact Dale Pudney,
correction is an art High Voltage Technology,
It takes experience and a gut feel to be
While we have tried to simplify some able to quickly and effectively design a Tel 012 666-9358, dale@hvt.co.za 

energize - November 2010 - Page 31

You might also like