Professional Documents
Culture Documents
S3-43 - Tower 2 Shear Wall Sections
S3-43 - Tower 2 Shear Wall Sections
OWNER
TYP CORNER
1200
THOMAS F. MIRASOL
T2-D T2-D
450
450
450
450
CHIEF OPERATING OFFICER, SENIOR VICE
PRESIDENT & GENERAL MANAGER
REAL ESTATE DIVISION
ARCHITECT OF RECORD
GF & Partners
A r c h i t e c t s
ANNETTE F. GADDI-LIGANOR
A R C H I T E C T
PRC REG. NO. : 6813 DATE: 11-12-1982 TIN : 108-782-800
PTR NO. : 4754954 DATE: 01-12-2015 PLACE : MAKATI CITY
TEODORO H. NARCISO TEOFILO A. SANTIAGO JR.
ANNETTE F. GADDI-LIGANOR ARNULFO M. VILLANUEVA
XAVIER ANTONIO J. GARCIA
11TH FLOOR, BDO PLAZA, 8737 PASEO DE ROXAS, MAKATI CITY, PHILIPPINES
TELEPHONE (632) 553-7232 FAX (632) 553-7230 E-MAIL: postmaster@gfparchitects.com
STRUCTURAL
incorporated
ASSOCIATES JOSE A. SY
450
450
450
450
STRUCTURAL ENGINEER
T2-F T2-F Unit 504 Pryce Center, 1179 Chino Roces Avenue
cor. Bagtican St., Makati City REG. NO. 22404 TIN 123-489-697
Telephone No. 896-97-04 to 05
Fax No. 896-97-60 to 61 PTR NO. 5330036 DATE 01-07-16
e-mail address: info@sysquared.com PLACE MAKATI CITY
ELECTRICAL
E F R E N B. C R U Z
TYP END
TYP END
PROFESSIONAL ELECTRICAL ENGINEER
1200
1200
MECHANICAL
CROSSTIES & HOOPS CROSSTIES & HOOPS CROSSTIES & HOOPS CROSSTIES & HOOPS
AT 150mm VERT SPCG AT 150mm VERT SPCG AT 150mm VERT SPCG AT 150mm VERT SPCG PROF. MECHANICAL ENGINEER
SANITARY ENGINEER
FIRE PROTECTION
DCCD ENGINEERING CORPORATION
SOL BUILDING 112 AMORSOLO ST., MAKATI M.M.
TEL. NOS. 892-45-86 TO 89
CROSSTIES & HOOPS CROSSTIES & HOOPS CROSSTIES & HOOPS CROSSTIES & HOOPSPTR NO.
ISSUED ON.
REG. NO.
TIN
AT 150mm VERT SPCG AT 150mm VERT SPCG AT 150mm VERT SPCG AT 150mm VERT SPCG
ISSUED AT
CONSTRUCTION MANAGER
T2-H T2-H
QUANTITY SURVEYOR
NOTES: NOTES:
1. ALL CROSSTIES AND HOOPS TO BE T16 @ 120mm VERTICAL SPACING WITH Fy = 60 KSI TYPICAL, UNLESS NOTED OTHERWISE. 1. ALL CROSSTIES AND HOOPS TO BE T16 @ 120mm VERTICAL SPACING WITH Fy = 60 KSI TYPICAL, UNLESS NOTED OTHERWISE.
Arcadis Philippines, Inc.
2. CONCRETE COVER TO REINFORCING IS 25mm. 2. CONCRETE COVER TO REINFORCING IS 25mm. 4th Floor King's Court 1, 2129 Pasong Tamo Makati City
Tel: +632 8112971 Fax: +632 8112071
3. ADDED VERTICAL REINFORCING IN BOUNDARY ELEMENTS AT WALL ENDS TO MATCH SIZE OF WALL REINFORCING. 3. ADDED VERTICAL REINFORCING IN BOUNDARY ELEMENTS AT WALL ENDS TO MATCH SIZE OF WALL REINFORCING. E-mail: info-ph@arcadis.com www.arcadis.com
AT CORNERS, MATCH REINFORCING SIZE OF THE LARGER OF THE TWO WALLS. AT CORNERS, MATCH REINFORCING SIZE OF THE LARGER OF THE TWO WALLS.
REVISIONS
NO. DATE DESCRIPTION
NOTES:
PURPOSE OF ISSUANCE
PROGRESS PLANS
SHEET CONTENTS