Professional Documents
Culture Documents
SJMS To Update Lists
SJMS To Update Lists
Done 4
Pending 36
TOTAL 40
S/N SOR No. User / Dept Location
1 SJQ21/W545R1 THK T1A37 & T1A38
2 SJQ21C577R2 ASA T12 L1 Workshop ABCD
15/2/2022 Pending
2/8/2021 Done
23/9/2021 Pending
21/7/2021 Pending
11/4/2022 Pending
3/1/2022 Pending
3/1/2022 Pending
3/1/2022 Done
3/1/2022 Done
21/3/2022 Pending
11/11/2021 Pending
26/10/2021 Pending
26/10/2021 Done
11/4/2022 Pending
23/3/2022 Pending
3/1/2022 Pending
12/4/2022 Pending
29/4/2022 Pending
23/11/2022 Pending
23/11/2022 Pending
27/4/2022 Pending
27/7/2022 Pending
11/1/2022 Pending
18/10/2022 Pending
8/9/2022 Pending
19/10/2022 Pending
24/2/2023 Pending
24/2/2023 Pending
30/6/2023 Pending
16/3/2023 Pending
16/3/2023 Pending
21/4/2023 Pending
21/4/2023 Pending
3/5/2023 Pending
30/5/2023 Pending
1/6/2023 Pending
22/6/2023 Pending
22/6/2023 Pending
S/N SOR No. User / Dept Location Job Scope
200 HID Cards 100 Acad 100 Non Acad with
3 SOR800291A HR HR Admin bld 101
Printing & Programming
27 SOR800255 Mr Wilkie Ong W515 Replace 1 x faulty IP Camera at W515
Andy Yak_x000D_ Hoyi System Integration of existing CAS with Fire
40 SJQ0323-52 SEN T17 L2
9236 1136 Alarm Panel with testing commissioning
Andy Yak_x000D_ Hoyi Andy New CAS items to supply and install at
42 SJQ0623-84R1 W3110E
9236 1136 W3110E
T11B303, T11B102 and
46 SOR800289R1 replacement of 12 cctv cam and power adaptor
T11A202
49 SOR800289R1 Ms Tan Chiao Ning Supply of CCTV Sign board
Work in Progress 2
Pending UAT 0
Pending Fonda
8
DO
Pending SJ DO 2
TOTAL 47
T1A37 &
1 SJQ21/W545R1 THK
T1A38
T12 L1
2 SJQ21C577R2 ASA Workshop
ABCD
T12 L1
3 SJQ21C578R3 ASA Workshop
ABCD
Ms Connie
6 SOR800009 CLS T11BL2
Chow
LT18B
Ms Jovia
17 SOR800075R2 Bouldering
Low
Gym
Mr Azlan / P-
28 SOR800127 T21L1 and L4
Jay Fonda
Mr. P-Jay
29 SOR800128 W319
Fonda
Mr. P-Jay
30 SOR800132 T15L7
Fonda
Mr. P-Jay
31 SOR800135 T21 Level 2
Fonda
Mr. Hong T19434,
32 SOR800143
Guan Soh T1941, T2249
Mr. P-Jay
33 SOR800148 Library
Fonda
Mr. P-Jay
34 SOR800146 INDT office
Fonda
See Thiam
44 SJQ0622-17 W511
Lye
T12505 &
45 SOR800177 Ms Tan
T12506
LT18B
Ms Jovia
48 SOR800075R2 Bouldering
Low
Gym
49 SOR800214 Beng Ha AMEC
SOR800221R1 Sharon Ang FC5 Gym
Mun Seok
SOR800183 W317
Ch
Supply and install 17 new IP CCTV Installation completed. IP all set, UAT signed DO
system requested
Supply and Install new CAS, Installation completed. IP all set, UAT signed DO
1Entrypass, 3 IEI requested
Disable, Connect to Fire Alarm & Connected and tested linked with Fire Alarm,
enable CAS waiting for handover date to enable back the CAS.
Supply & install new set of IEI Card CAS Installation completed, pending programming
Access System and BMS to CAS testing, Scheduled Jan 12 2022
Supply & install 5 new IP CCTV system Job Completed, waiting for DO from Fonda to sign
Supply & Install 2 new IEI CAS Installation and Testing completed.
Supply & Install 7 new IEI CAS Requested DO from office then Fonda to sign
Install additional relay to interface CAS Job Completed, Requested DO from office then
with Fire alarm Fonda to sign
Supply & install new set of IEI Card CAS Installation completed, pending programming
Access System and BMS to CAS testing, Scheduled Jan 12 2022
Supply & install new set of IEI Card CAS Installation completed, pending Fire and BMS
Access System to CAS testing, Scheduled April 18 2022
Supply and configure 3 wireless remote
Supply and install completed
control
Replacing Faulty CAS set Wrong quote, waiting for other items
Supply and Install 2 additional new
Supply and install 2 new cameras completed
CCTV
Supply and install additional relay to
Job Completed
interface CAS with Fire alarm
Supply and Install CCTV system for Supply and install CCTV completed
T11AL6 Training for CCTV usage scheduled on May 6
Supply and install 32 new IP CCTV
CCTV installation ongoing - overall 80% completed
system
CAS installation ongoing - overall 70% completed
Supply & install 18 new IEI Card
4 CAS DB to relocate, extra labour will be charged
Access System
to Maincon.
To supply & install 1 x bypass switch
(key type)
with 2 keys & 1 x wireless remote Job Completed, witing for SJ DO
control receiver
with 2 wireless control
Supply & install 2 doors with user
provided Controllers and DB box
Job Completed, witing for SJ and Fonda DO
additional 2x EMlock & 2 x Break glass
for back door.
Library Level 1 & L2
Supply & install 4 doors with new set of Job Completed, witing for SJ and Fonda DO
IEI Card Access System
Main Library
Waiting for cameras
3 x Additional Axis camera
TOTAL 3 1 52 7 71 73 73
Powerpack
14
9
3
1
4
7
17
55