Professional Documents
Culture Documents
net/publication/273832856
CITATIONS READS
43 2,349
4 authors, including:
Abdelmalek Bouazza
Monash University (Australia)
218 PUBLICATIONS 2,344 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Arul Arulrajah on 22 March 2015.
A high-speed railway project for trains of speeds of up to P peak angle of shear stress
160 km/h is currently being constructed between Rawang Pall coll allowable load on the column
and Bidor (110 km long) in Peninsular Malaysia. The s spacing of the columns in square grid pattern
ground improvement methods adopted in the project T shear stress
are vibro-replacement with stone columns, dry deep soil Th time factor for consolidation by horizontal drainage
mixing (cement columns), geogrid-reinforced piled t time
embankments with individual pile caps and removal/ U degree of consolidation
replacement works. This paper provides a detailed Us degree of settlement
insight into the design and implementation of vibro- Up average degree of pore pressure dissipation
replacement and the deep soil mixing treatment v volume of the element
methods used in the project. The use of plate bearing imp imposed stress due to dead load and live load on top
tests and field instrumentation to monitor the of the ground surface
performance of the stone columns and soil mixing ªc unit weight of column
ground treatment methods is also discussed. This paper ªf unit weight of fill
also provides a brief overview of other treatment allowable strain (ultimate)
methods implemented in this high-speed railway project all col allowable creep stress
such as a pile embankment with geogrids and removal/ fcol failure stress
replacement works. creep col creep stress of column
h horizontal stress calculated at the top of soft layer
NOTATION v9ert vertical stress
Acol /A area ratio d col undrained shear stress of the column
Acol area of column u col undrained shear stress of the column
a area replacement ratio calculated as a ¼ (Acol /s 2 ) for 9 friction angle of the composite system
square grid pattern of spacing, s c friction angle of column
C cohesion of the composite system d col drained angle of friction of the column
Cu undrained shear strength of the soil d comp drained angle of friction of composite soil
Cd comp drained cohesion of composite soil u comp undrained angle of friction of composite soil
Cu comp undrained shear strength of composite soil d soil drained angle of friction of the in situ soil
ccreep col creep stress of the column s friction angle of the soil layer
cd col drained cohesion of columns u col undrained angle of friction of columns
cd soil drained cohesion of in situ soil u soil undrained angle of friction of in situ oil
ch coefficient of consolidation for horizontal flow
cu col undrained cohesion of the column 1. INTRODUCTION
cu soil undrained cohesion of the in situ soil The electrified high-speed railway project runs between
Dc constrained moduli of columns Rawang in the state of Selangor and Bidor in the state of Perak
Ds constrained moduli of soil in Peninsular Malaysia over a total length of 110 km. Figure 1
d diameter of column indicates the location of the project site in Peninsular Malaysia.
de diameter of the equivalent soil cylinder The geotechnical design of the project includes ground
Ecol Young’s modulus of the columns improvement of the existing foundation to sustain the imposed
Ecomp Young’s modulus of composite soil dead and traffic loads for train speeds of up to 160 km/h. The
Esoil Young’s modulus of the in situ soil client’s design requirements are a maximum post-construction
m9 proportional load on the column settlement of 25 mm in six months and a differential
mc constant settlement of 10 mm over a chord spanning 10 m. In addition,
mE constant the degree of consolidation to be achieved is not to be lower
n2 final improvement factor than 85–90%. The required minimum long-term factor of
Ground Improvement 162 Issue GI1 Ground improvement techniques for railway embankments Arulrajah et al. 3
Delivered by ICEVirtualLibrary.com to:
IP: 136.186.1.187
Wed, 26 May 2010 00:59:09
width of the embankment
under the new track only.
Proposed Double Track
Stations and Halts
Treatment for the second
stage would include
treatment under the proposed
rehabilitated track which
KELATAN would be carried out once the
IPOH
train operations had been
shifted to the new live track.
PENANG
PERAK
BIDOR (km 245·5) 2. VIBRO-
ST
RA
ST
KUALA
S
STONE COLUMNS
OF
RA
LUMPUR
IT
Vibro-replacement with stone
MA
S SELANGOR
LA
OF columns is a subsoil
RAWANG (km 355·5)
CC
MA
improvement method in
A
LA
PENINSULAR SINGAPORE which large-sized columns of
CC
KUALA LUMPUR
MALAYSIA
A
coarse backfill material are
installed in the soil by means
of special depth vibrators.
The stone columns and the
intervening soils form an
Figure 1. Location of project site in Peninsular Malaysia integrated foundation support
system having low
compressibility and improved
safety for slope stability was 1.5. Due to the stringent load-bearing capacity. Vibro-replacement with stone columns
settlement restrictions and the fast-track nature of the project, allows for the treatment of a wide range of soils, from soft
an array of ground improvement techniques had to be clays to loose sands, by forming reinforcing elements of low
implemented in locations with soft soils or loose sands on compressibility and high shear strength. In addition to
which proposed high embankments were identified. Ground improving strength and deformation properties, stone columns
improvement was thus required to ensure adequate densify in situ soil, rapidly drain the generated excess pore
performance of the embankments in terms of settlement and water pressures, accelerate consolidation and minimise post-
slope stability as well as completion of the project within the construction settlement. Normally the columns fully penetrate
required project duration. the weak layer with the result that the stone column and
natural soil combination develops greatly enhanced bearing
This paper provides a detailed insight into the vibro capacity and reduced compressibility characteristics. The
replacement with stone columns and dry deep soil mixing method is an ideal solution for use in embankments as it
treatment methods applied in the project. Vibro replacement negates the effect of a ‘hard point’. The dry or wet method of
with stone columns is a subsoil improvement method in which installation can be used depending on the proximity to the
large-sized columns of coarse backfill material are installed in existing railway track and water sources. The size of the
the soil by means of special depth vibrators. Dry deep soil vibrator is around 40 cm and penetration of the vibrator into
mixing technology is a development of the lime–cement the ground with water jetting will result in a hole of diameter
column method. This paper also briefly discusses piled 50–60 cm being created. An annular space is created between
embankments with geogrids and removal/replacement, which the vibrator and the hole through which the stone is fed to the
were also treatment methods adopted in this project. compaction point. The up and down motion of the vibrator is
used to laterally displace the stone into the ground and at the
The railway embankments in the project have heights ranging same time compact the stone column. This will result in the
from 1 to 12 m. The top of the embankment has a minimum creation of the required diameter of column. Figure 2 presents
width of 14.9 m for embankments less than 10 m in height and
a width of 24.9 m for embankments greater than 10 m in
height. The side slopes of the embankments have gradients of
1V:2H. Berms of 3 m width are provided on either side of A
embankments which were greater than 5 m in height. The soils
encountered on the project site are highly variable mixtures of
very soft silts and clays, as well as loose sands to depths of up
to 30 m. Two approaches were needed for the treatment process
due to construction constraints: (a) treatment of the full width
of the embankment was required in locations where the new
alignments needed the construction of two new tracks; (b)
treatment at locations where a new track was to be first
Figure 2. Schematic illustrating the stone column installation
constructed while the existing live track was to be later process (courtesy of Keller)
rehabilitated. Treatment in the first stage would be for the
4 Ground Improvement 162 Issue GI1 Ground improvement techniques for railway embankments Arulrajah et al.
Delivered by ICEVirtualLibrary.com to:
IP: 136.186.1.187
Wed, 26 May 2010 00:59:09
a schematic diagram illustrating the installation process of portion of the load, m9, which depends on the area ratio, Acol /A,
stone columns. and the final improvement factor n2 . The process described
below has to be repeated for each of the various soil layers
2.1. Stone column design methodology
The following idealised conditions are assumed in the design: 4 m9 ¼ ð n2 1Þ=n2
the column is based on a rigid layer; the column material is
incompressible; the design considers the group effect of the
columns and the contribution of the attributable soil where m9 is the proportional load on the column.
surrounding the columns; column material shears from the
beginning whereas the surrounding soil reacts elastically. The cohesion of the composite system depends on the
proportional area of the soil and can be calculated as follows
2.1.1. Settlement. Settlement under the embankment loads
was calculated using the Priebe method. 1 This method gives 5 C9 ¼ ð1 m9Þ C u
consideration for improvement, overburden and compatibility
control with the use of the various improvement factors. The
process is repeated for each of the various soil layers. The where C9 is the cohesion of the composite system and Cu is the
reader is referred to Priebe, 1 Arulrajah and Affendi 2 and Bo undrained shear strength of the soil.
and Choa 3 for further details on the methodology of the
settlement design for stone columns. The shear resistance from the friction of the composite system
can be determined as follows
2.1.2. Time rate of settlement. Time rate of settlement can be
calculated by using the Terzaghi equation. The time factor for a 6 tan9 ¼ m9 tanc þ ð1 m9Þtans
degree of consolidation of 90% can be obtained from the
Balaam and Booker chart, 4 shown in Figure 3, which is
applicable for rigid inclusions. The equations relevant to these where 9 is the friction angle of the composite system; c is
calculation are as follows the friction angle of the column; and s is the friction angle of
the soil layer.
1 t ¼ Th d2e =ch
2.1.4. Stability. The improved cohesion and friction angle
values of the soil–column matrix is calculated from the final
2 de ¼ 1:128 3 spacing (for square grid) improvement factor, n2 , and these values are input into a slope
stability analysis program to attain the factor of safety of the
improved ground.
3 Th ¼ 0:044
2.1.5. Design details. Based on the analyses of the stone
column areas, the following design parameters and design
(Balaam and Booker chart for U ¼ 90%, de /d ¼ 3), where t is spacing were adopted
time; Th is the time factor for consolidation by horizontal (a) diameter of column, d ¼ 0.8 to 1.0 m
drainage; de is the diameter of the equivalent soil cylinder; and (b) unit weight of column, ªc ¼ 22 kN/m3
ch is the coefficient of consolidation for horizontal flow. (c) friction angle of column, c ¼ 408
(d) constrained moduli of columns, Dc ¼ 120 MPa
2.1.3. Strength properties of improved ground. Stone columns (e) constrained moduli of soil, Ds ¼ 100 3 Cu ¼ 500 3 SPT
deform until any overload has been transferred to the (f) unit weight of fill, ªf ¼ 20 kN/m3
neighbouring soil. The stone columns receive an increased (g) traffic load ¼ 30 kN/m3 .
0
For soft soils conditions encountered in the Rawang to Bidor
Barron’s solution
Biot theory stretch, stone column spacings were generally in the range 1.8–
0·2
E1/E2 ⫽ 40 10 1 2.3 m for embankment heights of 5–12 m.
0·4 de
Us
d
Predicted total settlements were of the order of 0.3–0.5 m.
Rigid
Up
0·6 Factors of safety for slope stability were greater than 1.5. Time
E1 E2 Raft
v1 v2 required for 90% degree of consolidation in the predominantly
kh sandy silts was less than two months. The treatment area ratio
0·8
Smooth Rigid
for the stone columns varied from 13 to 20%, depending on
v1 ⫽ 0·3, v2 ⫽ 0·3
1·0 the design spacings for the stone columns.
0·0001 0·001 0·01 0·1 1·0
c rt
Th ⫽ 2.2. Stone column installation
d 2e
Arulrajah et al.,5 have described the soil conditions and soil
parameters relevant for stone column design in the project site.
Figure 3. Time rate of settlement of stone columns for
de /d ¼ 3 (Balaam and Booker4 ) The results of site investigations revealed the presence of a
wide range of soils along the track, ranging from very soft silty
Ground Improvement 162 Issue GI1 Ground improvement techniques for railway embankments Arulrajah et al. 5
Delivered by ICEVirtualLibrary.com to:
IP: 136.186.1.187
Wed, 26 May 2010 00:59:09
clay or clayey silt to loose silty clayey sand. Figure 4 shows a new alignment. Figure 6 shows the schematic diagram of stone
typical cone penetration test (CPT) plot at one such stone column treatment works as carried out in the project at
column treatment location. locations next to the existing railway track.
Stone columns were used to treat soils over about 14 km length 2.3. Plate load testing on stone columns
of the railway line. Approximately 1 100 000 linear metres of After completion of stone column installation, plate load tests
0.8–1.0 m diameter stone columns were installed on the project were carried out on single-columns, or groups of four columns
site to depths of 6–30 m. for acceptance purposes. The load was applied on the stone
column and the soil surrounding the column. For the first cycle,
Figure 5 shows the schematic diagram of stone column the allowable design load was applied and maintained for a 24 h
treatment works as carried out in the project at locations of duration. In the second cycle, a maximum load of 150% of the
Tip resistance Qc: MPa Friction Fs: kPa Friction ratio: % Pore pressure Pw: kPa
0 1 2 3 4 5 0 25 50 75 100 0 1 2 3 4 5
0 0 200 400 600 800 1000
0 0 0
1 1 1 1
2 2 2 2
3 3 3 3
4 4 4 4
5 5 5 5
6 6 6 6
7 7 7 7
8 8 8 8
9
Depth: m
9 9
Depth: m
9
Depth: m
Depth: m
10 10 10 10
11 11 11 11
12 12 12 12
13 13 13 13
14 14 14 14
15 15 15 15
16 16 16 16
17 17 17 17
18 18 18 18
19 19 19 19
20 20 20 20
Figure 4. Plot of typical pre-treatment CPT result at stone column location (chainage 352130)
Embankment S
CL
4950 Min. 5000 4950 1000 mm∅
New track Rehab. track
CL CL 300 mm sub-ballast
1·5 1·5
2 1 1 2
1 1 3000
5·0% 5·0%
Formation
1 m compacted 1 1
1 5000 mm 2
2 sand blanket 2
max.
1000 mm∅
stone column Soft/loose
L material
Embedded in
SPT N ⭓ 10
S
Dense layer
W
Figure 5. Schematic of stone column treatment scheme for new alignment comprising two new tracks (dimensions in mm)
6 Ground Improvement 162 Issue GI1 Ground improvement techniques for railway embankments Arulrajah et al.
Delivered by ICEVirtualLibrary.com to:
IP: 136.186.1.187
Wed, 26 May 2010 00:59:09
S
Embankment
CL S
4950 Min. 5000 4950
Suitable fill material
compaction in layers
New track Rehab. track 1000 mm∅
CL CL
1 m compacted 300 mm sub-ballast
sand blanket
1·5 1·5
1 1
2
1 2
5·0% 5·0% 1
Existing Fill
Existing
ground
Formation ground
Soft/loose
material L 1000 mm∅
Embedded in
stone column
SPT N ⭓ 10
Dense layer S
Figure 6. Schematic of stone column treatment scheme for partial width treatment next to the existing railway track
(dimensions in mm)
design load was applied. The acceptance requirement of the load surface settlement plates and settlement markers. The surface
test was that the settlement should not exceed 50 mm under the settlement gauges on site consistently indicated settlements
allowable design load and not exceed 80 mm under 150% of the occurring for each additional lift and minimal post-
allowable design load. The size of plate used for the load test was construction settlements. Figure 9 presents typical results from
1.5 m by 1.5 m for a single column and 3 m by 3 m for a group of a settlement plate installed on the project site. Figure 10
four columns. Figure 7 presents the schematic diagram showing presents a typical Asaoka plot for the said settlement plate,
the plate load test set-up for a single column load test. The results which indicates that the degree of consolidation of the
of a typical single column plate load test carried out in the project improved ground at the location had achieved 94%. The long-
are presented in Figure 8. term performance of the stone columns were predicted by
means of the Asaoka method of back-analyses based on the
2.4. Field instrumentation of stone columns field settlement results. Settlement markers were also placed to
Extensive field instrumentation was carried out in the stone monitor the long-term performance of the stone columns after
column treatment areas after the installation of the stone the railway tracks were placed. The long-term monitoring
columns. The majority of the field instrumentation comprised results indicated that the stone columns had performed very
Crane
Crane tracks
Firm fill
Dial gauge Jack
Reference
Top of sand platform beam
1 m nominal diameter
stone column
Figure 7. Schematic diagram showing single column plate load test set-up
Ground Improvement 162 Issue GI1 Ground improvement techniques for railway embankments Arulrajah et al. 7
Delivered by ICEVirtualLibrary.com to:
IP: 136.186.1.187
Wed, 26 May 2010 00:59:09
0·0 320
First load cycle to allowable design load
0·5 Second load cycle to 1·5 times allowable design SPR(N)⫺261: 7-day intervals
1·0 45° line
1·5 280 Ultimate settlement, Sult ⫽ 282 mm
Settlement: mm
2·0 2·11 mm
2·5
Settlement (i): m
3·0 240
3·5
4·0
4·5 4·2 mm 200
5·0
0 40 80 120 160 200 240 280 320
20 60 100 140 180 220 260 300
Load: kN
160
Degree of consolidation ⫽ St /Sult
Figure 8. Load–settlement curves for a single column plate ⫽ 265·3/282
load test (chainage 352066) ⫽ 94%
120
120 160 200 240 280 320
Settlement (i ⫺ 1): m
6·0
5·5
5·0 Figure 10. Asaoka plot and determination of degree of
Embankment height: m
8 Ground Improvement 162 Issue GI1 Ground improvement techniques for railway embankments Arulrajah et al.
Delivered by ICEVirtualLibrary.com to:
IP: 136.186.1.187
Wed, 26 May 2010 00:59:09
the deep soil mixing process is a soil mass in the shape of a Soil description mc mE
cylindrical column with improved deformation and shear
resistance characteristics. Clayey silt 0.8–0.9 150–200
Silty clay 0.8 150–200
3.1. Dry deep soil mixing design methodology Clay 0.7–0.8 150
The design philosophy for dry DSM is to produce a stabilised Organic clay 0.6–0.7 100
Peat 0.6 50–75
soil mass that mechanically interacts with the surrounding Silty, clayey sand 0.9 200–250
natural soil. The intention is not to produce rigid pile-like
elements which will carry all the load. This method of semi- Table 1. Values of constants mc and mE applicable for deep
rigid stabilisation is often referred to as the ‘soft treatment’. soil mixing design
The ‘soft treatment’ can be achieved by designing with low
binder contents, which can achieve improved shear strength
values (typically undrained shear strengths ranging between
11 Pall col ¼ all col Acol
100 and 250 kPa depending on characteristics of the in situ
soil). The applied load is partly carried by the columns and
partly by the natural soil between the columns. Therefore, a too The spacing of the columns in square grid pattern can be
rigidly stabilised material is not necessarily the best solution assessed as
since such a material will prevent an effective interaction and
load distribution between the stabilised soil mass and 0:5
Pall col
surrounding natural soil. 12 s¼
imp
Ground Improvement 162 Issue GI1 Ground improvement techniques for railway embankments Arulrajah et al. 9
Delivered by ICEVirtualLibrary.com to:
IP: 136.186.1.187
Wed, 26 May 2010 00:59:09
embankment. The strength of the columns used directly under
19 u comp ¼ tan1 [a tan(u col ) þ (1 a) tan(u soil )] the proposed track was 250 kPa and that used in other areas
was 150 kPa. Figure 12 shows the schematic diagram of dry
deep soil mixing treatment works as carried out in the project
20 d comp ¼ tan1 [a tan(d col ) þ (1 a) tan(d soil )] at locations of new alignment.
3.2. Dry deep soil mixing installation 3.4. Field instrumentation of dry deep soil mixing
The results of soil investigation at the treatment area revealed During the construction of the embankment over the treated
the presence of a wide range of soils along the track, ranging ground, settlements and lateral movements of the embankment
from very soft silty clay or clayey silt to loose silty clayey were monitored using rod settlement gauges and inclinometers.
sand. 11 Figure 11 shows a typical CPT plot at the DSM Typical results from the rod settlement gauges are shown in
treatment location. Fig. 15. The settlement gauges showed virtually no settlement
(, 10 mm) for an embankment of height ranging from 1 to
Deep soil mixing treatment was used to treat soft soils over an 1.5 m. Typical results of lateral displacement (perpendicular to
800 m length of the railway line. Over 50 000 linear metres of the alignment of the embankment) are shown in Figure 16. The
0.6 m diameter columns were installed at the site to depths of inclinometers showed lateral movements to be within 15 mm in
6–14 m. 11 The embankment heights in the DSM treatment the direction perpendicular to the embankment alignment. The
areas varied between 1.5–3 m. Column spacing generally inclinometer measurements presented in the figure were
ranges between 1.0–1.5 m. Typically the spacing of the column monitored for seven months. Maximum displacement was
grids (square/rectangle) varies between 1.0–1.3 m centre to observed at the ground level. 11 Details of the field
centre under the location of the proposed rail tracks and 1.4– instrumentation of the dry deep soil mixing works at the
1.5 m centre to centre in the remaining area underneath the project site have been described by Raju. 11
4
Depth: m
10
12
Maximum depth ⫽ 11·00 m Depth increment ⫽ 0·05 m
Figure 11. Plot of typical pre-treatment CPT result at deep soil mixing location (chainage 341690)
10 Ground Improvement 162 Issue GI1 Ground improvement techniques for railway embankments Arulrajah et al.
Delivered by ICEVirtualLibrary.com to:
IP: 136.186.1.187
Wed, 26 May 2010 00:59:09
14·90 m
5·0 m
Ridge
2·5 m CL 2·5 m
2·62 m 2·62 m
New track Rehab. track
CL CL
Working
Existing Embankment
platform
ground
0·6 m dia.
cement
columns
Treatment ⫽ 22·90 m
Figure 12. Schematic of dry deep soil mixing treatment scheme (Raju 11 )
10
0
Grillage beams
⫺10
⫺20
RSG-3 RSG-6
Sand blanket
Cement
Figure 15. Time–settlement plot showing the typical results of
columns rod settlement gauges installed in a deep soil mixing
treatment area
Load: t 4
0 20 40 60 80 100 120
0 8
Depth: m
12
⫺2
Settlement: mm
16
⫺4
20
⫺6
24
Ground Improvement 162 Issue GI1 Ground improvement techniques for railway embankments Arulrajah et al. 11
Delivered by ICEVirtualLibrary.com to:
IP: 136.186.1.187
Wed, 26 May 2010 00:59:09
the embankment transferred through arching action between bridge hard point.5,14 Figure 18 shows a schematic diagram of
adjacent pile caps and finally where a geogrid is used and laid geogrid-reinforced piled embankments used for the railway
over the pile caps its tension will provide support and prevent bridge approach transitions.
lateral spreading of the embankment. The advantage of using
geogrids is that geogrids absorb the stress induced during 5. REMOVAL/REPLACEMENT
construction until arching is formed and prevents lateral This method is possibly the most widely used and economical
movement of the soil. The design of the geogrids involves treatment option for improving the presence of shallow soft
calculations for the serviceability and ultimate limit states, soil deposits. The removal and replacement method was used in
which incorporate the future, anticipated dead and live loads. the project at locations where there was soft cohesive material
Individual pile caps were designed for usage with the geogrids present. The unsuitable materials were removed from the site
as they were found to be more economical in comparison with and the excavation trench and they were replaced with suitable
a continuous slab. In the project, piles of size 250 mm by fill materials, which were subsequently compacted. 5 Excavation
250 mm (Concrete Grade 45) were installed at 1.5 m square to depths greater than 2 m may require temporary protection
spacing. The geogrid design was carried out as per BS 8006, 12 methods such as the use of temporary sheet piles. Non-woven
and incorporated the published method of Hewlett and geotextiles were provided as a separation layer at the base of
Randolph, 13 utilising allowable strain (ultimate) ¼ 12% and the excavation works to ensure an effective separation between
allowable strain (serviceability), ¼ 5%. A sand blanket was the in situ soils at the base of the excavation and the suitable
also provided just below the pile cap to provide a working fill. Figure 19 shows a schematic drawing of the removal and
platform and some lateral restraint on the pile during driving. replacement works.
Figure 17 shows the schematic drawing of geogrid-reinforced
piled embankments. 6. CONCLUSION
In this paper, the various ground improvement techniques used
For the design of transitions to railway bridges, the pile lengths in a major high-speed railway project in Malaysia have been
were reduced by 1 m for each pile spacing from the integrated discussed.
bridge abutment slab. By this approach, the piles near the
bridge are long and will settle little since they were designed to Vibro-replacement with stone columns allows for the treatment
carry the full weight of the embankment. Further away the of a wide range of soils, ranging from soft clays to loose sands
piles are shorter and will settle more. The ground conditions at by forming reinforcing elements of low compressibility and
the location of the piled embankment transitions are high shear strength. In addition to improving strength and
homogeneous which enables this design intent to be achieved deformation properties, stone columns densify in situ soil,
at site. This solution thus provides a gradual transition from rapidly drain the generated excess pore water pressures,
bridge to embankment and ensures there is no sudden change accelerate consolidation and minimise post-construction
in settlement profile. This design significantly reduces lateral settlement. In this paper, the design methodology, installation
pressure on the bridge abutment piles and eliminates methodology, load testing and field instrumentation for vibro
differential settlement between the adjacent ground and the replacement with stone columns for railway embankments
CL Embankment
Proposed formation level
4950 Min. 5000 4950
New track Rehab. track
300 mm sub-ballast
300 mm crusher run 1·5 CL CL 1·5
1 1
5·0% 3000
5·0%
Fill Formation
150 mm sand 1 2 Layers of high strength 1 1
5000
2 2 2 Detail ‘A’
geogrid, Kg 400/200
Direction of track
300 mm Geogrid, kg 400/200
crusher run Top and bottom layer 200 kN/m
1000 overlapping along the track
150 mm sand
Varies
250 mm ⫻ 250 mm
Geogrid, kg 400/200 precast Top and bottom layer 400 kN/m
RC piles Grade 45 perpendicular to the track
12 Ground Improvement 162 Issue GI1 Ground improvement techniques for railway embankments Arulrajah et al.
Delivered by ICEVirtualLibrary.com to:
IP: 136.186.1.187
Wed, 26 May 2010 00:59:09
Piled transition
with individual
pile cap Integrated pile embankment
Civil works Bridge works
10 m 8·65 m 10 m overlap of
5 m Individual pile cap top geogrid
Articulated slab 800 ⫻ 800 ⫻ 350 mm
H
750 mm
Crusher run blanket Geogrids
1 (wrapped with geogrid) Continuous slab
3
L2 ⭓ 6 m
L2 ⭓ 6 m
L1
L1
L1
L1
L1
L1
L1
L1
L1
L1
400 mm
1m
1m
S ⫽ 1·5 m RC piles
Piled transition
Civil works Bridge works with individual
pile cap Integrated pile embankment
Articulated slab
Abutment
RC piles with
individual pile caps
750 mm
5 ⫻ pile spacing ⫽ 7·5 m
Figure 18. Schematic diagram showing bridge approach transition using geogrid-reinforced piled embankments
Embankment
CL
Figure 19. Schematic diagram showing typical cross-section of removal/replacement works (dimensions in mm)
have been discussed. The results from numerous load tests and embankments have been discussed. Results from numerous
settlement plates indicate that the stringent performance load tests, settlement plates and inclinometers indicate that the
requirements of the new railway project were met. stringent performance requirements of the new railway project
were met.
Ground improvement by means of dry deep soil mixing allows
for the treatment of a wide range of soils, ranging from soft Piled embankments were designed for use for the bridge
clays to loose sands by forming stronger reinforcing elements approach transitions and allow for the embankments to be
of low compressibility and high shear strength. In this paper, constructed rapidly without any slowdown in the construction
the design methodology, installation methodology, load testing rate or sequence. Piled embankments also eliminate the effect
and field instrumentation for dry deep soil mixing for railway of settlement and stability problems.
Ground Improvement 162 Issue GI1 Ground improvement techniques for railway embankments Arulrajah et al. 13
Delivered by ICEVirtualLibrary.com to:
IP: 136.186.1.187
Wed, 26 May 2010 00:59:09
The removal and replacement method was widely used in the the 13th European Conference on Soil Mechanics and
project at locations where soft cohesive material was present. Geotechnical Engineering, Czech Geotechnical Society
Removal and replacement was an economical treatment option Prague, Czech Republic, 2003, 551–554.
for improving the presence of shallow soft soil deposits in the 6. HOLM G. Mitigation of Track and Ground Vibrations
project. induced by High Speed Trains at Ledsgard, Sweden.
Swedish Geotechnical Institute, Göteborg Sweden, 2002,
The type of ground improvement method adopted in the SD Report 10, pp. 1–44.
project dependant on various factors such as type of soil, 7. HOLM G. State of the practice in dry deep mixing methods.
height of embankment and thickness of soft or loose deposits. Grouting and Ground Treatment, Geotechnical Special
The various ground improvement techniques were employed Publication No. 120, ASCE, New Orleans, USA, 2003, 1,
successfully in the construction of embankments in the high- 145–163.
speed railway project. 8. BROMS B. B. Can lime/cement columns be used in
Singapore and Southeast Asia? Proceedings of the 3rd GRC
7. ACKNOWLEDGEMENT Lecture, Singapore, Nanyang Technology University,
The authors would like to thank Keller (Malaysia) Sdn Bhd for Singapore, 1999.
providing field measurement data for the vibro replacement 9. BROMS B. B. Design of lime, lime/cement and cement
and dry deep soil mixing works. The Keller-Bauer (Malaysia) columns. Proceedings of the International Conference on
Consortium executed the vibro replacement with stone columns Dry Mix Methods for Deep Soil Stabilisation, Balkema,
work. Keller (Malaysia) Sdn Bhd executed the dry deep soil Stockholm, Sweden, 1999, pp. 125–153.
mixing works. Emas Kiara Sdn Bhd (Malaysia) provided the test 10. SWEDISH GEOTECHNICAL SOCIETY. Lime and Lime Cement
results and properties of their geosynthetic products which Columns. Swedish Geotechnical Society, Linkoping, 1997,
were used in the project. SGF Report 4:95E.
11. RAJU V. R. Ground treatment using dry deep soil mixing
REFERENCES for a railway embankment in Malaysia. Proceedings of the
1. PRIEBE J. H. The design of vibro replacement. Proceedings 2nd Conference on Advances in Soft Soil Engineering and
of the Institution of Civil Engineers, Ground Engineering, Technology, Putrajaya, University Putra Malaysia,
1995, Technical paper GT 037-13 E 31–37. Malaysia, 2003, 589–600.
2. ARULRAJAH A. and AFFENDI A. Vibro replacement design of 12. BRITISH STANDARDS INSTITUTION. Code of Practice for
high-speed railway embankments. Proceedings of the 2nd Strengthened/Reinforced Soils and Other Fills. British
World Engineering Congress, Kuching, Malaysia, University Standards Institution, London, 1995, BS 8006.
Putra, Malaysia, 2002, 157–164. 13. HEWLETT W. J. and RANDOLPH M. F. Analysis of piled
3. BO M. W and CHOA V. Reclamation and Ground embankments. Proceedings of the Institution of Civil
Improvement. Thomson Learning, Singapore, 2004. Engineers, Ground Engineering, 1988, 21, No. 3, 12–18.
4. BALAAM N. P. and BOOKER J. R. Analysis of rigid rafts 14. ABDULLAH A., JOHN A. N. and ARULRAJAH A. Augeo Pile
supported by granular piles. International Journal of System used as piled embankment foundation in soft soil
Numerical and Analytical Methods in Geomechanics, 1981, environment. Proceedings of the 2nd Conference on
5, No. 4, 379—403. Advances in Soft Soil Engineering and Technology,
5. ARULRAJAH A., ABDULLAH A. and HAR L. Y. K. Geosynthetic Putrajaya, University Putra Malaysia, Malaysia, 2003,
applications in a high-speed railway project. Proceedings of 703–714.
14 Ground Improvement 162 Issue GI1 Ground improvement techniques for railway embankments Arulrajah et al.
Delivered by ICEVirtualLibrary.com to:
IP: 136.186.1.187
Wed, 26 May 2010 00:59:09
View publication stats