Attach-7 Work Procedure For Building's Water Supply and Drainage
Attach-7 Work Procedure For Building's Water Supply and Drainage
17125
WUHUAN
Talcher Fertilizers Project
ENGINEERING 17125-PC10-PP-004
CO.,LTD
WORK PROCEDURE 1 of 14 Rev. 0
0 For Bidding
REV. DESCRIPTION DEGND CHEKD APPRD DATE
MUST NOT BE COPIED, TRANSMITTED TO OTHERS OR USED WITHOUT PERMISSION OF WUHUAN ENGINEERING CO. LTD
WUHUAN Talcher Fertilizers Project WUHUAN Job. No.17125
CONTENTS
1. GENERAL ....................................................................................................................................3
2. REFERENCES .............................................................................................................................3
3. RESPONSIBILITIES ..................................................................................................................3
MUST NOT BE COPIED, TRANSMITTED TO OTHERS OR USED WITHOUT PERMISSION OF WUHUAN ENGINEERING CO. LTD
WUHUAN Talcher Fertilizers Project WUHUAN Job. No.17125
1. General
This Procedure stipulates the building’s water supply and drainage construction of xxxxx
Project.
The building’s water supply and drainage piping installation work include ::
1) Pipe sand blasting, painting ,PE tape construction.
2) Soil excavation and backfilling .
3) Pipe cuting, welding and erection .
4) Testing.
5) Fixtures construction
2. References
Construction Management Plan
Construction QC Procedure
Welding Work Management procedure
Welder Training and Qualification Procedure
Non-Destructive Examination(NDE) Procedure
Soil Excavation and Backfill Procedure
Piping Material Classification
pecification for CPVC Piping System
Construction drawings.
3. Responsibilities
3.1EPC Contractor
3.1.1 Construction Manager
Responsible for the purchase material inspection and transportation
Decide the location and layout of sub-contractor’s temporary facilities.
Supervise the construction process of subcontractor, urge and assist the sub-contractor
to finish the task on time and meet the quality requirements.
Coordinate and communicate with PMC, Owner, sub-contractors and other department.
3.1.2 Piping engineer
MUST NOT BE COPIED, TRANSMITTED TO OTHERS OR USED WITHOUT PERMISSION OF WUHUAN ENGINEERING CO. LTD
WUHUAN Talcher Fertilizers Project WUHUAN Job. No.17125
Mobilize enough manpower and equipment to meet the construction schedule and the
quality requirement.
Arrange for purchasing construction materials.
Responsible for the site planning, the organization arrangement of equipment and
manpower.
Control the schedule, ensure the construction quality and safety.
3.2.2 Piping engineer
Absolutely understand the design document, drawings and the relevant specification
requirements; Responsible for guidance to technical worker on-site.
Assign an proper workers and machines for construction work on-site;
Prepare construction schedule, supervise and inspect the construction completion status,
and report it to construction manager timely.
Arrange manpower for each construction process, and coordinate the handover of the
work for the construction process.
3.2.3 Welding engineer
MUST NOT BE COPIED, TRANSMITTED TO OTHERS OR USED WITHOUT PERMISSION OF WUHUAN ENGINEERING CO. LTD
WUHUAN Talcher Fertilizers Project WUHUAN Job. No.17125
Carrying out the installation of pipe under the direction of pipe engineer.
3.2.5 Welder
All Welders must take part in and pass the welder qualification testing in site before
starting welding.
Welder must carry out welding work according to relevant WPS.
3.2.6 Rigger
Direct the crane operate the winch, and scaffold a working platform to assist pipe fitter
to erect piping material or spool.
3.2.7 Machine operators
The machine operators must operate machines according to the operating regulations of
machines, and keep the machines running well.
4. Construction process
4.1 The flowchart of construction work
See Appendix 1
The construction process when pipes are crossings: main pipes then branch
pipes.Undergroundpipes then aboveground pipes, gravity pipes then pressure pipes.
It will happen crossing construction between civil work and installing work during
construction, placing the key of construction in a construction area, completing
installation of all buried pipes in such construction area one –off, then transferring to
next construction area.
Reasonably, keeping construction roads free. Achieving excavating one and restoring
one, completing civilized construction and making use of site reasonably.
4.2.2 Technical preparation
Drawing reviewing
MUST NOT BE COPIED, TRANSMITTED TO OTHERS OR USED WITHOUT PERMISSION OF WUHUAN ENGINEERING CO. LTD
WUHUAN Talcher Fertilizers Project WUHUAN Job. No.17125
Design disclosure
The design engineer is responsible for reviewing the construction drawings and disclosures,
and solves the technical problems and design problems during the process of construction
on site
Preparation ITP
The pipe engineers of WUHUAN prepare the ITP for PMC/OWNER to approval.
Site disclosure
The engineer of sub-contractor should make disclosure to constructors on technique,
quality and safety.
For potable water system, PPR pipes are connected with hot-melt or threaded
MUST NOT BE COPIED, TRANSMITTED TO OTHERS OR USED WITHOUT PERMISSION OF WUHUAN ENGINEERING CO. LTD
WUHUAN Talcher Fertilizers Project WUHUAN Job. No.17125
5. COMMISSIONING &TESTING
5.1 HOT&COLD WATER SYSTEM
The general requirements for commissioning, testing and handover, together with standard
test reports, are given in this specification.
All water lines inside building should be tested on pressure of 10 bars for 1 hour according
to local standard (specified in project specification) without any pressure loss. In case of
leakage, the leak shall be fixed and test shall be Performed again. Trench shall be backfilled,
with pipe work joints left exposed, before leakage testing. After successful testing ,joints
shall be covered in a similar manner to the pipe.
MUST NOT BE COPIED, TRANSMITTED TO OTHERS OR USED WITHOUT PERMISSION OF WUHUAN ENGINEERING CO. LTD
WUHUAN Talcher Fertilizers Project WUHUAN Job. No.17125
Appendix 1
Commissioning
MUST NOT BE COPIED, TRANSMITTED TO OTHERS OR USED WITHOUT PERMISSION OF WUHUAN ENGINEERING CO. LTD