You are on page 1of 69

EPC Project Rule Of Credit

and
Progress measurement
Our Belief

Now Everyone Can Be Trained


Corporate Profile

Ignite Resources is a Corporate Training and Consulting company since 2012. We shape the way organizations
implement strategy through training, development and consulting . Our approach covers the processes, people
and tools essential to tactical planning and implementation.

We specialize in Training, Consultation and Human Capital Development, for both management and technical
skills. We work together with companies as smart partnership in providing hands-on solution to solve day to day
business challenges by developing their human capital and providing custom made solutions.

Our expertise comes from years of experience working with industries and public training. Ignite resources is
committed to provide cutting-edge training that align with our vision. To deliver on our aspiration of becoming a
leading low-cost training provider. We have put in an ambitious plan that will bring us closer towards our goal ...
Development for all.

Seth Godin wrote once that “Every company, indeed, every organization, is a tribe, or if it’s large enough, a
network of tribes—groups of twenty to 150 people in which everyone knows everyone else, or at least knows of
everyone else. Tribes are more powerful than teams, companies, or even CEOs, and yet their key leverage points
have not been mapped—until now.”

Ignite is here to start with a spark to create a flame that everyone member in the tribes will be developed.
Outline

1. Progress Calculation

2. Rule of Credit - Engineering

3. Rule of Credit - Procurement

4. Rule of Credit – Fabrication and Construction

5. Managing Rule of Credit in Primavera P6


Progress Calculation

+ Rule of Credit / Weighted Steps method

01
Food for Thought
Progress Measurement
The work scope to be measure includes fabricate and
Project progress monitoring and control is one of the most
installation of pipeline including tie-in work, insulation work,
important tasks of construction project management. Every
painting work, fabricate and installation of new pipe racks,
team member needs to know, in a timely and accurate
fabricate and installation of equipment access platforms,
manner, how is the project progressing, where they are
installation of process equipment.
currently in comparison to the initially set plans, whether
deadlines are met, budgets are safely measured and followed.
Progress measurement system would be different depending
on organizational and/or project preference.
Executing a successful project depends on many factors, but
ultimately the most important question that need to be
Prior implementing a system for progress evaluation an
answered before any measures can be taken is
estimate must be developed for both man-hours and
quantities of drawings for each engineering discipline.
“What’s been accomplished so far?”
When working with progress calculation, you should know the
Progress measurement addresses this question and serves as
level of reporting. In a typical project, engineering progress is
a fundamental building block for effective project controls.
measured as level 2 (phase wise) and level 3 (engineering
discipline wise) and level 4 (document wise).
Progress measurement system plays an important part
of project control. It includes the detail progress tracking
sheet of its WBS elements, work categories and work steps
for each deliverable.

It is developed either when the additional requirements


are occurred for a particular project or when progress
measurement system is not in placed.
Progress Measurement

Progress measurement system plays an important part Physical progress for the engineering phase of a project consists of
of project control. It includes the detail progress tracking three levels of indenture as follows:
sheet of its WBS elements, work categories and work steps
for each deliverable. •Progress by Drawing, Datasheet, Document and Request for
•Quotation (RFQ)
It is developed either when the additional requirements
are occurred for a particular project or when progress •Progress by Discipline
measurement system is not in placed.
•Total Engineering Progress
The work scope to be measure includes fabricate and installation
of pipeline including tie-in work, insulation work, painting work,
fabricate and installation of new pipe racks, fabricate and
installation of equipment access platforms, installation of
process equipment.

Progress measurement system would be different depending


on organizational and/or project preference.

Prior implementing a system for progress evaluation an estimate


must be developed for both manhours and quantities of drawings
for each engineering discipline.

When working with progress calculation, you should know the


level of reporting. In a typical project, engineering progress is
measured as level 2 (phase wise) and level 3 (engineering
discipline wise) and level 4 (document wise).
Weighted Step

One of the most important choices that a control project


controller or project manager makes in establishing
an progress control or EVM plan is to select an appropriate
measure of earned value for each work package.
According to the 5th edition of the
This choice of the measure of interim progress, or PMBOK Guide,
completion, for each work package will do more than any
other discretionary choice in making the EVM results
meaningful. “ Weighted milestone method. An earned
The execution process for a successful project depends on value method that divides a work package
mange factors, but one fundamental question that need to into measurable segments, each ending
be answered is before proactive or prescriptive measures
can be implemented is: What’s been accomplished so far? with an observable milestone, and then
Progress measurement addresses this question and serves assigns a weighted value to the
as a fundamental building block for effective project
controls. achievement of each milestone. ”
Steps make it possible to describe and report progress for
activity work at a granular level by breaking an activity into
its component parts. Steps can have a step weight that
quantifies the portion of an activity's total work that each
step represents. On a project per project basis, you can use
step weights to calculate Activity Percent Complete.
Weighted steps enable you to track the progress of an
activity based on the number of steps completed.
Weighted Step

How do you figure out percent complete on a project?

How is it you go about objectively assigning a reasonable


and accurate measurement of how far along you are on an
item of work?

How many times have you asked, “Hey, where


did that number come from?”

Rule Of Credit can answer those questions.

For any workpackage in the work breakdown structure, a


project manager can define any number of milestone
events that define the incremental progress of that task.

An example milestone could be, “Engineering


Completed”. Another milestone could be “Pre-construction
Completed". Connected with that, a percent complete value
is associated with each milestone.

All milestones in the task will tally up to 100%. As work is


completed on the task, these milestones can be checked-off
as completed and the associated percent will be auto-
applied to the task.
EPC Weighted Level

Level 1 - Project
Project 1 Project 2 Project 3 Level 1
1 Activity per project

Level 2 - Phases
Level 2
Design
Engineering Procure Construction
3-5 Activity’s per project

Level 3 - WorkPackages
Level 3
Site Prep Foundation Slab Steel
Also called the “CM” schedule. 25 – 35 activities per project.

Level 4 - Contractor
Form Loc 1 Mesh Loc 1 Pour Loc 1 Level 4

As much detail as needed to communicate W4


Progress Planning

Engineering Progress Plan will be prepared by engineering milestones and by


engineering deliverables for each category.
Engineering
Weight point of engineering deliverables for each category will be based on the
estimated manhours

Procurement Progress Plan will cover equipment and bulk materials to be


purchased. This plan will be prepared respectively for the milestones of purchase
commitment, receipt of major raw materials to vendor shops, FOB and/or ex-
Procurement works and arrival at the Site.
Weight percentages for categories will be based on the costs defined in the
CONTRACT.

Construction Progress Plan will be prepared construction milestones covering


mobilization, demobilization, management, temporary facilities and by
Construction construction including pre-commissioning progress for permanent facilities.

For construction including pre-commissioning progress, the representative Bills


of Quantities (B/Q) will be allocated to work packages.
Progress Calculation
-Engineering Weightage
Why Rule of Credit

1 Very Accurate through all phases

2 Easily identifies changes and slippage in schedule

3 Can provide detailed historical information for future estimates

4 Can be used for “What If” scenarios

Clear defined information as to what will be provided and expected in each


5
review package

Can provide cost, hour and schedule alignment.


6
Engineering Weighted Level

Engineering
Level 1

Civil and
Process Mechanical Electrical Instrumentation Piping Level 2
Structure

Drawing Document Datasheet RFQ Level 3

Approved for
Issue For Review Issue For Issue For
Construction Level 4
(IFR) Approval (IFA) Construction (IFC)
(AFC)
Engineering Progress Measurement

 Engineering progress for each document


Level 4  The sum of the product of weight factor for each work step
and engineering progress for each work step

Engineering
 Engineering progress for each discipline
 The sum of the product of weight factor for each Progress
Level 3
document and engineering progress for each document Calculation

 Calculate total engineering progress


 The sum of the product of weight factor for each discipline
Level 2 and engineering progress for each discipline
Weighted Progress

Calculate the progress for each document or item


EPd = Σ (WFws x EPws)

Step 1 Where, EPd = Engineering progress of each document or item


WFws = Weight factor of each work steps
EPws = Percent completion of each work step

Calculate engineering progress for each discipline or work category


EPwc = Σ(WFdd x EPdd)

Step 2 Where, EPwc = Engineering progress of each discipline or category


WFdd = Weight factor of each document or item

Calculate engineering progress for each discipline or work category


Calculate total engineering progress
EP = Σ(WFwc x EPwc)
Step 3
Where, EP = Total engineering progress
WFwc = weight factor of each discipline or category,
Level 1 - WBS

WEIGHTAGE WEIGHT
WBS DESCRIPTION COST (RM)
BASIS FACTOR

ENG ENGINEERING Manhour 1,862,010 0.064

PRC PROCUREMENT Cost 6,499,944 0.223

CM CONSTRUCTION Cost 19,770,791 0.679

CON COMMISIONING Cost 967,255 0.032

Total Cost 2,9100,000

Weight Factor = Cost


Total cost
Level 2 - WBS

Engineering Work Category Breakdown


WEIGHT
BASIS COST (RM)
FACTOR

ENGINEERING (TOTAL COST) $1,862,010.00

CIVIL & STRUCTURE Manhour $380,890.00 20.46%


Manhour
PROCESS $207,710.00 11.16%
Manhour
MECHANICAL $260,160.00 13.97%
Manhour
GENERAL $140,580.00 7.55%

Manhour
PIPING $376,430.00 20.22%

Manhour
ELECTRICAL $296,200.00 15.91%

Manhour
INSTRUMENTATION $200,040.00 10.74%

Weight Factor = Discipline Cost


Engineering Total cost
Level 4 - WBS

( Option 1) ( Option 2)
ENGINEERING (Weightage) Proposed Weightage Proposed Weightage

Study & Design Preparation 40 %

Issued for Approval 40%

Client Comment -

Incorporate Client Comment -

Issued for Construction 20%

Issue for review (IFR) 10%

Issue for approval (IFA) 20%

Issue for construction (IFC) 30%

Approved for construction 40%


Level 4 - WBS

Progress tracking Excel sheet available for download in ignite.com Weight factor = 0.0584 * 76.6 %

% Complete= (5% x 100%) + (15% x 100%) + (20% x 100%) +(25% x 100%)+( 35% x 33.0%)

Study and
Progress (% Weight
Design IFR IFA IFC AFC
Complete) Progress
Preparation

Budgeted Weight
Document Title Category Discipline 5% 15% 20% 25% 35%
Man Hour Factor

Tie In Plan Dwg Piping 300 0.05484 100.0% 100.0% 100.0% 100.0% 33.0% 76.6% 4.2%

Piping GA Dwg Piping 400 0.07313 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 7.3%

Tie In Isometric Dwg Piping 350 0.06399 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 6.4%

Standard Pipe Support Dwg Piping 450 0.08227 100.0% 100.0% 100.0% 100.0% 33.0% 76.6% 6.3%

Demolition Dwg Piping 350 0.06399 100.0% 100.0% 100.0% 75.0% 0.0% 58.8% 3.8%

Tie In List Doc Piping 550 0.10055 100.0% 55.5% 0.0% 0.0% 0.0% 13.3% 1.3%

Critical Line List Doc Piping 600 0.10969 100.0% 55.5% 0.0% 0.0% 0.0% 13.3% 1.5%

Stress Analysis Report Doc Piping 800 0.14625229 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Coating Specs Doc Piping 850 0.15539305 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Piping class Doc Piping 820 0.14990859 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
GRAND TOTAL 5470 1.0000 30.8%
Rule of Credit

+ Engineering

02
Engineering Rule Of Credit

For Engineering, the weighting is according to the estimated man hours (units) assigned to each discipline. The
Master Deliverable List (MDL) is the document for contractual required Engineering deliverables, containing all
submittal (delivery) drawings and documents required to complete a specific project.

The Engineering Master Deliverable List will be the basis of progress measurement of engineering work.
Rule of Credit Overview

Cumulativ
Step Rule of Credit Increment %
e%

1 Study and design preparation 5% 5%

2 Issue for review (IFR) 10% 15%

3 Issue for approval (IFA) 20% 35%

4 Issue for construction (IFC) 30% 65%

5 Approved for construction 35% 100%


Engineering

Step Rule of Credit Increment % Cumulative %

1 Study and design preparation 5% 5%

2 Issue for review (IFR) 10% 15%

3 Issue for approval (IFA) 20% 35%

4 Issue for construction (IFC) 30% 65%

5 Approved for construction 35% 100%


Engineering

Step Rule of Credit Increment % Cumulative %

1 Study and design preparation 10% 10%

2 Issue to client 30% 40%

3 Approval by client 35% 75%

4 Issue for construction / purchasing 25% 100%


Engineering

Step Rule of Credit Increment % Cumulative %

1 Study/ design preparation 10% 10%

2 Issue for internal review 5% 15%

3 Issue to client 15% 30%

4 Approval by client 35% 65%

5 Issue to construction 35% 100%


Engineering

Step Rule of Credit Increment % Cumulative %

1 Study 10% 10%

2 Issue for internal review 5% 15%

3 Issue to client 15% 30%

4 Approval by client 35% 65%

5 Issue to construction 35% 100%


Engineering

Step Rule of Credit Increment % Cumulative %

1 Document Started, Format Accepted, TOC Complete 10% 10%

2 Write-up Complete 10% 20%

3 Issue IDC 5% 25%

4 IDC approved 15% 40%

5 Code 3 – Rejected, Revise & Re-Submit - 40%

Code 2 – Approved with Comments, Revise & Re-Submit &


6 20% 60%
Proceed with Construction

7 Code 1 – Approved without Comments 25% 85%

8 AFC 15% 100%


Engineering

Step Rule of Credit Increment % Cumulative %

1 Study & design preparation 10% 10%

2 Issue for approval 25% 35%

3 Client comment - 33%

4 Incorporate client comment 35% 70%

5 Issue for construction 30% 100%


Process – P&IDs, PFD

Step Rule of Credit Increment % Cumulative %

1 Document Started, Format Accepted, TOC Complete 25% 25%

Write-up Complete, Dept Sign-off, Issue for Review / Issue for


2 25% 50%
Client Approval

3 Code 3 – Rejected, Revise & Re-Submit 10% 60%

Code 2 – Approved with Comments, Revise & Re-Submit &


4 20% 80%
Proceed with Construction

5 Code 1 – Approved without Comments 10% 90%

6 Final Issue / Upload in SAP / Issue for Construction (IFC) 10% 100%
Instruments & Valves

Step Rule of Credit Increment % Cumulative %

1 Document Started, Format Accepted, TOC Complete 25% 25%

Write-up Complete, Dept Sign-off, Issue for Review / Issue for


2 25% 50%
Client Approval

3 Code 3 – Rejected, Revise & Re-Submit 10% 60%

Code 2 – Approved with Comments, Revise & Re-Submit &


4 20% 80%
Proceed with Construction

5 Code 1 – Approved without Comments 10% 90%

6 Final Issue / Upload in SAP / Issue for Construction (IFC) 10% 100%
3D modelling

Step Rule of Credit Increment % Cumulative %

1 Completion to 30% Status 20% 20%

2 Completion to 60% Status 25% 45%

3 Completion to 90% Status 30% 75%

4 Code 3 – Rejected, Revise & Re-Submit 0% 75%

Code 2 – Approved with Comments, Revise & Re-Submit &


5 10% 85%
Proceed with Construction

Code 1 – Approved without Comments, Final Issue / Release into


6 15% 100%
SAP
Piping Modeling

Step Rule of Credit Increment % Cumulative %

Preliminary : modeled point to point, branch fittings modeled,


1 20% 20%
pipe support location shown, critical line issued for stressing

Detailed : line modeled with valves, fittings and instruments, ISO


2 25% 45%
generating free of errors

Checking : Clash free, physical supports modeled, conforms to


3 30% 75%
stress analysis,, extracted for checking

4 Code 3 – Rejected, Revise & Re-Submit 0% 75%

Code 2 – Approved with Comments, Revise & Re-Submit &


5 10% 85%
Proceed with Construction

Code 1 – Approved without Comments, Final Issue / Release into


6 15% 100%
SAP
Piping Calculation

Step Rule of Credit Increment % Cumulative %

1 Initiate Pipe Stress Calcs/Issue Deliverables to Mech Eng 20% 20%

2 Prepare / Issue for Client Approval 55% 75%

3 Release / Approved for Construction 25% 100%


Piping Drawing

Step Rule of Credit Increment % Cumulative %

1 Document Started, Format Accepted, TOC Complete 25% 25%

2 Issue for Review / Issue for Client Approval 25% 50%

3 Code 3 – Rejected, Revise & Re-Submit 10% 60%

Code 2 – Approved with Comments, Revise & Re-Submit &


4 20% 80%
Proceed with Construction

5 Code 1 – Approved without Comments 10% 90%

6 Final Issue / Upload in SAP 10% 100%


MTO

Step Rule of Credit Increment % Cumulative %

1 Drawing / PDMS received or completed 10% 10%

2 MTO generation 45% 55%

3 Internal verify 35% 90%

4 MTO released 10% 100%


Rule of Credit

+ Procurement

03
Procurement - Subcontract

Step Rule of Credit Increment % Cumulative %

1 RFQ issued to subcontractor 10% 10%

2 Technical Bid Evaluation (TBE) 5% 15%

3 Cost Bid Evaluation (CBE) 5% 20%

4 Purchasing Request (PR) 10% 30%

5 PO issued 30% 60%

6 Site mobilization 40% 100%


Procurement - Subcontract

Step Rule of Credit Increment % Cumulative %

1 RFQ issued to subcontractor 10% 10%

2 Tender evaluation done 5% 15%

3 PO placed to vendor 10% 25%

4 Received key vendor drawings 5% 30%

5 Approved key vendor drawing 5% 35%

6 Fabrication 50% 85%

7 Final inspection finished 5% 90%

8 Ex-Work 5% 95%

9 Delivery at site 5% 100%


Procurement – Valves, Bulk Materials

Step Rule of Credit Increment % Cumulative %

1 Issued RFQ 10% 10%

2 Technical Bid Evaluation 10% 20%

3 P.O. Issued 15% 35%

4 Receipt of Major Materials 10% 45%

5 Function Testing 25% 70%

6 Final Inspection 15% 85%

7 Inco Term Delivery Complete 10% 95%

8 PO invoice close out 5% 100%


Procurement – Vessel Standalone

Step Rule of Credit Increment % Cumulative %

1 Issued RFQ 10% 10%

2 Technical Bid Evaluation 10% 20%

3 P.O. Issued 15% 35%

4 Commencement of Fabrication 10% 45%

5 Hydro Static testing 25% 70%

6 Final Inspection 15% 85%

7 Inco Term Delivery Complete 10% 95%

8 PO invoice close out 5% 100%


Major Buyout (Pumps, Control System)

Step Rule of Credit Increment % Cumulative %

1 Issued RFQ 10% 10%

2 Technical Bid Evaluation 10% 20%

3 P.O. Issued 15% 35%

4 Commencement of Fabrication 10% 45%

5 Hydro Static testing 25% 70%

6 Final Inspection 15% 85%

7 Inco Term Delivery Complete 10% 95%

8 PO invoice close out 5% 100%


Rule of Credit

+ Fabrication / Construction

04
Fabrication of Equipment Erection

Step Activities Increment % Cumulative %

Equipment Erection

1 Chipping & Padding 5% 5%

2 Lifting & rigging 40% 45%

3 Levelling & grouting 15% 60%

4 Preliminary alignment 20% 80%

5 Final alignment 10% 90%

6 Clear punch list 10% 100%


Fabrication of Piping Erection

Step Activities Increment % Cumulative %

Piping Erection

1 Material at site 5% 5%

2 Pipe laying 20% 25%

3 Preparation 20% 45%

4 Full welding execution 35% 80%

5 NDT 5% 85%

6 Pipe support erection 10% 95%

7 Final inspection 5% 100%


Fabrication of Piping

Step Activities Increment % Cumulative %

Piping Fabrication

1 Weld map drawing preparation 4% 4%

2 Withdrew material 3% 7%

3 Welding preparation 20% 27%

4 Spool assemble and tack weld 25% 52%

5 Full welding execution 20% 72%

6 Non Destructive Test (NDT) 6% 78%

7 Surface preparation and coating 15% 93%

8 Final Inspection 4% 97%

9 Deliver at Site 3% 100%


Tie-In work

Step Activities Increment % Cumulative %

Tie-in Work

1 Preparation done 10% 10%

2 Tagging done 10% 20%

3 Tie-in work 70% 90%

4 Final inspection 10% 100%


Hydrotest

Step Activities Increment % Cumulative %

Hydrotest

1 Preparation done 20% 20%

2 Testing 45% 65%

3 Reinstated 25% 90%

4 Punchlist cleared 10% 100%


Fabrication of Vessel

Step Activities Increment % Cumulative % WBS Weight


Fabricate Nozzles 5%
1 Weld/Fabricate nozzles 50% 50%
2 Completed NDE 50% 100%

Fabricate section number head 5%


1 Layout, cut holes prep 30% 30%
2 Fit/Weld nozzles/compensation pads 70% 100%

Fabricate Section Number 20%


1 Bevel, square, roll vessel 10% 10%
2 Weld long seams / re-roll 15% 25%
3 Layout, cut holes prep 10% 35%
4 Fit/weld nozzles/compensation pads 10% 45%
5 Build/install internal pads and external (trial fit) 55% 100%

Complete vessel / pressure envelope 55%


1 Fit Sections and Weld Circ Seams 25% 25%
2 Local PWHT with Overlap 10% 35%
3 Complete Internal / External Attachments 50% 85%
4 Hydrotest Vessel 15% 100%
Fabrication of Vessel

Step Activities Increment % Cumulative % WBS Weight

Paint 15%

1 Blasting 20%

2 Painting 40%

3 Lining & Acceptable Holiday (Spark) Testing 25%

4 Release 15%
Mechanical Work – Rotating Equipment

Step Activities Increment % Cumulative %

Rotating Equipment

1 Receive material 15% 15%

2 Rough, set. And prelim alignment 20% 35%

3 Level & grout 10% 45%

4 Final alignment 15% 60%

5 Run in 20% 80%

6 Clear punch list 20% 100%


Civil Work – Foundation & Concrete Paving

Step Activities Increment % Cumulative %

Foundation

1 Excavation 10%

2 Rebar 30%

3 Formwork 10%

4 Pouring concrete 15%

5 Strip & finishing 10%

6 Backfilling & compaction 15%

7 Clear punch list 10%


Civil Work – Cable Trench

Step Activities Increment % Cumulative %

Cable Trench

1 Excavation 35% 35%

2 Pre-cast concrete 25% 70%

3 Installation of concrete 25% 95%

4 Clear punch list 5% 100%


Civil Work – RCC Structure

Step Activities Increment % Cumulative %

Cable Trench

1 Excavation/PCC 10% 10%

2 Raft concrete 15% 25%

3 Super structure wall 40% 65%

4 Slab and backfilling 35% 100%


Electrical Cabling

Step Activities Increment % Cumulative %

Electrical cabling

1 Transportation to site 10% 10%

2 Tray erection 30% 40%

3 Cable laying 40% 80%

4 Cable connection 10% 90%

5 Testing 10% 100%


Electrical Fittings

Step Activities Increment % Cumulative %

Cable Trench

1 Installation 50% 50%

2 Cable connection 10% 60%

3 Testing 40% 100%


Fabrication of Piping

Progress tracking Excel sheet available for download in ignite.com


Rule of Credit in P6

+ “Step” function in Primavera P6

05
Without Using STEPs Function

Option 1 : Detail construction activity listed as activities.


With STEPs Function

“Steps” is a function in Primavera P6 that allow user to divide activities into smaller increments and track the completion.

• Activity percent complete is calculated based on the relative weights of the completed steps versus incomplete steps.
• This method suit of large activities that contents few activities steps.

Steps make it possible to describe and report progress for activity work at a granular level by breaking an activity into its component
parts.
With STEPs Function

“Steps” features in Primavera P6 in an interesting features to be used rather than creating a list of activities short-durations and no
priorities.

If you’re going to use the Steps feature in Primavera™ P6 to progress % Complete you need to check the “ Activity Percent Complete
Bases on Actual Steps” box in Project Calculations tab.
With STEPs Function

As you tick this box you will get a message explaining that the Physical Percent Complete values will be recalculated from the steps.

Note: if an activity is set to Percent Complete Type “Physical” but does not have Steps, then the values will NOT be recalculated. It will
only recalculate values that have steps assigned AND are Percent Complete Type “Physical”
With STEPs Function

Following that you need to use “ Physical % Complete “on the Activity that contains the steps
Steps Function

To indicate the portion of activity work that a single step represents, you can assign it a numerical value, or weight.

Once work for a step is underway, Primavera can use the step weight and the reported progress of step work (Step Percent Complete) to
calculate the percentage of total work that has been completed for the activity (Activity Percent Complete).

In the diagram above , each step is assigned a Step Weight and the Step Weight Percent is calculated.

When you add a step to an activity that already has steps defined, the default weight for the new step is 1, providing no steps have been
marked Completed, and no steps have a Step % Complete of 100%.
With STEPs Function

Option 2: Detail construction activity listed as steps


Steps be saved as templates for repetitive process.
Primavera P6 STEPs Function
Thank You …

You might also like