You are on page 1of 60

SKYSMART II

INSTALLATION MANUAL
Engineering by ARCTECH TRACKERS

MA-ECIDI-maroc-34MW

This document is property of Arctech. It is strictly forbidden to reproduce this document, it whole or in a part, and provide to others without the previous written consent by Arctech
Table of Contents
1 FOREWORD ................................................................................................................................................. 3
1.1 ABOUT ARCTECH ............................................................................................................................................... 3
1.2 ABOUT THIS MANUAL ....................................................................................................................................... 3
1.3 SAFETY RECOMMENDATIONS AND SYMBOLS USED .........................................................................................5
1.4 AFTER SALES SERVICE ........................................................................................................................................ 5
2 GENERAL SOLAR TRACKER DESCRIPTION ....................................................................................................... 6
2.1 DAYTIME TRACKING .......................................................................................................................................... 6
2.2 BACKTRACKING ..................................................................................................................................................7
2.3 TRACKER DATASHEET ........................................................................................................................................ 8
3 GENERAL ARRANGEMENT .............................................................................................................................9
4 LIST OF MAIN COMPONENTS ...................................................................................................................... 10
5 DEFINITION OF HARDWARE ........................................................................................................................ 15
6 FOUNDATION PROCEDURE ......................................................................................................................... 17
6.1 LAYOUT OF FOUNDATIONS ............................................................................................................................. 17
6.2 TERRAIN REQUIREMENTS ................................................................................................................................17
6.3 TOLERANCES FOR RAMMING POST .................................................................................................................18
6.4 TOLERANCES FOR INSTALLATING POSTS .........................................................................................................18
7 DEGREES OF FREEDOM AND TOLERANCES FOR INSTALLING SLEW DRIVES AND BEARINGS ............................20
8 STRUCTURE INSTALLATION PROCEDURE ......................................................................................................21
8.1 STEP 1: INSTALLATION AND LEVELING OF DRIVE SEATS AND ¨POST SEATS ................................................... 22
8.2 STEP 2: INSTALLATION AND ALIGNMENT OF “SLEW DRIVES” ........................................................................ 24
8.3 STEP 3: INSTALLATION OF PURLINS .................................................................................................................27
8.4 STEP 4: INSTALLATION OF TORQUE TUBES AND PREASSEMBLED PURLINS ................................................... 28
8.4.1 TORQUE TUBES AND BEARING SEAT ............................................................................................................................28
8.4.2 TORQUE TUBES AND PURLINS ......................................................................................................................................28
8.4.3 TORQUE TUBES AND DRIVE POST ................................................................................................................................ 29
8.4.4 BEARING SEAT AND POST SEAT ................................................................................................................................32
8.4.5 TORQUE TUBES AND TORQUE TUBE CONNECTION .....................................................................................................35

8.5 STEP 5: PURLINS DISTRIBUTION ALONG THE TRACKER ...................................................................................36


8.6 STEP 6: INSTALLATION OF TRANSMISSION SHAFT .......................................................................................... 37
8.7 STEP 7: TIGHTENING HAND-TIGHTENED FASTENERS ......................................................................................44
8.8 STEP 8: MODULES INSTALLATION ................................................................................................................... 44
8.9 STEP 9: MOUNTING OF CONTROLLER ........................................................................................................... 44
ANNEXES ........................................................................................................................................................... 46

www.arctechsolar.com
2
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

1 FOREWORD

1.1ABOUT ARCTECH
Arctech (SSE-STAR: 688408) is a leading manufacturer and supplier of intelligent solar trackers, fixed-tilt
structures and BIPV systems for utility-scale and commercial solar PV projects worldwide. As of the end of
2020, the company had supplied over 32GW of tracking and racking systems to nearly 1,100 PV plants in
40 countries, thanks to its extensive marketing networks including its offices in China, Japan, India, the
U.S., Spain, Australia, UAE, Mexico, Chile, Brazil, Vietnam and Argentina. With innovation and a customer-
first philosophy in its DNA, Arctech is committed to offering industry-leading solar trackers and best-in-class
services to boost energy yield for solar power plants and maximize returns for investors. For more
information, please visit www.arctechsolar.com.

1.2ABOUT THIS MANUAL


This manual describes the proper installation procedures and provides minimum standards required
for product reliability and warranty. Thoroughly understanding this manual is imperative to proper
installation; failure to follow the guidelines set forth can result in property damage, bodily injury, or even
death. Any modification of the installation procedures must be informed immediately to Arctech Solar in
order to be validated or not.

 Ensure that the installation is completed by a solar professional, and all tasks are supervised by
technical staff assigned for this purpose.
 Comply with all applicable local or national building codes, including any that may supersede
this manual.
 Ensure all installation equipment is appropriate for the installation, environment, and site’s
conditions.
 Use only “SkySmart II” original parts or parts supplied or recommended by Arctech Solar.
Replacements with parts from other sources may void any applicable warranty.
 Validate foundation parameters prior to installation, as a local geotechnical report may be
required to assess soil conditions. We recommend consulting with a local engineer familiar with
local regulations and build site requirements, including soil conditions, terrain and load criteria. All
parameters may impact foundation requirements. Lengths of foundation posts here are illustrative
only.
 Comply with all applicable fire codes including, but not limited to, keeping walkways clear and
avoiding obstacles.
 Ensure provided information is accurate. Issues resulting from inaccurate information are the
installer’s responsibility.
 Confirm with the module manufacturer that Ground Mount Tracker is compatible with the
selected module.
 Ensure safe installation of all electrical aspects of the PV system. All electrical installation and
procedures should be conducted by a licensed and bonded electrician or solar contractor. All work
must comply with national, state and local installation procedures, product and safety standards.
 See installation O&M manual for details about the periodic and preventive maintenance labors on
the trackers.

To facilitate the comprehension of this manual, some symbols and messages are included:

www.arctechsolar.com
3
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

NOTICE: Indicates a situation which, if not observed, will or could result in malfunction or damage.

ADVICE: indicates a suggestion to carry out an action in a useful way, or indicates additional information
of interest

Arctech Solar’s trackers are customized on project basis. Figures, tables, quantities, in this manual may vary.
For specific project information refer to the “Project Specific Annex” at the end of the document.

COPYRIGHT STATEMENT: All the contents of this manual, including the graphics contained herein, are
intended for the use of the recipient to whom the document and all associated information are directed.
Arctech Solar Holding Co., Ltd. owns the copyright of this document, which is supplied in confidence. It
must not be used for any purpose other than that for which it is supplied and must not be reproduced, in
whole or in part stored in a retrieval system or transmitted in any form or by any means without prior
permission in writing from Arctech Solar Holding Co., Ltd. ARCTECH SOLAR® is a trademarked tracker
and module mounting structure of Arctech Solar Holding Co. A patent covering the ARCTECH SOLAR®
has been granted.

DISCLAIMER: Information and data contained in this manual is exclusively for the purpose of assisting in
the operation and maintenance of Arctech Solar Holding Co., Ltd.’s ARCTECH SOLAR®. No warranty is
given nor can liability be accepted for use of this information for any other purpose. Arctech Solar Holding
Co., Ltd. has a policy of continuous product development and reserves the right to amend specifications
and parameters without notice.
The parts and spare parts supplied by Arctech Solar have been specially designed by Arctech Solar for its
trackers, non-original parts and spare parts and / or not validated by Arctech Solar will be considered
invalid, however Arctech Solar may certify these elements and their safety.

www.arctechsolar.com
4
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

1.3SAFETY RECOMMENDATIONS AND SYMBOLS USED


1. Comply with all applicable safety standards and codes, including those that may supersede this
manual.
2. Use only original parts or parts supplied or recommended by Arctech Solar. Replacements with
parts from other sources may void any applicable warranty.
3. Use only recommended tools in good condition. These tools must only be used for their intended
purpose.
4. Certified personal protective equipment (PPE) must be worn by all personnel involved with the
activities described in this manual, according to local safety codes
It is mandatory to wear high visibility clothing, safety boots, protection gloves, hearing
protectors and a hard hat throughout all tasks comprised in this manual.
5. The working area and its environment must be clean and tidy with no elements that could obstruct
visibility or works.
6. Do not perform any works while under the influence of alcohol or drugs.
7. Do not perform any works if feeling tired or sleepy.
8. Make sure that you adopt an appropriate posture while performing the tasks which will not cause
pain or injuries.
9. In case of doubt or if any of the above-mentioned safety recommendations are not in place, stop
and communicate to your supervisor.

1.4AFTER SALES SERVICE


Arctech's clients have a wide range of services available, based on project requirements. We offer
comprehensive engineering support from project planning to commissioning and O&M guidance.

www.arctechsolar.com
5
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

2 GENERAL SOLAR TRACKER DESCRIPTION


SkySmart II is a string-powered single-axis solar tracker designed to be significantly more stable under
wind loading when compared with the industry state-of-the art.

The new tracker concept SkySmart II is defined as an Independent Row 2P tracker, which includes a
Synchronous Multi-point Driving System (3, 4 or 5 fixed points) which significantly increases torsional
stiffness.

Up to 160 Modules 50-90 kWp* Capacity


*420-560Wp modules

This single-axis solar tracker consists of horizontal steel beams, aka torque tubes, (aligned in the North /
South direction) supported on a series of structural posts, which are fixed on the terrain. The torque tubes
support mounting rails and PV modules (along the East / West direction), these horizontal steel beams turn
(±60º) by mechanical rotating drive to orient the PV modules to their optimal position with respect to solar
radiation.

The solar tracker tracks the Sun’s position throughout the day and returns to stow during night-time or
when the stow strategy against the high winds gets triggered.

2.1DAYTIME TRACKING
This tracking technology uses geographic latitude, longitude, and time as the main parameters, and
astronomical algorithms (a general formula for the sun's position and horizontal coordinates) to calculate
the sun's altitude α and azimuth γ.
The tracker is a structure with a mechanism and electric motor, which is connected to a control box with the
tracking algorithm. This controller receives information about the specific tilt angle through an inclinometer.

www.arctechsolar.com
6
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

2.2BACKTRACKING
During sunrise and sunset, the first row of trackers cast shadows on consecutive PV arrays due to Sun’s
low altitude. Increasing row spacing can effectively reduce power losses caused by shadow occlusion, but
it will increase investment costs such as land, cables, and construction.
Backtracking technology is a reverse-direction tracking routine. Its application in PV tracking systems can
avoid shadow occlusion between PV arrays ensuring the optimization of power generation of PV systems,
and reducing the land area.
In simple terms, the backtracking routine uses the control system to calculate whether there is a shadow
between the PV arrays in the morning and afternoon according to the module pitch, the array size and the
azimuth and altitude of the sun. If there is shadow, the tracker will turn in the opposite direction to avoid it
and until the shadow is no longer there.
The operation of the tracker throughout the day is: as the Sun's altitude increases after sunrise, the tracker
gradually rotates from the flat or starting position to the maximum angle until the time when there is no
shading between PV arrays. Then it goes into regular tracking, which is turning towards the sun. In the
afternoon, there will be shadow occlusion between PV arrays and the tracker will be in the backtracking
mode again, from the maximum tracking angle position gradually turning to flat position to ensure that there
is no shadow occlusion in the PV array throughout the day.

PV arrays in the morning or evening without backtracking PV arrays in the morning or evening with backtracking

www.arctechsolar.com
7
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

2.3TRACKER DATASHEET

SKYSMART II TRACKER SPECIFICATIONS


Tracking Type Independent horizontal single-axis tracker
Tracking Range ±60°
Driving System Slewing drive, synchronous multi-point design
Tracker N-S Length ≤95m
Limitation
System Voltage 1,000 V or 1,500 V
Ground Coverage Ratio Typical ≥32%
Foundation Options Ramming/Pre-drilling/Concrete Piles
Terrain Adaption Up to 20% N-S Slope
Structure Material Hot dipped galvanized/Pre-galvanized steel/ Mg-Al-Zn steel
Power Supply Powered by PV strings, back-up Li-ion battery
Power Consumption Typical 0.04kWh/day
Standard Design Wind
105mph (47m/s) per ASCE7-10, higher wind load available
Speed
Module Supported All commercially available modules
Operation Temperature -20℃ to 60℃ (-30℃ to 60℃ Optional)
ELECTRONIC CONTROLLER SPECIFICATIONS
Control System 1 controller per tracker
Control Algorithm Astronomical algorithms + Tilt sensor close loop
Tracking Accuracy ≤ 2°
String-Powered Yes
Backtracking Yes
Communication Options Lora wireless/ RS 485 cable
Night Position Yes
Flood Mode Optional
Snow Mode Optional
Wind Protection Mode Yes

www.arctechsolar.com
8
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

3 GENERAL ARRANGEMENT

General Post Drive Post General Post General Post Drive Post General Post General Post Drive Post General Post

3 Fixed Point Tracker Front View

3 Fixed Point Tracker Top View

General Tracker Side View

The above illustrations do not show the exact tracker dimensions for a specific project. To obtain such,
please refer to the detailed drawings in the Annex A.1

www.arctechsolar.com
9
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

4 LIST OF MAIN COMPONENTS

Pos. Pos. Pos.


Drive Post Post Seat 7in Slew Drive Seat
① ② ③
Code Code Code
Details see Details see
300005753
300023796
Annex BOM Annex BOM
Weight[kg] a/p(*) Weight[kg] 9.44 Weight[kg] 7.79

Pos. Pos. Pos.


7in Slew Drive 7in Slave Drive A 7in Slave Drive B
④ ⑤ ⑥
Code Code Code

300002214
300018942 300018943
300002216 300018944
300004390
Weight[kg] 80 Weight[kg] 69.9 Weight[kg] 69.9

Pos. Pos. Pos. Grounding


Gasket20-40 General Post
⑦ ⑧ ⑨ Washer
Code Code Code
Details see
300000939
300023802 300003285
300003284
Annex BOM
Weight[kg] 0.04 Weight[kg] a/p(*) Weight[kg] 0.002

Pos. Slew Drive Pos. Pos.


AI Control Box Control Box Hoop
⑩ Reinforcing Plate ⑪ ⑫
Code Code Code

300000953
300023774 300022705
300003759 300023049
300001020
Weight[kg] 0.1 Weight[kg] 10 Weight[kg] 0.31

Pos. Antenna Fixed Pos. Pos. Tube


Tube Connector
connector
Torque Tube
⑬ Support ⑭ ⑮ Pre-assemble
Code Code Code
Details see 300023790
300000973
300023050 300001172
Annex BOM
Weight[kg] 0.4 Weight[kg] a/p(*) Weight[kg] 13

Pos. Pos. Pos. Transmission


Bearing Seat Plastic Bearing
⑯ ⑰ ⑱ Shaft Fixed Plate
Code Code Code

300008350
300000455 300007944
300004331 300023052
300001004
Weight[kg] 1.9 Weight[kg] 0.5 Weight[kg] 0.25

(*) a/p = Weight varies per project. Please see the specific value in Annex BOM.

www.arctechsolar.com
10
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

Pos. Transmission Pos. Transmission Shaft Pos. Transmission


⑲ Shaft Connection ⑳ Plastic Bearing 21 Shaft
Code Code Code

300007866 Details see


300002325
300023051 300004325
Annex BOM
Weight[kg] 2.27 Weight[kg] 0.06 Weight[kg] a/p(*)

Pos. Clamp Fixed Pos. Pos.


Grounding Cable Gasket20-60
22 Member 2 23 24
Code Code Code

300023795
300001077 300012410 300023803
300000975
Weight[kg] a/p(*) Weight[kg] 0.02 Weight[kg] 0.15

Pos. Clamp Fixed Pos. Purlin with Pos.


Purlin Assy.
25 Member 3 26 Bracing Assy. 27
Code Code Code
Details see Details see
300001091
Annex BOM Annex BOM
Weight[kg] 0.61 Weight[kg] a/p(*) Weight[kg] a/p(*)

Pos. Pos. Pos. Grounding Cable


Tube Cover 7inMotor
motor
28 29 Hoop
34
Code Code
Code
300007909
300003234 300019973
300003711 300004338
300008369
Weight[kg] 0.21 Weight[kg] a/p(*) Weight[kg] 0.09

(*) a/p = Weight varies per project. Please see the specific value in Annex BOM.

Refer to the Annex A.4. to consult the List of Electronic and Communication parts.

www.arctechsolar.com
11
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL
Pos.
Post Seat Pos.
② Post Seat

Code Code
TZ9057385 TZ9057385
Pos.
Post Seat Weight[kg] 9.44
② Weight[kg] 9.44
Code Pos.
General Post Pos.
⑧ General Post

TZ9057385 Code Code
Weight[kg] 9.44 Details see Details see
Pos. Annex BOM Annex BOM
General Post Weight[kg] a/p(*)
⑧ Weight[kg] a/p(*)
Code Pos.
Pos.
Bearing Seat Bearing Seat
Details see ⑯

Annex BOM Code Code
Weight[kg] a/p(*)
300000455 300000455
Pos.
Bearing Seat Weight[kg] 1.9
⑯ Weight[kg] 1.9
Code Pos.
Plastic Bearing Pos.
⑰ Plastic Bearing

300000455 Code Code
Weight[kg] 1.9
300004331 300004331
Pos.
Plastic Bearing Weight[kg] 0.5
⑰ Weight[kg] 0.5
Pos.
Code Grounding Cable Pos.
23 Grounding Cable
23
300004331 Code
Code
Weight[kg] 0.5
300012410
Pos.
300012410
Grounding Cable Weight[kg] 0.02
23 Weight[kg] 0.02
Code

300012410
Weight[kg] 0.02
South

North

Pos.
Pos. Pos. Pos. Grounding Cable
Pos. Pos. Drive Post Grounding Cable Drive Post 23
Drive Post Grounding Cable ① 23 ①
① 23 Code
Code Code Code
Code Code
Details see Details see 300012410
Details see 300012410
300012410 Annex BOM Annex BOM
Annex BOM Weight[kg] 0.02
Weight[kg] 0.02
Weight[kg] a/p(*) Weight[kg] a/p(*)
Weight[kg] a/p(*) Weight[kg] 0.02
Pos. Pos.
Pos. 7in Slew Drive Seat 7in Slew Drive Seat
7in Slew Drive Seat ③ ③

Code Code
Code
300005753 300005753
300005753
Weight[kg] 7.79 Weight[kg] 7.79
Weight[kg] 7.79
Pos. Pos.
Pos. 7in Slew Drive 7in Slave Drive A
7in Slave Drive A ④ ⑤

Code Code
Code
300002214 300002216
300002216
Weight[kg] 80 Weight[kg] 69.9
Weight[kg] 69.9
Pos. Pos.
Pos. Gasket20-40 Gasket20-40
Gasket20-40 ⑦ ⑦

Code Code
Code
300000939 300000939
300000939
Weight[kg] 0.04 Weight[kg] 0.04
Weight[kg] 0.04
Pos. Slew Drive Pos. Slew Drive
Pos. Slew Drive
⑩ Reinforcing Plate ⑩ Reinforcing Plate
⑩ Reinforcing Plate
Code Code
Code
300000953 300000953
300000953
Weight[kg] 0.1 Weight[kg] 0.1
Weight[kg] 0.1
Pos. Pos.
Pos. Gasket20-60 Gasket20-60
Gasket20-60 24 24
24
Code Code
Code
300000975 300000975
300000975
Weight[kg] 0.15 Weight[kg] 0.15
Weight[kg] 0.15

www.arctechsolar.com
12
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

Pos.
Tube Cover
28
Code

300003234
Weight[kg] 0.21

Pos. Tube Connector


⑮ Pre-assemble
Code

300001172
Weight[kg] 13

South

North

Purlin Assembly

Pos.
Tube Cover
28
Code

300003234
Weight[kg] 0.21

www.arctechsolar.com
13
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

Pos. Transmission Shaft


⑱ Fixed Plate
Code

300001004
Weight[kg] 0.25

Pos. Transmission Shaft


⑳ Plastic Bearing
Code

300004325
Weight[kg] 0.06

South

North

Pos. Transmission Shaft


⑱ Fixed Plate
Code

300001004
Weight[kg] 0.25

Pos. Transmission Shaft


⑳ Plastic Bearing
Code

300004325
Weight[kg] 0.06

www.arctechsolar.com
14
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

5 DEFINITION OF HARDWARE

TIGHTENING TIGHTENING
SCREW SIZE JOIN DESCRIPTION (From – To) TORQUE TORQUE
[Nm] [ft-lb]
M4 WIFI Antenna bracket to Antenna 1.5 1

M6 Wind Sensor joints 8 6

M8 Control Box to Fixing hoops 10 7


PV Modules to Purlin Assy.
Transmission shaft connection to
M8 Transmission shaft 15 11
Transmission shaft to Slew drive
Grounding cable hoop to torque tube

M10 Wind Sensor post 40 30

Bearing seat to Post seat


M12 80 59

Purlin with bracing to Clamp Fixed


M12*60 10 7
Member3
M12*60 Purlin to Bracings 30 22
Drive post to Drive Seat
General post to Bearing Seat
M16 Slew Drives to Torque tubes 210 155
T.T. Connection to Torque Tube
Wind sensor seat
M20 Slew drive to Drive Seat welding 290 214

Recommended equipment as below:

www.arctechsolar.com
15
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

Recommended equipment and tooling as below:

www.arctechsolar.com
16
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

6 FOUNDATION PROCEDURE
6.1LAYOUT OF FOUNDATIONS

General Post Drive Post General Post General Post Drive Post General Post General Post Drive Post General Post

X (According to Project) X (According to Project)

All above dimensions identified as “a”, “b”, “c”, & “x” (according to project) are project specific.
Please See Annex A.
Foundation depths and distances to ram, please see the specific foundation drawings in Annex
A.1. This installation manual takes the top of the posts as reference.

30±30 mm 30±30 mm

Take drive post as a reference post, always take the tolerance between the same reference post.

6.2TERRAIN REQUIREMENTS

Dim. Dimension Orientation


α < 20 % N/S or S/N

www.arctechsolar.com
17
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

6.3TOLERANCES FOR RAMMING POST

The figure shows the height scenarios for Post ramming (it depicts the same posts in three different
scenarios, not different posts)

6.4TOLERANCES FOR INSTALLATING POSTS


b

a α

Nominal Position E-W Position N–S Position (*) Clocking Position

θ β

N-S Plumbness E-W Plumbness Height Adjustment

www.arctechsolar.com
18
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

Pos. Dimension Orientation


a +/- 20mm E-W
b +/- 20mm (*) N-S
c +/- 30mm Height
α +/- 3 degrees Clocking
θ +/- 2 degrees N-S
β +/- 1 degree E-W

(*) Not cumulative. ±20 from reference post

Example of valid posts positions for any tracker

www.arctechsolar.com
19
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

7 DEGREES OF FREEDOM AND TOLERANCES FOR INSTALLING


SLEW DRIVES AND BEARINGS

Pos. Dimension Orientation Pos. Dimension Orientation


a +/- 20mm E-W a +/- 20mm E-W
b +/-6 mm N-S b +/- 3mm N-S
c +/- 30mm Vertical c +/- 30mm Vertical
α +/- 3 degrees Clocking α +/- 3 degrees Clocking
β +/- 12 degrees N-S β +/- 12 degrees N-S

www.arctechsolar.com
20
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

8 STRUCTURE INSTALLATION PROCEDURE

The step-by-step installation procedure of the Tracker components is described below:

 STEP 0: RAMMING POSTS (described above)

 STEP 1: INSTALLATION AND LEVELING OF DRIVE SEATS AND THE POST SEAT

 STEP 2: INSTALLATION AND ALIGNMENT OF “SLEW DRIVES”

 STEP 3: INSTALLATION OF PURLINS

 STEP 4: INSTALLATION OF TORQUE TUBES AND PREASSEMBLED PURLINS

 STEP 5: PURLINS DISTRIBUTION ALONG THE TRACKER

 STEP 6: INSTALLATION OF TRANSMISSION SHAFT

 STEP 7: TIGHTENING HAND-TIGHTENED FASTENERS

 STEP 8: MODULES INSTALLATION

 STEP 9: MOUNTING OF CONTROLLER

www.arctechsolar.com
21
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

8.1STEP 1: INSTALLATION AND LEVELING OF DRIVE SEATS AND ¨POST


SEATS 3
1

4
5

Drive Seat onto Drive Post

Qty. Tightening Socket


Pos. Ref. Description per Torque Wrench sizes
figure [Nm] / [ft-lbs] DIN / ANSI
1 300023796 Slew Drive Seat 2 - -
2 See Annex Drive Post 1 - -
3 -- Bolt M16x50, 8.8 8
4 -- Flat Washer 16 8
5 -- Big Flat Washer 16 8 210 / 155 (*) 24 / 24
6 -- Spring Washer 16 8
7 -- Nut M16 8

(*) Do not exceed Maximum Torque.

Leveling of Drive seats

www.arctechsolar.com
22
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

Please keep the slots facing


the same direction in all posts
within the same tracker.

7 5
6 4
3
Assembly of Post Seat onto General Post

Qty. Tightening Socket


Pos. Ref. Description per Torque Wrench sizes
figure [Nm] / [ft-lbs] DIN / ANSI
1 300023789 Post Seat 1 -
See Annex
2 BOM General Post 1
3 -- Bolt M16x50, 8.8 4
4 -- Flat Washer 16 6 210 / 155 (*) 24 / 24
5 -- Big Flat Washer 16 2
6 -- Spring Washer 16 4
7 -- Nut M16 4

Leveling of Post Seats

173±15 mm

(*) Do not tighten until Step #7.

General post Drive post

www.arctechsolar.com
23
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

8.2STEP 2: INSTALLATION AND ALIGNMENT OF “SLEW DRIVES”

Put this Locknut in place and do not apply the torque


until Step #8, when the Antenna Support plate will be
1 installed.

2
Drive Seats
Assembly of Slew Drive onto Drive Seat

Qty. Tightening Socket


Pos. Ref. Description per Torque Wrench sizes
figure [Nm] / [ft-lbs] DIN / ANSI
1 See Annex Motor and Slew Drive 1 --
2 -- Bolt M20x100, 10.9 4 West
3 300023803 Gasket20-60 4
290 / 214 (*) 30 / 30
4 300023802 Gasket20-40 4
5 -- Hexagon Nut M20 8

Only the first four nuts should be tightened to spec.


The four locking nuts must not be tightened yet.

(*) Do not tighten until Step #7.

The DC Motor always towards the West direction.

www.arctechsolar.com
24
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

1
1

5
5
4
4

3
3
2
2

Assembly of the Slave Drive A (South) onto Drive Seat Assembly of the Slave Drive A (North) onto Drive Seat

Qty. Tightening Socket


Pos. Ref. Description per Torque Wrench sizes
figure [Nm] / [ft-lbs] DIN / ANSI
1 See Annex Slave Drive A(South)/(North) 1 --
2 -- Bolt M20x100, 10.9 4
3 300023803 Gasket20-60 4
290 / 214 (*) 30 / 30
4 300023802 Gasket20-40 4
5 -- Hexagon Nut M20 8

(*) Do not tighten until Step #7.

Tightening the first four nuts after the alignment of slew drive.

www.arctechsolar.com
25
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

Once the "Slew Drives" have been mounted onto the posts, it is absolutely necessary to align and level
them, as described below:
1st ALIGNMENT STEP:

1 2

Slave Drive A (North)as Slave Drive A (South) as


Initial Reference E-W alignment & clocking
regulated Point (Target)

I. The “Slave Slew Drive A(North)” is the Initial reference.


II. Put the “Slave Slew Drive A(South)” onto its support. Center and align it according to the first one
so the line they form goes through the center of each post.

2nd ALIGNMENT STEP:

Slave Drive A (North)as Motor and Slew Drive as Slave Drive A(South)
Initial Reference regulated Point (Target) as secondary reference

E-W alignment & Clocking

III. Mount the “Main Slew Drive with Motor” in the center post so its center is aligned with the
previous slew drives.

If the alignment #2 is not possible, the Slew Drive to the North must be readjusted until the
same line goes through the center all slew drives.

www.arctechsolar.com
26
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

8.3STEP 3: INSTALLATION OF PURLINS


PURLIN OPTION III: PURLINS WITHOUT BRACES(Outside gasket 400)

2
4
5
6

Qty.
Tightening Torque
Pos. Ref. Description per
[Nm] / [ft-lbs]
figure
1 See Annex Purlin 1
2 300023795 Clamp Fixed Member2 1
3 -- Bolt M12x200 ,8.8 2
4 -- Flat Washer 12 2 80 / 59 (*)
5 -- Spring Washer 12 2
6 -- Nut M12 2

Do not tighten
completely in this Step

There are two types of purlin without brace designs. The difference is the length of bottom strengthen plate. Exact purlin design will
be selected basing on project load. Below shows one purlin with long strengthen plate.

www.arctechsolar.com
27
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

8.4 STEP 4: INSTALLATION OF TORQUE TUBES AND PREASSEMBLED


PURLINS
8.4.1 TORQUE TUBES AND BEARING SEAT
3

Torque Tubes mounting through the Plastic Bearing


Housing

Qty. Tightening Socket


Pos. Ref. Description per Torque Wrench sizes
figure [Nm] / [ft-lbs] DIN / ANSI
1 See Annex Torque Tube 1 -
2 300007944 Plastic Bearing 2 -
3 300008350 Bearing Seat 1 -

8.4.2 TORQUE TUBES AND PURLINS

(*) Please refer to the detailed drawings in the Annexes to know the exact torque tube thicknesses.

Inserting the Purlins along


the Torque Tube

Purlin without Braces

The picture above is just illustrative. It does not show


the exact quantity of purlins. Please refer to the
Annexes to know the exact quantity of purlins needed

www.arctechsolar.com
28
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

Do not fix the Purlin assy. to the Torque tube yet, they must be moved freely as they will be positioned
in place later. See Step #5.

For the quantities of purlins to be pre-assembled, please refer to the detailed drawings in the Annexes

8.4.3 TORQUE TUBES AND DRIVE POST

Notice
-All the M16 bolt (part 3 in the table below) connecting slew Drive T.T. to slew Drive must have screw
thread sealant painted before inserting into the hole.

-Make sure the spacings are correct before tightening.

Pour some thread sealant into a small container (the thread sealant is anaerobic and will not solidify in non-
closed spaces). Try to keep the thread as clean as possible and then immerse the bolt into the sealant as 4
teeth are covered with sealant. Now you can install the bolt. Refer to below:

The M16 bolt with 10 teeth’s sealant

www.arctechsolar.com
29
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

3
2

T.T. install to the bottom at the


shaft of slew drive

Torque Tubes mounting onto the Slave Drive A

Put all bolts in place and then then fasten


Purlin without Braces
and tighten according to the sequence
above.
It is recommended to place all preassembled purlins
on one side in order to perform subsequent steps
more conveniently.

www.arctechsolar.com
30
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

Qty. Tightening Socket Wrench


Pos. Ref. Description Per Torque sizes
figure [Nm] / [ft-lbs] DIN / ANSI
1 See Annex Torque Tube 2 -
2 300023774 Slew Drive reinforcing plate 8 -
3 -- Bolt M16x30 ,10.9 16 210 / 155 24 / 24

(*) Please refer to the detailed drawings in the Annexes to know the exact torque tube thicknesses.

www.arctechsolar.com
31
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

8.4.4 BEARING SEAT AND POST SEAT


Bearing Seat

Detail of Flange Nut

Post Seat

Assembly of Bearing Seat onto Post Seat

Socket
Qty. Tightening
Wrench
Pos. Ref. Description per Torque
sizes DIN /
figure [Nm] / [ft-lbs]
ANSI
1 -- Bolt M12x40, 8.8 4
2 -- Spring Washer 12 4
80 / 59 19 / 18
3 -- Big Flat Washer 12 4
4 -- Flange Nut M12 4

Detail of Grounding Cable

www.arctechsolar.com
32
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

Socket
Qty. Tightening
Wrench
Pos. Ref. Description per Torque
sizes DIN /
figure [Nm] / [ft-lbs]
ANSI
1 300008369 Grounding cable hoop 1
2 -- Bolt M8 x 25 1
3 -- Flat Washer 8 2 15 / 11 -
4 -- Spring Washer 8 1
5 -- Nut M8 1
6 300012410 Grounding Cable 1

These grounding cables will be installed in each posts (as shown in below figure)

3 Fixed Point Tracker

Bearing Seat

Detail of Flange Nut

Transmission Shaft
Fixed Plate

Post Seat

Assembly of Bearing Seat onto Post Seat with Transmission Shaft Fixed Plate

Socket
Qty. Tightening
Wrench
Pos. Ref. Description per Torque
sizes DIN /
figure [Nm] / [ft-lbs]
ANSI
1 -- Bolt M12x40, 8.8 4
2 -- Spring Washer 12 4
80 / 59 19 / 18
3 -- Big Flat Washer 12 4
4 -- Flange Nut M12 4

www.arctechsolar.com
33
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

Purlin without Braces


Auto-adjusting of Bearing Seat

It is recommended to place all preassembled purlins


on each side in order to perform subsequent steps
more conveniently.

The Bearing seat should be not fastened when it is installed, since it will adapt itself when the
Torque Tube is totally aligned. Therefore, no tolerances are needed.

(*) Please refer to the detailed drawings in the Annexes to know the exact Torque Tube thicknesses.

www.arctechsolar.com
34
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

8.4.5 TORQUE TUBES AND TORQUE TUBE CONNECTION

Purlin without Braces

Torque Tubes assembly and alignment

1 4 8 4 2 6

5 1 3 7

Tighten long M16*190 bolts first, then tighten


the remaining 8 bolts according to the sequence
above and retighten 2xM16*190 once again.
After installation, max. distortion angle of both
ends is not more than 0.3°.

www.arctechsolar.com
35
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

Qty. Tightening Socket Wrench


Pos. Ref. Description per Torque sizes
figure [Nm] / [ft-lbs] DIN / ANSI
1 300023790 Tube Connector 2 - -
2 -- Bolt M16x190, 8.8 2
160 / 118
3 -- Big Flat washer 16 4
4 -- Bolt M16x50, 8.8 8 24 / 24
210 / 155
5 -- Flat washer 16 16
6 -- Spring Washer 16 10 -
7 -- Nut M16 10 -

Qty. per
Pos. Ref. Descripción
figure
1 300007909 Tube Cover 1

8.5STEP 5: PURLINS DISTRIBUTION ALONG THE TRACKER

In this Step is defined the adjusting and lock of the Purlins along the Torque Tubes (both sides). The
dimensions “x” varies by project. Please refer to the detailed drawings in the Annex A.1.

www.arctechsolar.com
36
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

8.6STEP 6: INSTALLATION OF TRANSMISSION SHAFT

Transmission Shaft
Fixed Plate

Please install the transmission shaft fixed plate in the same face.

The axes of “Torque tube” and “Transmission Shaft” shall be in parallel.

Both Blue faces must be in


parallel

www.arctechsolar.com
37
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

Hereafter, it is recommended to follow the following sequence for the Central section of “Transmission
shaft” installation:
 Step 6.1: Put the “Transmission Shaft Plastic Bearing” into the “Transmission Shaft fixed plate” first, and
then insert the “Transmission Shaft” into it.

(*) Please refer to the detailed drawings in the Annex A.1 to know the exact length of each Transmission
Shaft to be installed.

 Step 6.2: Keep the above parts horizontally fixed on the General post “a” (Do not tighten in this step).

Central Section Transmission Shaft

General Post “b” General Post “a”

(*) Do not tighten until the end of Step #6.

www.arctechsolar.com
38
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

 Step 6.3: Sliding the “Transmission Shaft” on its axis direction to the opposite General Post “b”.

General Post “b”

 Step 6.4: Pre-assembly Transmission Shaft Plastic Bearing in the same way and then move the
Transmission Shaft through its center.

General Post “b”

 Step 6.5: Ensure the Transmission Shaft Fixed Plate is installed tightly and keep the transmission
Shaft on the same line.

(*) Do not tighten until the end of this Step #6.

www.arctechsolar.com
39
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

The central section installation should be so:

Transmission Shaft#3
Fixed Plate #1 Fixed Plate #1

Plastic Plastic Bearing #2


Bearing #4

&

Installation subsequence of central Transmission shaft and support pieces

 Step 6.6: Once Central section of “Transmission shaft” has been installed, install the transmission shaft
to the slew drive as below:

Slew Drive & DC Motor Slave Drive A

1
2
4
3

Nuts above are preassembled and it must be taken off before starting this step.

Qty. Tightening Socket


Pos. Ref. Description per Torque Wrench sizes
figure [Nm] / [ft-lbs] DIN / ANSI
1 -- Hexagon socket Screw M8x60 1
2 -- Flat washer 8 2
3 -- Nut M8 1 15/11
4 -- Spring Washer 8 1

www.arctechsolar.com
40
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

Transmission Shaft on Slave Drive A Transmission Shaft on Slew Drive

(*) Please refer to the detailed drawings in the Annex A.1 to know the exact length of each Transmission
Shaft to be installed.

Do not tighten until Transmission shaft assy. is completely set and leveling.

 Step 6.7: Installation of the transmission shaft connection

3 2

1
7
8

6
1
4

Installation of Transmission Shaft connection

www.arctechsolar.com
41
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

Tightening
Qty. Socket
Po Torque
Ref. Description per Wrench sizes
s. [Nm] / [ft-
figure DIN / ANSI
lbs]
1 See Annex Transmisión Shaft 1 - -
2 300023051 Transmission Shaft Connection 1
3 -- Bolt M8x70, 8.8 2
4 -- Big Flat washer 8 4
5 -- Spring Washer 8 6 15/11
6 -- Nut M8 6
7 -- Bolt M8x25 ,8.8 4
8 Flat washer 8 8

Do not tighten until transmission shaft is completely set and leveling.

www.arctechsolar.com
42
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

8.7STEP 7: TIGHTENING HAND-TIGHTENED FASTENERS


Once all previous components have been assembled, it is necessary to tighten all threaded
connections, where torque was not applied, for levelling and alignment of all tracker components.
These connections that need to be tightened at this point are listed below:
 Bearing Seat onto General Post
 Assembly of Slew Drive onto Drive Seat
 Assembly of Slave Drive onto Drive Seat

8.8STEP 8: MODULES INSTALLATION


Please refer to the Annex A.3 for modules installation.
1) The PV module and purlin are fixed with bolt .

Module fixing system

Electrical current:
Module Washer Bolt Purlin Torque tube

2) The PV module and purlin are fixed with Bolt and flat washer.

www.arctechsolar.com
43
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

8.9STEP 7: TIGHTENING HAND-TIGHTENED FASTENERS


Once all previous components have been assembled, it is necessary to tighten all threaded
connections, where torque was not applied, for levelling and alignment of all tracker components.
These connections that need to be tightened at this point are listed below:
 Bearing Seat onto General Post
 Assembly of Slew Drive onto Drive Seat
 Assembly of Slave Drive onto Drive Seat

8.10 STEP 8: MODULES INSTALLATION

Please refer to the Annex A.3.

8.11 STEP 9: MOUNTING OF CONTROLLER


1

5 2
2 4
3

Communication Antenna and Support plate

Qty. Tightening Socket Wrench


Pos. Ref. Description per Torque sizes
figure [Nm] / [ft-lbs] DIN / ANSI
1 See Annex Antenna communication 1 - -
2 300023050 Antenna support plate 1
- Allen key
3 -- Bolt M4x10 3
4 -- Spring Washer 4 3
5 -- Flat Washer 4 3

www.arctechsolar.com
44
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

The AI control box is mounted on the torque tube side with the emergency button facing south.
This grounding cable connects the control box with the torque tube. The cable is fixed to the torque tube
with a self-tapping screw which cannot damage the torque tube.

5
7
6
2 8

North

South
4

1
3
Control Box and fixing plates

Socket
Qty. Tightening
Po Wrench
Ref. Description per Torque
s. sizes
figure [Nm] / [ft-lbs]
DIN / ANSI
1 300022705 AI Control Box 1 - -
2 300023049 Control box hoop 2
3 300012450 Control Box Grounding Cable 1
4 300002028 Self-tapping screw 1
5 -- Bolt M8x30 4
6 -- Flat Washer 8 8
10/7
7 -- Spring Washer 8 4
8 -- Nut M8 4

The distance from the end of Torque Tube to Control box hoop is 620mm (Refer to below figure).

www.arctechsolar.com
45
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

ANNEXES
LIST OF ANNEXES

A.1. GENERAL ASSEMBLY DRAWINGS


A.2. STANDARD COMPLETE B.O.M.
A.3. FIXING PV MODULES TO PURLINS
A.4. ELECTRICAL WIRING

www.arctechsolar.com
46
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

A.1. GENERAL ASSEMBLY DRAWINGS

www.arctechsolar.com
47
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

A.2. STANDARD COMPLETE BOM.

www.arctechsolar.com
48
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

A.3. FIXING PV MODULES TO PURLINS


There are two possible panel installation methods:
a) Tracker in horizontal position (0 degree).

b) Tracker in tilted to ~45 degrees.


For trackers that mount up to 120 PV modules, the PV modules installation must be performed
in the lower row in one go (as picture follows).

Then, the tracker can be rotated to -45 degrees to install the remaining PV modules.

WARNING!
For trackers that mount more than 120 PV Modules, the team at site should contact with
Arctech Engineering in order to provide them alternative installation procedure.

WARNING!
-Modules should be place in stow position (horizontal, i.e. 0 deg.) after panel installation is
complete or interrupted due to shift change.

www.arctechsolar.com
49
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

A.4. ELECTRICAL WIRING


A.4.1. “ARTIFICIAL INTELLIGENT” (AI) CONTROLLER
Power is obtained directly from the module string using a T-connector as shown below, DC
extension cable & T-connectors are provided by Arctech Solar.

When connecting power ensure the DC switch is in OFF position, and the emergency
stop is pushed in.

Use only for wired


communication solution

DC switch

+/- DC power directly


from module string

There is no LED
and Sensor, only Connects to motor Emergency Stop Button
two terminals.

www.arctechsolar.com
50
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

In-line fuse T-connector

MC4-connector

Follow guidance below to tie the motor cable. If already tied up, skip this step.

Lay the motor cable along the motor shell and make sure the cable loop radius is larger than 50mm.

Tie the cable with cable ties and cut the excess plastic tie.

www.arctechsolar.com
51
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

Ⅰ:For Exterior Tracker (as shown in below figure)

Tie the motor cable with cable ties, make sure the cable loop radius is larger than 50mm.

The reserved cable of antenna cannot be too long, it should be tied together with motor
cable and control box cables on the purlin bracing.

Ⅱ:For Interior Tracker (as shown in below figure)

The reserved cable of antenna cannot be too long, it should be tied together with motor
cable and control box cables on the torque tube.

www.arctechsolar.com
52
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

A.4.2. COMMUNICATION BOX WIRING

Requirements for the communication box power supply:


 220VAC±10%
 50/60Hz
 200W
Requirements for the communication box cable:
 Flexible cable
 Rated voltage 300/500AC,
 Temperature resistance 125℃
 UV resistance F2
 STP (shield twisted pair)
 Recommended Communication distance is within 100m given the onsite electrical
installation

www.arctechsolar.com
53
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

A.4.3. WIND SENSOR


The wind sensor post should be installed in an open & a leveled place. It should not be near wall or in a
place with big slope or terrain depression. The height of the wind cup’s center is 4m to 4.5m off the
ground.
Objects within 5m around the post should be at least 1m lower than the height of wind cup’s center.

Wind sensor must be adjusted to face north.

Foundation type for the wind sensor post should be followed as the one considered for the
project (direct ramming/predrill/concrete encased posts), but with the embedment of 1300mm.

Wind sensor

Communication
antenna holder

Mid pole

Communication Box
Wind sensor seat

1200mm±20
Wind Sensor Seat Connector

A.

General Overview of Wind Sensor Assay

www.arctechsolar.com
54
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

For the detailed dimension as annotated in B, can be referred in below figure.

Detailed Dimension of Wind Post Assy.

www.arctechsolar.com
55
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

Grounding is required on the wind sensor post above the ground. The post needs to be self-
grounded with the project grounding net. (Marked “A” in above figure.)
The grounding materials such as grounding cable or grounding flat iron can be used. Fixed with
self-tapping screw, welding or other installing methods according to the specific project.

Qty. Tightening Socket


Pos. Ref. Description per Torque Wrench sizes
figure [Nm] / [ft-lbs] DIN / ANSI
A -- Wind Sensor holder 1 - -
B -- Wind Sensor 1
a -- Flat Washer 6 4
8/6
b -- Spring Washer 6 4
c -- Bolt M6x30 4

Tightening
Qty. Socket
Torque
Pos. Ref. Description per Wrench sizes
[Nm] / [ft-
figure DIN / ANSI
lbs]
a -- Bolt M6x30 3
b -- Flat Washer 6 6
8/6
c -- Spring Washer 6 3
d -- Nut M6 3

www.arctechsolar.com
56
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

Qty. Tightening Socket


Pos. Ref. Description per Torque Wrench sizes
figure [Nm] / [ft-lbs] DIN / ANSI
A -- Antenna 1
300000929 Communication Antenna
B 1
Holder Hoop B
a -- Bolt M6x30 6 8/6
b -- Flat Washer 6 12
c -- Spring Washer 6 6
d -- Nut M6 6

Communication Antenna
Holder hoop A

Qty.
Tightening Socket
per
Pos. Ref. Description Torque Wrench sizes
figur
[Nm] / [ft-lbs] DIN / ANSI
e
a -- Bolt M10x50 4
b -- Flat Washer 10 8
40 /30
c -- Spring Washer 10 4
d -- Nut M10 4
Communication Antenna
A 300000574 1
Holder
Communication Antenna
B 300000947
Holder hoop A
www.arctechsolar.com
57
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

Tightening
Qty. Socket
Torque
Pos. Ref. Description per Wrench sizes
[Nm] / [ft-
figure DIN / ANSI
lbs]
A 300023805 Wind Sensor Mid Pole 1
a -- Bolt M10x50 4
b -- Flat Washer 10 8 40 / 30
c -- Spring Washer 10 4
d -- Nut M10 4

Tightening
Qty. Socket
Torque
Pos. Ref. Description per Wrench sizes
[Nm] / [ft-
figure DIN / ANSI
lbs]
A 300023054 Communication Box Hoop 2
B 300023053 Communication Box Mounting Plate 2
40 / 30
a -- Bolt M10x50 4
b -- Flat Washer 10 8
www.arctechsolar.com
58
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

c -- Spring Washer 10 4
d -- Nut M10 4

Tightening
Qty. Socket
Torque
Pos. Ref. Description per Wrench sizes
[Nm] / [ft-
figure DIN / ANSI
lbs]
A 300022702 Communication Box 1
a -- Bolt M8x25 2
b -- Flat Washer 8 4 15 / 11
c -- Spring Washer 8 2
d -- Nut M8 2

A
c

Qty. Tightening Socket


Pos. Ref. Description per Torque Wrench sizes
figure [Nm] / [ft-lbs] DIN / ANSI
A 300023138 Wind Sensor Seat Connector 1
a -- Big Flat Washer 16 4
210 / 155 24 / 24
b -- Spring Washer 16 4
c -- Nut M16 4

www.arctechsolar.com
59
SKYSMART II-MA-ECIDI-maroc-34MW ▌INSTALLATION MANUAL

d
A
c

Qty. Tightening Socket


Pos. Ref. Description per Torque Wrench sizes
figure [Nm] / [ft-lbs] DIN / ANSI
A 300023804 Wind Sensor Seat 1
a -- Bolt M16x60 4
b -- Flat Washer 16 4
210 / 155 24 / 24
c -- Spring Washer 16 4
d -- Nut M16 4
e -- Big Washer 16 4

www.arctechsolar.com
60