Professional Documents
Culture Documents
TECHNICAL SPECIFICATION
FOR
PULL OUT TEST PROCEDURE
PROJECT
JORDAN RISHA 50 MW PV PROJECT
CLIENT
ACWA POWER
EPC CONTRACTOR
STERLING & WILSON PVT. LTD
OWNER’S CONSULTANT
TYPSA GROUP
Rev 01
DOCUMENT NO. DOCUMENT TITLE
Date: 10/11/2018
TECHNICAL SPECIFICATION FOR PULL OUT
SWLD-ACWA-JOR-50MW- Pages 16
TEST PROCEDURE
C-DOC-PTP-206
CC SH DG
FOR APPROVAL PRPD. BY CHKD. BY APPR.BY
STATUS ISSUE AUTHORITY
TECHNICAL SPECIFICATION FOR
PULL OUT TEST PROCEDURE
This document has been generated for pull out test procedure of the solar power plant being constructed by
Sterling and Wilson Pvt. Ltd. This document must not use anywhere until it is specially released for the
project.
Copyright
All rights reserved. No part of this publication may be reproduced, distributed, or transmitted in any form or
by any means, including photocopying, recording, or other electronic or mechanical methods, without the
prior written permission of the publisher, except in the case of brief quotations embodied in critical reviews
and certain other non-commercial uses permitted by copyright law. For permission requests, write to the
publisher, addressed “Attention: Permissions Coordinator,” at the address below.
Document History
PJE-000005 Rev. C ©NEXTracker, Inc., 2017 CONFIDENTIAL/PROPRIETARY Contents subject to change without notice
NEXTracker General Requirements for Pile Load Testing page 2 of 13
Contents
Introduction ....................................................................................................................................................... 3
1.1 Summary and Scope............................................................................................................................................ 3
1.2 Submittals .......................................................................................................................................................... 3
1.3 Project Conditions ............................................................................................................................................... 4
Products (Materials and Equipment)................................................................................................................. 4
2.1 Apparatus for Applying and Measuring Loads .................................................................................................... 4
2.2 Testing Equipment and Apparatus .................................................................................................................... 4
Execution ........................................................................................................................................................... 5
3.1 Referenced Documents....................................................................................................................................... 5
3.2 Test Pile Preparation ........................................................................................................................................... 5
3.3 Load Test Procedure ........................................................................................................................................... 5
Report ................................................................................................................................................................ 7
4.1 Field Report ......................................................................................................................................................... 7
4.2 Pile Design Report ............................................................................................................................................... 7
Acceptance Criteria............................................................................................................................................ 8
Appendices
A. Test Load Table ................................................................................................................................................ 10
B. Vertical Load Test ............................................................................................................................................ 12
C. Lateral Load Test.............................................................................................................................................. 13
PJE-000005 Rev. C ©NEXTracker, Inc., 2017 CONFIDENTIAL/PROPRIETARY Contents subject to change without notice
NEXTracker General Requirements for Pile Load Testing page 3 of 13
Introduction
1.1 Summary and Scope
Testing includes axial tensile and lateral loading of driven steel W6 piles or other Grade 50 steel sections approved by
NEXTracker.
The test method described in these specifications measures the axial and lateral deflections of a vertical pile when subjected
first to axial tension and second to lateral loading.
The contractor hires or engages a qualified engineer to design and approve all loading apparatus, loaded members, support
frames, and test procedures.
1.2 Submittals
Before a pile test, submit the following documentation for review:
Product Data: The contractor submits the product catalog for the following items:
• Hydraulic jack
• Tension dynamometer
• Dial gauge
• Rigging sling and hand pull winch
Shop Drawings:
• Site plan: Depict layout of pile location subject to testing with corresponding coordinate referenced from the legal
boundary of the site. The site plan shows all existing ground utilities on the site. Test pile location is not located closer
than 20 ft (6.1 m) to the existing utility.
• Include arrangement of static pile reaction frame, reaction anchor piles, equipment, and instrumentation. Submit
structural analysis data signed and sealed by the qualified professional engineer responsible for their preparation.
Qualification Data: Present data for qualified personnel, professional engineer, and the testing company conducting the pile
load testing.
Calibration Certificates:
• Submit calibration certificate issued by an approved testing agency accredited by ASTM or AASHTO for dial gauge and
tension dynamometer.
• Calibration certificates are not older than 6 months at the time of pile load testing; they bear the signature and/or
stamp/seal of the agency performing the calibration. The serial numbers of the gadgets, instruments, or equipment
corresponds with the numbers listed in the certificate.
• A sticker bearing the dates of calibration are visibly attached to the gadgets, instruments, and equipment.
Pile Load Testing Records and Final Report: Submit records and report within one week after completing test.
PJE-000005 Rev. C ©NEXTracker, Inc., 2017 CONFIDENTIAL/PROPRIETARY Contents subject to change without notice
NEXTracker General Requirements for Pile Load Testing page 4 of 13
The contractor ensures that the testing company gathers information about the site. Any data provided by NEXTracker or its
client are for information only. The contractor is responsible for independently verifying all site conditions before performing
work and does not rely upon NEXTracker-supplied information for accuracy. The contractor also instructs the testing company
not to rely upon such information. All NEXTracker-provided information is therefore subject to verification by the testing
company.
instability. Test members and apparatus have flat, parallel bearing surfaces. The support reactions are designed and
constructed to prevent instability and to limit undesired rotations or lateral displacements.
• A qualified engineer designs and approves all loading apparatus, loaded members, support frames, and loading
procedures. The apparatus for applying and measuring loads, including all structural members, is of sufficient size,
strength, and stiffness to safely prevent excessive deflection and instability.
Tension Dynamometer: The tension dynamometer has a calibration to at least the maximum anticipated load capacity
performed within the 6 months before each test or series of tests. The contractor furnishes the calibration report(s) before
performing a test. Each dynamometer is certified and calibrated per Section 1.2. Calibration Certificate.
Gauges: Pressure gauges have minimum graduations less than or equal to 1% of the maximum applied load and have a
permissible error of 1% of the span. Each gauge is certified and calibrated per Section 1.2. Calibration Certificate.
PJE-000005 Rev. C ©NEXTracker, Inc., 2017 CONFIDENTIAL/PROPRIETARY Contents subject to change without notice
NEXTracker General Requirements for Pile Load Testing page 5 of 13
Execution
3.1 Referenced Documents
ASTM Standards:
• D 3689-07 Test Methods for Deep Foundations Under Static Axial Tensile Load
• D 3966-07 Test Methods for Deep Foundations under Lateral Load
This specification is an adaptation of the referenced ASTM standards to satisfy the specific objectives of the NEXTracker pile
load testing program. The most significant departure from the referenced ASTM standards is the rapid loading sequence and
duration because the controlling design loads to the solar PV frame are a result of short-duration wind loading.
PJE-000005 Rev. C ©NEXTracker, Inc., 2017 CONFIDENTIAL/PROPRIETARY Contents subject to change without notice
NEXTracker General Requirements for Pile Load Testing page 6 of 13
5. Attach sling to post at 2.5 ft (.75m) above ground to tension dynamometer; slowly apply horizontal load with a hand-
pulled winch supported on cribbing to reaction system.
6. Apply incremental load in accordance to load schedule (see Appendix B) and record lateral displacement at 500, 1000,
1500 lb and release back to zero.
7. During each load interval, keep the load constant for a time interval of not less than 1 minute and not more than 2
minutes, using the same time interval for all loading increments throughout the test.
8. Continue load test in accordance to tension load schedule in Appendix A until failure displacement of 1.0 in. (25.4 mm) or
until testing equipment either reaches capacity or no longer holds the applied load without slippage.
Below are the general and standard requirements typically for load test as per the size, But the proposed test at Site is
preliminary to verify the ramming feasibility and basic design.
1. Number of pile load test locations per MW for the project is suggested in Table 1. Typically, test two piles at each
location, with one pile W6x9 or approved section, which has a flange width of 4 in. (100 mm) and another pile W6x15 or
approved section with a 6-in. (150 mm) flange width or at embedment depths shown on pile test plan.
2. Per discretion of the engineer, the number of tests may be adjusted to reflect variations in site plan and geotechnical
zones. During pile driving, if one location exhibits unusual soft soil conditions (i.e., less than 10 seconds to reach a 6-ft
embedment depth), suggest adding 4 piles around the parameter of the soft pile to delineate the localized soft soil
condition.
Array Size, MW MW Array Ground Coverage, acre Number of Test Locations
1 to 10 10 40 4
11 to 30 20 120 6
31 to 50 20 200 8
51 to 100 50 400 10
101 to 150 50 600 14
151 to 250 100 1400 18
251 to 350 100 1800 20
351 to 500 150 2000 24
501 to 650 150 2600 30
651 to 800 150 3200 34
801 to 1000 200 4000 40
PJE-000005 Rev. C ©NEXTracker, Inc., 2017 CONFIDENTIAL/PROPRIETARY Contents subject to change without notice
NEXTracker General Requirements for Pile Load Testing page 7 of 13
Report
General:
a. Date of pile installation/date of test
b. Project identification and location
c. Test site location
d. If available, nearest test boring test location
The pile test report includes a pile test summary in the format shown in Table 2.
PJE-000005 Rev. C ©NEXTracker, Inc., 2017 CONFIDENTIAL/PROPRIETARY Contents subject to change without notice
NEXTracker General Requirements for Pile Load Testing page 8 of 13
Acceptance Criteria
The thresholds for pile acceptability are as follows:
• Criterion 1: Displacement in tension load = 0.75 in
• Criterion 2: Displacement in lateral load at 4 in. from grade = 1.00 in.
• Criterion 3: Drivability = All test piles are driven at specified embedment.
PJE-000005 Rev. C ©NEXTracker, Inc., 2017 CONFIDENTIAL/PROPRIETARY Contents subject to change without notice
NEXTracker General Requirements for Pile Load Testing page 9 of 13
APPENDIX
PJE-000005 Rev. C ©NEXTracker, Inc., 2017 CONFIDENTIAL/PROPRIETARY Contents subject to change without notice
NEXTracker General Requirements for Pile Load Testing page 10 of 13
kN kN
Referring to the top of pier loads: top of pier is at 4.667 feet (1.42 m) above grade level.
Moment
For Heavy Array Pier,
is calculates as followed:
PJE-000005 Rev. C ©NEXTracker, Inc., 2017 CONFIDENTIAL/PROPRIETARY Contents subject to change without notice
NEXTracker General Requirements for Pile Load Testing page 11 of 13
The diameter of borehole shall be less than size of the post to ensure the required bond is generated
between backfilled soil and the steel post.
PJE-000005 Rev. C ©NEXTracker, Inc., 2017 CONFIDENTIAL/PROPRIETARY Contents subject to change without notice
NEXTracker General Requirements for Pile Load Testing page 12 of 13
Test No.
Predrilled (yes/no)
VERTICAL LOAD TEST
Drive Date
N
Coordinate
W
Steel Section Profile
200% Lateral
0 0
250 1
500 1
750 1
1000 1
1500 1
2000 1
2500 1
3000 1
3500 1
4000 1
4500 1
XXX 1
XXX 1
19 mm 19 mm
XXX 1 (.75 in) (.75 in)
0 1
25.4 mm 25.4 mm
XXX 1 (1 in) (1 in)
PJE-000005 Rev. C ©NEXTracker, Inc., 2017 CONFIDENTIAL/PROPRIETARY Contents subject to change without notice
NEXTracker General Requirements for Pile Load Testing page 13 of 13
Test No.
Predrilled (yes/no)
LATERAL LOAD TEST
Drive Date
N
Coordinate
W
Steel Section Profile
Tipo de
200% Lateral
perfil
Carga de diseño
(Design Load) Fvd (Kg)
0 0
500 1
1000 1
1500 1
0 1
1500 1
2000 1
2500 1
0 1
2500 1
3000 1
3500 1
0 1
3500 1
4000 1
4500 1
0 1
4500 1
5000 1
5500 1
0 1
XXX 1
XXX 1
25.4mm 25.4mm
XXX 1 (1.0 in) (1.0 in)
PJE-000005 Rev. C ©NEXTracker, Inc., 2017 CONFIDENTIAL/PROPRIETARY Contents subject to change without notice
866.52
866.50
P1 P2
866.43
866.13
866.34
866.55
STANDARD ARRAY PIER
866.77
867.15
867.64
868.23
869.10
870.53
871.15
871.28
SEAL
871.21
871.35
ZONE-III 871.27
871.46
B
871.51
RD
YA
CH
IT
SW
2 kV
13 871.27
P7 P8 ZONE-III Y
871.30
MA
COMMON
BURNT
4(L)x4(W)
OIL
AR
PIT
x2(D)
OR
IN
MP E
TE FIC
CO
OF
NT
871.38
P5
RO
ER
P6
AIN
L RO
NT RE
CO R WAE
FO US
OM
HO
871.53
871.83
871.93
872.14
872.11
871.24
871.63
P9 P10
ZONE-III
SECURITY
866.22 ROOM
MAIN GATE
P3 P4
ZONE-II
RISHA
S&W
JORDAN
EMEA
P15 P16
P19 P20
ZONE-III
P11 P12
PROJECT NUMBER:
17446
SHEET TITLE:
TEST PILE
ZONE-I LOCATIONS
P21 P22 P17 P18
NO. REVISION DATE INIT.
A ZONE MARKING 08/28/2016 VR
E
P23 P24 F
K
SITE DETAILS
LATITUDE 32°34'20.0"N
LONGITUDE 39°00'37.0"E
SNOW LOAD 30.08 PSF
WIND LOAD 120MPH ASCE 7-10
STOW STRAT. 50 STOW
NEXTRACKER 2.4.1 I M-6-8-8-8-8-7
DATE 08/28/2018
DRAWN BY VR
CHECKED BY KM
SHEET NO.: