You are on page 1of 4

Document No.

JGPL-EPC.03-GRIAN- TECHNICAL SPECIFICATION OF


AMPS-RE-CV-002 GEOTECHNICAL INVESTIGATION
Revision No. R0
Date: 19-01-2023

PILE TEST FOUNDATION TEST METHODOLOGY


As per IS 2911 Part IV

A) Construction of Pile

Following steps are adopted to cast a pile:

Step-I Drilling a bore hole into the ground for mentioned (in the drawing) diameter and
depth.
Step-II Placing the steel leg inside the borehole.
Step-III Concreting the bore hole and providing collar/pedestal of mentioned height.
Step-IV Curing of concrete to be done

B) Testing of Pile

 Test shall be carried out as per latest IS:2911 Part IV.


 Piles shall be tested for Pull out, Lateral loads & compression loads till maximum
load failure at site

C) List of Equipment:

Lateral Test
 Pressure Pumping unit
 Hydraulic Jack of suitable capacity having load gauge of 100KN.
 Dial gauge with least count of 0.01 mm
 Steel Bearing Plate
 Appropriate chains, fasteners, and riggings as required.
Axial Test
 Pressure Pumping unit
 Hydraulic Jack of suitable capacity having load gauge of 100KN.
 Dial gauge with least count of 0.01 mm
 Steel Bearing Plate
 ISMB supporting beam (ISMB 125mm)
 Supporting Post.
 MS plate clamp
 Appropriate chains, fasteners, and riggings as required

D) Application of Load on Test Piles through Jack:

1. The test shall be carried out for failure load or following displacement, whichever is
achieved earlier.
1.1) For Pull Out Test: 12mm total displacement
1.2) For Lateral Test: 5 mm total displacement
1.3) For Ultimate compression load: 12mm total displacement
Document No.
JGPL-EPC.03-GRIAN- TECHNICAL SPECIFICATION FOR
AMPS-RE-CV-002 GEOTECHNICAL INVESTIGATION
Revision No. R0
Date: 19-01-2023

2. The loading should be applied in increments of about 20% up to failure Load Test Pile
value.
3. The next increment should be applied after the rate of displacement is nearer to
0·1 mm per 30 minutes ( ie 0.003 mm per minute)
3.1) Each Load & next increment of load application to be at least for 15
minutes.
3.2) Last Increment of Load application to be at least for 30 minutes.
3.3) Load should be applied at 1.355m & 0.15m above ground level on the
respective leg sections as per attached Pile Testing layout.
4. Deflections shall be recorded at minimum of 0.5tons incremental loads for compression &
0.2tons for lateral test or as per vendor’s machine.
5. All instruments calibration report shall be available during Pile testing.
6. Grade of concrete shall be M25 as per IS-456.
7. OPC 43/53 grade of cement to be used for concrete.
8. Support pile to be provided for lateral tests at 1.5m centre to centre distance from the test
pile.
9. Pile testing to be done till final breakage load.

E) Preparation of Report
Report shall be prepared as per criteria given in latest IS:2911 Part IV, along with safe and
ultimate load calculation.
Submit records and report within one week after completing test.

SCHEDULE OF BORED CAST-IN SITU CONCRETE PILE FOR TRACKER


LOAD
PILE DEPTH PULLOUT LATERAL APPLICATION
DIAMETER COMPRESSION
SR.NO. BELOW GL TEST TEST HEIGHT
(mm) TEST POINTS
(m) POINTS POINTS ABOVE GL
(m)
1 300 1.70 POT-01 LT-01 CP-01 1.355
2 300 1.85 POT-02 LT-02 0.150
3 300 2.00 POT-03 LT-03 1.355
4 300 2.20 POT-04 LT-04 CP-02 0.150
5 300 2.40 POT-05 LT-05 1.355
6 300 2.70 POT-06 LT-06 0.150
7 300 3.00 POT-07 LT-07 CP-03 1.355
8 300 1.70 POT-08 LT-08 0.150
9 300 1.85 POT-09 LT-09 1.355
10 300 2.00 POT-10 LT-10 CP-04 0.150
11 300 2.20 POT-11 LT-11 1.355
12 300 2.40 POT-12 LT-12 0.150
13 300 2.70 POT-13 LT-13 CP-05 1.355

Page |1
Document No.
JGPL-EPC.03-GRIAN- TECHNICAL SPECIFICATION FOR
AMPS-RE-CV-002 GEOTECHNICAL INVESTIGATION
Revision No. R0
Date: 19-01-2023

14 300 3.00 POT-14 LT-14 0.150


15 300 1.70 POT-15 LT-15 1.355
16 300 1.85 POT-16 LT-16 CP-06 0.150
17 300 2.00 POT-17 LT-17 1.355
18 300 2.20 POT-18 LT-18 0.150
19 300 2.40 POT-19 LT-19 CP-07 1.355
20 300 2.70 POT-20 LT-20 0.150
21 300 3.00 POT-21 LT-21 1.355
22 300 1.70 POT-22 LT-22 CP-08 0.150
23 300 1.85 POT-23 LT-23 1.355
24 300 2.00 POT-24 LT-24 0.150
25 300 2.20 POT-25 LT-25 CP-09 1.355
26 300 2.40 POT-26 LT-26 0.150
27 300 2.70 POT-27 LT-27 1.355
28 300 3.00 POT-28 LT-28 CP-10 0.150
29 300 1.70 POT-29 LT-29 1.355
30 300 1.85 POT-30 LT-30 0.150
31 300 2.00 POT-31 LT-31 CP-11 1.355
32 300 2.20 POT-32 LT-32 0.150
33 300 2.40 POT-33 LT-33 CP-12 1.355
34 300 2.70 POT-34 LT-34 CP-13 0.150
35 300 3.00 POT-35 LT-35 0.150
36 300 1.70 POT-36 LT-36 0.150
37 300 1.85 POT-37 LT-37 CP-14 1.355
38 300 2.00 POT-38 LT-38 0.150
39 300 2.20 POT-39 LT-39 CP-15 0.150
40 300 2.40 POT-40 LT-40 CP-16 1.355
41 300 2.70 POT-41 LT-41 0.150
42 300 3.00 POT-42 LT-42 0.150
43 300 1.70 POT-43 LT-43 0.150
44 300 1.85 POT-44 LT-44 CP-17 1.355
45 300 2.00 POT-45 LT-45 0.150
46 300 2.20 - LT-46 1.355
47 300 2.40 - LT-47 CP-18 0.150
48 300 2.70 - LT-48 1.355
49 300 3.00 - LT-49 0.150
50 300 1.70 - LT-50 1.355
51 300 1.85 - LT-51 0.150
52 300 2.00 - LT-52 1.355
53 300 2.20 - LT-53 CP-19 0.150

Page |2
Document No.
JGPL-EPC.03-GRIAN- TECHNICAL SPECIFICATION FOR
AMPS-RE-CV-002 GEOTECHNICAL INVESTIGATION
Revision No. R0
Date: 19-01-2023

54 300 2.40 - LT-54 1.355


55 300 2.7 - LT-55 CP-20 0.150

Page |3