Professional Documents
Culture Documents
Increased Cost
This is an important factor in any job, but who pays for this? The project engineer
has more important things on his mind. The construction superintendent is looking at
the overall schedule, so the installer or end user pays, either in dollars or equipment
and foundation problems down the road.
Figure 12.1 Head box can facilitate grout placement under large skid-mounted equipment.
Figure 12.2 The ability of the grout to flow and sufficient clearance is necessary.
Skid Grouting 153
Figure 12.4 Have enough people at the job site to accomplish the various tasks associated
with grout placement.
steel?” Epoxy grout will develop some type of a bond to whatever it touches. How well it
bonds depends on the surface profile and the extent of contamination. Most epoxy grouts
will develop a bond of about 2,000 psi to properly prepared steel. Properly prepared steel
is a surface that has been sandblasted to white metal with a 3–5 mil surface profile.
The strength of bond a paint or primer will develop is best determined by asking
the manufacturer of that product.
Figure 12.5 Mixing of the liquids takes at least two people, maybe more to keep up with the
mixer team.
Figure 12.6 Mixing teams should work together during grout mixing and placement.
156 The Grouting Handbook
Figure 12.7 Grout placement may require more wheelbarrows than mixers since it may take
longer to place than to mix.
liquids into the mortar mixer and ensure proper mixing. The other workers should be
responsible for opening the aggregate bags and adding the correct amount of aggre-
gate to the liquid mixture. Depending on the size of the area to be grouted this could
require several mixers.
Two or more people should transport the completed mixture of epoxy grout from
the mortar mixer to the various areas around the piece of equipment to be grouted
(Figure 12.7).
Two or sometimes even three people are needed to ensure that the material is
properly placed and spread out, if necessary.
One person should be in charge to oversee the work, coordinate the different
stages, and direct the placement of the epoxy grout.
At least nine people or more are required to do the job right. Crew size is depend-
ent on skid size and the amount of grout to be poured.
Figure 12.8 Pouring the grout and setting the skid will probably require some planning but is
possible.
Several large skids have been set directly from the truck transporting them into
uncured epoxy grout. With a little planning and forethought, you can use the follow-
ing methods to do the same:
1. Before the truck transport and lifting crane arrives at the job site, chip and form the foun-
dation and set the jackscrew pads in epoxy putty, leveling them in two directions. After the
putty has set up, glue 2 in. urethane foam pipe insulation to the jack pads.
2. After the skid arrives at the job site and before the crane lifts it off the truck, back out the
jackscrews, install the jam nuts, and reinstall the jackscrews. Set the skid directly on the
foundation, level it, and place at the correct elevation using the jackscrews. After the lev-
eling is complete, use the jam nuts to secure the jackscrews.
3. Lift the skid off of the foundation and move it away. Pour epoxy grout over the foundation
to a depth of ¼ in. below the final required elevation of the grout. The urethane pipe insula-
tion prevents the grout from getting between the jackscrews and the jackscrew pads, and
the jackscrew from coming in contact with the epoxy grout.
4. Set the skid back onto the foundation and into the epoxy grout. After the grout cures, back
off the jackscrews, tighten the anchor bolts, and remove the forms.
The result is 100% contact under the skid and a much quicker grout time.
NOTE: Ambient temperature and epoxy grout pot life play an important part in
a successful grout installation of this type. Also, having more than one mortar
mixer (as a backup) is highly recommended.
158 The Grouting Handbook
Skid Chocking
Chocking of skid-mounted equipment is dependent on the rigidity of the skid itself.
Always check with the original equipment manufacturer (OEM) or the skid manu-
facturer to determine the suitability or practicality of chocking skids.
You can do skid chocking in the following ways:
Base grout cap with epoxy chocks.
Prior to putting the skid on the foundation, install and secure the expansion
joints. Fill all anchor bolt sleeves (where required) with a suitable isolation mate-
rial. Wrap anchor bolts and then pour the epoxy grout a minimum of 2 in. thick.
This puts the top of the grout cap 2–2½ in. below the base of the skid’s final eleva-
tion (Figure 12.9).
After the grout is allowed to cure, the skid may be placed in position and brought
to final elevation. After the skid is level and at its final elevation, it is chocked at
each anchor bolt with an epoxy chocking compound (Figure 12.10).
●
Pouring chocks directly on concrete.
Very similar to pouring chocks on epoxy grout, this technique is possible, but not
recommended as the chocks will bear directly on the concrete. If using this type of
installation, follow these guidelines:
1. Paint the entire foundation with two coats of epoxy paint per the manufacturer’s
recommendation.
2. Set the skid. (Jackscrew pads should be round and have no sharp corners.)
3. Level the skid and install wrapping around anchor bolts and jackscrews.
4. Install chock forms.
Skid Grouting 159
Figure 12.10 Set the pump and connect it to the piping prior to pouring chocks.
Figure 12.12 The epoxy chock is sized and the angle iron forms are welded to the skid
around the anchor bolt. Soleplate jackscrews and the anchor are wrapped with pipe insulation
to isolate them and prevent bonding of the chocking compound.
Figure 12.13 They are careful to allow enough free length to the anchor bolt to gain
maximum clamping force.
Skid Grouting 161
Figure 12.14 The soleplates are set in position and rough leveled.
Figure 12.15 The compressor is set and aligned to the prime mover.
162 The Grouting Handbook
Figure 12.16 Once alignment is obtained the epoxy chocking compound is installed to secure
the soleplate.