LABOR COMPOSITION
PERSONNEL WAGES
1- CARPENTER A 655.57
1- LABORER 490.91
TOTAL 1146.48
LABOR COMPOSITION
PERSONNEL WAGES
1-CONST. FOREMAN 941.17
2- MASON 1311.14
9 - LABORER 4418.19
TOTAL 6670.5
LABOR COMPOSITION
PERSONNEL WAGES
1-STEELMAN 704.77
2 - LABORER 981.82
TOTAL 1686.59
SUMMARY
WAGES TOTAL 3,287.54 / m³
A. PORTLAND CEMENT
CYCLE TIME
LOADIED 1:
5 Kms = 0.29
35 Km/hr
W/o Load:
5 Kms = 0.22
45 Km/hr
LOADING:
110 BAGS/ TRIP = 0.37
300 BAGS/ HR
UNLOADING:
110 BAGS/ TRIP = 0.37
300 BAGS/ HR
TOTAL 1.24 SAY 1.00 hr /trip
SUMMARY
BASE COST 297.5
RENTAL 5.28
TOTAL 302.78 /bag
B. SAND & GRAVEL
CYCLE TIME
LOADIED 1:
20 Kms = 0.73
35 Km/hr
W/o Load:
20 Kms = 0.57
45 Km/hr
LOADING:
5.0 m³/ TRIP = 0.83
6 m³/ hr
UNLOADING:
5.0 m³/ TRIP = 0.83
6 m³/ hr
TOTAL 2.97 SAY 3.00 hr /trip
CYCLE TIME
LOADIED 1:
5.0 Kms = 0.77
35 Km/hr
W/o Load:
5.0 Kms = 0.60
45 Km/hr
LOADING:
150 PC/ TRIP = 0.75
200 PC/ hr
UNLOADING:
150 PC/ TRIP = 0.75
200 PC/ hr
TOTAL 2.87 SAY 3.00 hr /trip
SUMMARY (CEMENT)
BASE COST 600.00
RENTAL 75.00
TOTAL 675.00 /m³
D. FORM LUMBER
CYCLE TIME
LOADIED 1:
5.0 Kms = 0.72
25 Km/hr
W/o Load:
5.0 Kms = 0.51
35 Km/hr
LOADING:
1000 bd.ft/ TRIP = 0.33
3000 bd.ft/ hr
UNLOADING:
1000 bd.ft/ TRIP = 0.33
3000 bd.ft/ hr
TOTAL 1.90 SAY 2.00 hr /trip
EQUIPMENT COST: 2.00 hr/trip x 696.00 hr = 5.00 /bd.ft
RENTAL 1000 bd.ft/trip
SUMMARY (CEMENT)
BASE COST 35.00
RENTAL 5.00
TOTAL 40.00 /m³
E. RSB, CWN, TIE WIRES
CYCLE TIME
LOADIED 1:
5.0 Kms = 0.14
35 Km/hr
W/o Load:
5.0 Kms = 0.11
45 Km/hr
LOADING:
5000 Kgs/ TRIP = 1.00
5000 Kgs/ hr
UNLOADING:
5000 Kgs/ TRIP = 1.00
5000 Kgs/ hr
TOTAL 2.25 SAY 2.00 hr /trip
SUMMARY (CEMENT) RSB CWN TIE WIRE WELDING ROD (FUJI) 6013 1/8
BASE COST 50.00 70.00 80 150.00
RENTAL 0.28 0.28 0.28 0.28
TOTAL 50.28 70.28 80.28 150.28 /m³
CYCLE TIME
LOADIED 1:
5.0 Kms = 0.14
35 Km/hr
W/o Load:
5.0 Kms = 0.11
45 Km/hr
LOADING:
500 PC/ TRIP = 1.00
500PC/ hr
UNLOADING:
500 PC/ TRIP = 1.00
500PC/ hr
TOTAL 2.25 SAY 2.00 hr /trip
2. PLASTERING OF CHB
OUTPUT: 12 Sq.m/day
LABOR COMPOSITION
PERSONNEL WAGES
1-MASON 655.57
1 - LABORER 567.32
TOTAL 1,222.89
LABOR COST WAGES:
1,222.89 /day = 101.91
12 Sq.m/day TOTAL 101.91 /sq.m
SUMMARY
WAGES TOTAL 280.93 / m³