Professional Documents
Culture Documents
POLICY
The effect that our proposed construction work will have on the surrounding
environment.
Client specific requirements.
Identifying and taking appropriate preventive action on potential or actual adverse
environmental impact situations.
Implementing an environment in which we will be working.
Compliance with ISO 1400 and other Environmental laws
EXECUTIVE CHAIRMAN
Task Description: Replacing of conveyor belt & gearboxes
DEGREASING, ENVIRONMENL
CHEMICAL 3 5 15 High SOLIDIFY, BAG AND SEND TO RECYCLERS 3 4 12 Serious
CLEANING SPILLAGE
DIGRESSER
OLD BOLTS & NUTS CONTAMINATION,ENVIROMENT INDUCTION AND PPE TO ISSUED WARING
REMOVAL OF WASTE SCRAP METAL SPACE 3 4 12 Serious SINGS TO BE PLACE AND BARRICATE AND 3 2 6 Medium
MSDS TO USED ON CHEMICALS
SPILLS,DESPOSAL OF
REMOVAL OF OIL SPILLAGES 3 3 9 Medium USE A SPILL PLATE, 3 1 4 Low
OIL
GEARBOXES
REMOVAL OF OLD
REMOVE THE WASTE TO DISPOSAL SITE . PPE
CONVEYOR BELT AND CLEANING DUST, PULVARISED COAL 3 4 12 serious 3 2 6 Medium
TO BE ISSUED AND USED
PULLEYS
Occasionally 20 16 12 8 4
Probable 15 12 9 6 3
Unlikely 10 8 6 4 2
Improbable 5 4 3 2 1
2 Minor Minimal environmental effect 2 Unlikely An unlikely event, could occur i f control measures are disregarded
3 Significant Significant environmental effect 3 Probable An event which may occur despite existing control measures
4 Serious Major environmental effect that can be controlled 4 Occasionally An event l ikely to occur unless control measures are improved
5 Extreme Extreme environmental effect that cannot be controlled 5 Certain An event which will occur unless immediate controls are applied
1-4 Low Activities in this category present minimal levels of impact or risk and are unlikely to occur, proceed with these activities as planned and monitor against objectives
Activities in this category present minor levels of impact or risk. The application of risk management strategies to reduce the impact or risk is advised. Consider ways
5-9 Medium
of modifying the process or implementing controls to reduce the impacts and risks to as low as reasonably practicable (ALARP)
Activities in this category present serious and unacceptable levels of impact or risk. Consider ways of modifying the process and implementing controls to reduce the
10 + Serious
impacts and risks to as low as reasonably practicable (ALARP). Additional control measures and monitoring may be required.
Activities in this category present high levels of impact or ri sk and should not be allowed to proceed without very careful planning. Consider consulting specialists.
15 + High
The company should evaluate whether the activity i s actually necessary in the first place or whether alternative processes are available.
20 + Extreme Activities in this category present extreme levels of impact or risk, such as loss of life or breach of legislation and must not be undertaken.
The risk rating (R) is calculated by multiplying the likelihood (L) by the severity (S), L × S = R. In this way, the potential of an impact affecting operations is
evaluated according to its perceived severity. Where a legislative requirement for change is identified, an automatic score of 25 is given since immediate
corrective action is required to ensure compliance. All aspects which present legitimate concerns to major stakeholders or clients also receive an automatic
score of 25 to initiate immediate corrective action. The results of the above scoring methodology are recorded on the aspects and impac ts register. From this,
the impacts are prioritised for action on the basis of their risk score.
Evaluate the risks and Consider how likely it is that each hazard could cause harm by using risk ratings to prioritize risk. Determine whether or
Step 3 decide whether current not you need to do more to reduce the risk and implement control measures (actions list) if the risks are not adequately
controls are adequate controlled
Keep written records for future reference in order to demonstrate compliance to lega l requirements (e.g. air emissions,
Step 4 Record your findings
or controlled waste)
Review risk Review and revise the risk assessment when there is any significant change (e.g. new aspects arise due to new machines,
Step 5 assessments and revise substances and processes). Regularly review the risk assessment to check that the precautions for each aspect still
if necessary adequately control the risk and, if necessary, reassess the risk.
MANYAKAZA ENGINERING AND
CONSTRUCTION
ENVIRONMENTAL MANAGEMENT
THE ENVIRONMENT
Definition: The combination of external conditions that surround and influence a living
organism.
Ovio Gi Engineering has a responsibility towards the environment and aims to achieve
excellence in environmental management.
Sustained development is not possible without the protection and wise management of
our resource base. Responsible environmental management is a day-to-day commitment
that will result in sound business performance.
The effect that our proposed construction work will have on the surrounding
environment.
Client specific requirements.
Identifying and taking appropriate preventive action on potential or actual adverse
environmental impact situations.
Implementing an environment in which we will be working.
Velemseni Sibeko
EXECUTIVE CHAIRMAN
1. ENVIRONMENTAL MANAGEMENT SYSTEM
2. ENVIRONMENTAL POLICY
The Ovio Gi Engineering policy is to ensure that the biophysical and social
environment receives due consideration to ensure its protection, conservation,
enhancement and sustainability of the existing quality, within areas of contractual
extent.
3. PLANNING
Environmental Aspects
Environmental aspects will be identified for each project. This could be through
the Contract Document.
These mitigation measures will be, where possible, considered and formally
incorporated into risk assessments and followed through into the construction,
operation and maintenance stages.
Communication System
An effective communication system between the client, the environment control
officer the supervisory engineers and contractors will be established.
Reviews of Reports
Site inspections and report back meetings will be carried out monthly during
construction.
Reviews of Reports
Reviews of instruction given in site inspection reports will be discussed and evaluated
at the site meetings.
Senior Management:
The system: its function the hierarchy and reporting protocols
Middle Management:
As above plus the responsibilities of supervisory personnel.
Labor Force:
The inter relationship and importance of natural
elements both physical and biophysical. The
reasons for environmental management and control
action.
Communication
Effective records of documents on paper or in electronic form will be provided with easy
reference and access during construction activities.
Control of Documents
Operational Control
A Monitoring system shall be set in place to ensure that the procedures are
carried out in accordance with required level of standards. This shall
include
the monthly monitoring of rehabilitation progress in relation to the objectives.
Where appropriate documented procedures will be set up for periodically
evaluating and reviewing compliance with legal aspects
Non Conformance
Preventative actions will be agreed at site meetings and time limits set for these to
be executed.
Records
Records of all reports and decisions will be kept, maintained and stored for easy
access at any time.
6. MANAGEMENT REVIEW
1. INTRODUCTION
With Sound planning and practice this Environment Management Plan forms part of
the integrated Environmental Management process.
The following objectives are set to comply with the environmental policy.
Construction Phase
The following objectives are set to comply with the environmental policy.
a) Limit the extent and degree of change to the biophysical and socio economic
environment.
b) Improve the biophysical environment within the construction area where
downgraded or unstable conditions exist.
c) Enhance, where appropriate, the Quality of life for local communities affected by
the project.
d) Maintain effective communication links with the local communities.
e) Implement and practice a concurrent rehabilitation program to stabilize all new
landforms and disturbed areas within the construction area. This shall include the.
stripping, stockpiling and re-spreading of topsoil over new or disturbed landforms within
the construction area, to ensure rapid and effective vegetation establishment
4. MITIGATION MEASURES
The mitigation measures described here are those necessary to limit or prevent
environmental degradation and social and economic benefits during the lifetime of a
project.
All areas affected by construction works will need to be rehabilitated and re-
vegetated. This will include – temporary access roads, construction cams sites,
borrow pits, lay down areas, quarries, etc.
Bush and tree cleaning must be kept to an absolute minimum where temporary
structures are to be erected. It must be done in such a way to maximize the protection
of trees and other natural features. The environmental officer must, in collaboration
with an expert inspect all areas prior to bush and tree cleaning and mark those species
which are to be transplanted or which must remain intact.
Fauna identification must also be considered at this stage as they may be dependant
on the flora.
All wood, derived from bush and tree cleaning must be made available, free of
charge, to logic inhabitants. No personnel of LEKWABORWA CONSTRUCTION are
allowed to remove or sell any of the wood.
LEKWABORWA CONSTRUCTION DOCUMENT REFERENCE: REV 1
MAFOLOS I/SMS/01
ENVIRONMENTAL MANAGEMENT DATE: APRIAL 2013
PAGE: 3 OF 13
6. TOPSOIL
The special conditions of a contract must include for the stripping and stockpiling of
topsoil from the site for re-use. Topsoil is considered to be the top layer of soil
surface capable of sustaining growth and includes grass, roots and organic matter.
The areas to be cleared of topsoil should be all areas, which will be covered by
pacing, roads, structures, waste dumps and material storage.
7. QUARRYING
Borrow pits are usually relatively shallow pits where explosives are not used for the
excavation of material. Despite being shallow, borrow pits may cover large areas.
Material from borrow pits are usually used for the construction on the infrastructure
for a project.
No excavation of any borrow pit is allowed to start without the authorization of the
Environmental Officer. The Environmental Officer must inspect the proposed site for
suitability, and may give authorisation only after he has satisfied himself that the
proposed site will not impact negatively on the environment or local population. He
may consult with any affected party before making a decision
Borrow pit working areas, including stockpiles, must be clearly demarcated to ensure
that workers, plant, material or any other operation associated with the borrow pit do
not encroach onto surrounding land. The necessary steps must be taken to ensure that
livestock, wildlife, local residents or any unauthorized third party do not have access
to the borrow pit area.
The topsoil, where it exists, must be removed, along with the vegetation and be
stockpiled in an effective manner to avoid self compaction. This is to be used for
later rehabilitation of the area. Any other overburden must be removed to a separate
stockpile. Where necessary, berms must be constructed to divert storm water from
the operating areas of the borrow pit.
Upon closure of a borrow pit, the pit must be constructed to drain freely except if
local communities or authorities make a written request that the pit be left as a water
collection point.
If the pit is not to be used as a water collection point, the inner surface must be
shaped to a grade not steeper that 1:3 so as to minimize erosion. In areas where the
soil is loose or dispersive this gradient must be flattened to 1:4.
The final surface of the borrow pit must be constructed in such a manner that
drainage and the replacement of overburden and topsoil are facilitated. Rehabilitation
of borrow pits must always be done in such a manner that storm water erosion is
prevented.
Overburden and Topsoil must be replaced evenly over the entire borrow pit. Roads
and stockpile areas which served the borrow pit must be scarified and leveled after
the topsoil and overburden have been replaced. It may be necessary to install wind
breaks of appropriate material to prevent erosion while vegetation is re establishing.
The Environmental Officer must certify, in writing, upon final closure of the pit that
these guidelines have been followed.
All temporary construction camps and workers accommodation must conform to local
and national building regulations.
These structures must not adversely affect the natural surroundings or the local
population.
The campsite and workers accommodation will require rehabilitation at the end of a
contract. For this to be effective the topsoil must be stripped and stockpiled prior to
establishment of the camp. On completion the total area will require ripping and the
These pits must not be located within 100m of any water body or source such as well
or borehole. Such pits must be filled upon closure of the camp.
In areas where there is no waterborne sewerage the use of septic tanks, pit latrines and
/ or chemical toilets must be approved by local authorities. Full compliance with
local and national legal requirements is the minimum standard.
Provision for the removal of solid waste generated by the workers as well as by
workshops shall be made. Adequate litter bins are to be provided and workers must
be encouraged to use them.
Campsites must not be site on steep slopes as this will increase soil erosion. All
temporary structures must be removed at the end of a contract and any environmental
degradation due to these structures must be rectified to the satisfaction of the
Environmental Officer.
These areas must be stripped of topsoil, the topsoil must be stockpiled for later re-use.
These areas may be extensive and will require effective rehabilitation. The topsoil
will provide a good growth medium for the re-establishment of vegetation. The area
would need to be graded and ripped on completion after all machinery, foundations
etc. have been removed. Dust control measures must be set in place.
Concrete shall only be mixed in areas which have been specially designated for this
purpose. All concrete spilled outside these areas shall be promptly removed and
taken to a approved dump site.
LEKWABORWA CONSTRUCTION DOCUMENT REFERENCE: REV 1
LEKWABORWA/S MS/01
ENVIRONMENTAL MANAGEMENT DATE: APRIAL 2013
PAGE: 7 OF 13
After concrete mixing is complete, waste concrete shall be removed from the
batching area and disposed of at an approved dumping site. Storm water shall not be
allowed to flow through the batching area. Water laden with cement shall be
collected in a retention area for evaporation. The remaining cement sediment shall be
removed from time to time and disposed of in a manner as instructed by the Site
Agent.
On completion of a contract the area would need to be graded and ripped after all
machinery, foundations etc. have been removed.
Fuel and oil must be stored in bunded areas so that accidental spillage can be
prevented from contaminating a wide area. Fuelling, lubrication, repairs and
servicing of mechanical plant must be conducted in an orderly manner at designated
sites only.
These sites must be provided with oil and fuel catching pans and concrete slabs to
prevent liquids soaking into the ground. Spillage must be cleared up immediately.
All effluent discharged to rivers or other water courses shall at all times conform to
the general or special standard (water act, 1957). In certain instances when the local
population use water directly from rivers or wells, more stringent standards may be
required.
By the department of water affairs and forestry. The Environmental Officer must
ensure that all sampling and analysis of effluent, rivers and water courses are done
according to correct procedures and applicable standards.
All areas where wash or run off water may have polluting potential will be drained to
a central sedimentation basin and or oil separator.
An approved waste contractor will remove the contaminated water. A task analysis
sheet will control this.
Lekwaborwa construction shall take measures to the approval of the Site Engineer or
Environmental Officer to ensure that there is no undue storm water damage and soil
erosion resulting from construction activities inside and outside the construction
camps or work area.
Surface storm water shall, where possible, not be allowed to concentrate and flow
down cut or fill slopes without erosion protection measures being in place.
Overflow and/or scour channels shall be lined with stone pitching along their length
and at the point of discharge to prevent soil erosion.
The point of discharge shall be at a point where is dense natural grass or water
discharge channels, These channels shall not discharge straight down the contours but
shall be aligned at such angle to the contours that they have the least possible
gradient.
LEKWABORWA CONSTRUCTION DOCUMENT REFERENCE: REV 1
LEKWABORW A/S MS/01
ENVIRONMENTAL MANAGEMENT DATE: APRIAL 2013
PAGE: 8 OF 13
This work shall be carried out well in advance of the commencement to construction.
Included under archaeological sites are pre-historic artifacts rock paintings, old mine
workings, remnants or structure, burial grounds etc. Palaentological sites include fossils
and fossil rock deposits.
Archaeological and Palaentological sites must be preserved if they are of cultural, historic
or pre-historic significance.
All sites must be specifically surveyed for such finds. Finds, if any, must be reported to
the Environmental Officer who will decide after consultation with authorities, company
representatives and local communities whether work may go ahead.
Protection measures
Archaeological sites shall be protected by a free stand fence which will be at least 2m
outside the extremities of the site. The fence shall be clearly marked by danger tape or
sign boards.
The Site Manager shall advise workers of the penalties associated with the unlawful
removal of archaeological of palaentological artifacts as set out in the National
Monuments Act (Act 28 of 1969) section 12.
No employees shall gain access to any of these sites (whether fenced or unfenced) except
when authorised to do so by the Environmental Officer.
Random driving across terrain destroys vegetation and soil structures and creates
unsightly tracks that remain visible for years. Such tracks may also lead to soil erosion
and dust generation. Existing roads shall be used as far as possible. Vehicles must travel
on designated routes only.
No new access roads other than detailed by the Engineer of Environmental Officer shall
be developed by anyone.
Roads shall be watered on a regular basis. All temporary roads no longer required shall
be decommissioned, ripped and the land rehabilitated to its original use. All storm water
channels or berms shall be constructed to allow for easy vehicular crossing.
Access roads on slopes shall not be constructed directly up or down the slope but across
the contour utilising switchbacks, the corners of which shall be protected on the down
slope by gabions.
Regular wetting of roads and construction sites may be necessary to ensure that dust does
not become a nuisance for the work environment and the local community.
Dust masks must be provided to workers working in a dust environment. Paved surfaces
within the construction area will be washed off regularly. Employees to repot any
excessive dust conditions to the Engineer of Environmental Officer. Regular inspections
to be carried out at areas of concern.
Having due regard for the proximity to the site and local communities any operations
which will result in undue noise shall be restricted to hours laid down by the Engineer or
Environmental Officer.
The necessary test will be conducted in working and surrounding areas. The noise levels
must not exceed 85 DB(A).
All legal requirements pertaining to worker noise exposure and hearing conservation
must be maintained.
The necessary safety equipment must be issued to all employees working in a noise
environment. Safety Signs will be displayed in noise zones. Tests will be carried out to
demonstrate compliance with the applicable standards as set out in the regulations of the
Environmental Conservation Act 1989. All records must be maintained.
Where water is withdrawn from a river, borehole or wells the Environmental Officer
must make sure that all legal requirements pertaining to the abstraction are met.
Regular test are to be carried out to ensure the water maintains its potability.
Safety Signs to be displayed “Safe for Drinking” or “Not Safe for Drinking”.
Non hazardous refuse must be disposed in a manner so as to minimize health risks and an
adverse impact on the environment. An adequate number of receptacles for litter and other
waste must be provided at camps and work areas. The receptacles must be emptied on a
regular basis.
On site approved refuse disposal must be in pits in ground with a deep water table. No refuse
sites may be constructed over or near rivers, wells or boreholes.
All refuse must be compacted and covered with 150mm soil. This is to be done on a daily
basis if refuse is dumped daily. If refuse is not dumped daily the compacting and covering
must be done when disposing refuse into the pit.
Berms or storm water channels must be constructed as necessary to prevent surface water
flow into the refuse disposal trench.
Steps must be taken to keep the disposal site tidy and to eliminate nuisances. These steps
may include fences and gates to keep animals and people out and to prevent windblown
debris.
At the end of a contract the refuse site must be closed to the satisfaction of the Environmental
All refuse drums are to be marked (type of waste). All hazardous refuse must be taken to an
appropriately licensed landfill site for disposal.
Used oils must be stored separately in clearly marked containers. These containers must be
removed by a waste contractor for recycling.
Gas cylinders will be stored in a well secured area under roof, away from any building.
The storage area must be well ventilated. Gas cylinders must be stored separately in an
upright position and secured. Full and empty cylinders must be segregated
Signs must be displayed for full and empty cylinders. Safety signs and fire extinguishers
must be posted. Control of cylinders must be implemented.
The above is punishable by law and could lead to imprisonment or high fines. It
could also lead to confrontation with the local communities.
All employees should try to understand the cultural beliefs of the local community
where construction work will be executed.
Employees must treat members of the local community and their traditions with
respect.
Protected areas demarcated on site and off the site shall not be entered by
workers.
Employees shall not build informal housing in the area or encourage members of
their family to do so.
Employees shall abide by all rules and regulations set out by clients.
No forced labor or harmful child labor will be allowed.
Crime and theft will lead to immediate dismissal and imprisonment.
All members of the organization should understand and encourage the importance of
achieving the environmental objectives and targets for which they are responsible and
accountable for.
Motivation through education and training will be done to continually improve the
objectives encouraging all employees to make suggestions and report environmental
concerns that could lead to improved environmental performance.
Induction training on environmental issues will be conducted with all new employees.
Awareness training will be done at toolbox talks by the Site Supervisor or Foreman.
Where environmental matters do not conform to, or deviate from, procedures, a non-
conformance report will be raised.
Non-Conformance Reports must be discussed at the monthly meeting to clear out the
corrective and preventive action required to rectify the problem. N.C.R’s must be
handled as per the Quality Management System Procedure
LEKWABORWA/QMS/14-15-16, control of Non Conforming Product, Corrective
and Preventive Action.