Professional Documents
Culture Documents
Prior to the application of sprayed concrete, the nozzleman should be aware of the
required properties of the sprayed concrete lining. This may include the required
thickness, profile and knowledge of any safety-critical elements of the lining that need
careful attention during spraying, e.g. sidewall connection joints to main lining.
Immediately after excavation and before application of sprayed concrete, the exposed
ground should be geologically mapped or photographed in accordance with the
procedures of the tunnelling project.
For effective adhesion of the sprayed concrete to the substrate, the surface to receive
the sprayed concrete should be damp and cleared of loose material by scaling and the
use of compressed air and water from the nozzle. Sprayed concrete overspray from the
previous advance that is loosely adhered to mesh and steel arches should also be
removed.
In-treated groundwater ingress into the tunnel often has detrimental effects on the quality
and strength of the sprayed concrete. Typically, un-skilled teams will attempt to spray
over active water ingress using sprayed concrete with high accelerator dosages.
1
10.2 General spraying techniques
The delivered mix to the pump should be checked for batch time and for workability (wet-
mix). All delivery lines from the pump to the nozzle should be securely fixed and
lubricated with grout. Ifthere are delays, then the workability and life of the mix should be
checked. Under no circumstances should water be added to the mixer, or old mixes that
have undergone hydration be used. The use of hydration control admixtures, such
Delvocrete Stabiliser is therefore recommended at all time and projects.
With accelerated sprayed concrete mixes, it is essential not to apply sprayed concrete
into the works until the sprayed concrete exhibits the correct setting performance. This is
typically carried out be spraying directly onto the tunnel face until the correct setting
performance is observed. Furthermore, the correct air pressure and volume for the
specific spraying operation is evaluated by the nozzleman and adjusted accordingly.
One of the skills of the nozzleman is to recognise the need for applying sprayed
concrete in a manner that minimises the risk of loosened blocks from falling, but also to
prevent the concrete from sagging or even falling out of the crown sections. To meet this
goal, the nozzleman should firstly fill all overbreaks and zones of substrate weakness,
such as cracks. The sooner this action is taken the safer the work place.
Spraying should then commence from the lower sections moving methodically upwards
to the crown. It may be prudent to increase the accelerator dosage marginally to achieve
a slightly faster set, and applying numerous thinner layers rather than attempting to
spray the entire thickness in one pass of the nozzle. In the crown sections of the tunnel,
a thin layer of approximately 50mm should be sprayed to prevent the completed sprayed
lining from debonding. Subsequent layers may be built up to 150mm in thickness.
For thick structural members, each subsequent layer should be given sufficient time to
set before the next layer is applied. In large diameter tunnels this allows the spraying
process to be continuous. It is good practice to apply thick sections in a series of layers,
but the number should be kept to a minimum where possible. All surfaces to receive a
new layer should be damp and free from loose materials.
One of the principal causes of poor sprayed concrete quality and increase in lining costs
is the amount of rebound produced during spraying. This is particularly evident in the
dry-mix sprayed concrete process where the nozzleman has control over the water-
cement ratio, and is responsible for the effective mixing of the concrete mix between the
nozzle and the substrate. This section highlights some actions to be considered to
reduce rebound and improve quality.
Figure 2 attempts to illustrate some of the major factors that can effect the degree of
rebound produced by both wet and dry-mix sprayed concrete during the spraying
process. In the case of the dry-mix the values given are conservative. Figure 2 assumes
that the mix design, particularly the aggregate grading and water-cement ratio are
optimised as described in Chapter 3. The amount of rebound is broken down into four
major factors:
2
• Nozzle distance to substrate
• Area of application in tunnel
100
Poor
50
Average
Good
10
Excellent
Figure 2: Effect on rebound and sprayed concrete quality of principal spraying parameters
The distance between the nozzle and the substrate should be between 1 and 2m, as
indicated in Figure 4. If the nozzle is closer than this the projected concrete will tend to
tear-off the freshly placed material. If the nozzle distance is reduced, the output should
be lowered and the nozzle moved faster. Furthermore, if the nozzle distance is extended
3
to 3m say, then the energy to compact
the concrete is severely reduced, again
resulting in excessive, rebound poor
compaction and low strengths. Hand held
applications will tend to lower the air
output to maintain the correct nozzle-
substrate distance, this in turn has also
detrimental effects to the quality of the
sprayed concrete.
Further factors that can influence the degree of rebound and hence quality of sprayed
concrete are sumarised as follows:
• Mesh reinforcement
Mesh should be securely fixed to the substrate prior to spraying. Vibrating
mesh can increase rebound values considerably and cause shadows that
reduce the structural capacity of the lining and long-term durability. Where
possible, elect for fibre reinforced mixes for improved productivity, low
rebound, enhanced structural properties, and reduced overall project costs.
• Nature of substrate
In hard rock tunnels, the amount of rebound can significantly higher than in
soft ground tunnels. This is due to the contact surface being both hard and of
4
various incidental angles due to the blocky nature of the rock. In such cases
an initial sprayed concrete layer is advisable to act as a “cushion” to receive
the structural sprayed concrete lining.
Many of the factors that cause high rebound values, poor compaction, loss in structural
performance and hence increased project costs are attributed to the performance of the
nozzleman, particularly that of the hand held nozzle systems using the dry-mix process.
The advent of modern admixtures applied to wet-mix sprayed concrete has reduced
these problems significantly by enabling the mix to be plastic in nature. For some
minutes after application, new sprayed concrete can be absorbed and compact more
readily than very fast, or flash setting materials. This approach reduces rebound
significantly and allows steel encapsulation to be achieved more readily.
Problems relating to nozzle angle, nozzle distance and achieving the correct compaction
with the required air volume and pressure have been facilitated by the use of robotic
spraying manipulators, particularly in large diameter tunnels. As shown in Figure 5, the
MEYCO Robojet spraying manipulator is controlled by a remote-control joystick by the
nozzleman to allow the nozzle to be spraying at the correct distance and angle at all
times. This coupled with the required air volume and pressure ensures low rebound and
well-compacted sprayed concrete. Good surface finishes can be achieved by selecting
the automatic oscillating movement of the nozzle mode.
New advances in spraying robots makes the task of setting the optimal nozzle angle and
distance even easier using the automatic mode with the MEYCO Robojet Logica, as
described in Chapter 7.
Co
rre
ct n
ozz
le d
ista
nce
Figure 5: MEYCO Robojet spraying manipultor - correct angle and distance for reduction in rebound and
enhanced quality
5
Prevailing regulations place added requirements on the people doing the spraying work
to have knowledge of concrete technical issues, particularly with sprayed concrete.
Present requirements have led to a better training of involved personnel. The result of
this is an improved quality of the work. The number of special contractors who are
working with sprayed concrete has increased over the last few years, which has globally
improved the quality of application.
Likewise, the construction team should be made aware of the design elements that are
key factors in determining the safety and durability of the structure. To ensure the quality
of the concrete lining is achieved, quality review systems should be adequate to control
the production. It is of paramount importance that the communication link between
design and construction teams should be maintained from pre-design stage to project
completion so that the above processes are promoted.
Modern sprayed concrete specifications now address the issues of achieving a quality
controlled modern mix design, providing guidance on promoting durability and effective
execution of the spraying processes. As an example, the new European Specification for
Sprayed Concrete (1996) produced by EFNARC, provides comprehensive systems to
attain permanent sprayed concrete. This specification has been the basis for new project
specific specifications worldwide, and is the basis of the new European Norm Sprayed
Concrete Specification. Furthermore, the EFNARC Sprayed Concrete Specification
tackles issues such as nozzleman training and accreditation, and also sets out systems
for contractors and specifiers to consider the structures they are building and to adapt
the sprayed concrete system and mix design accordingly.