Definition: A work center is a machine where activities are performed.


In Work center is used for the following operations

a) Capacity calculation
b) Scheduling of an operations
c) Calculate operation costs

How to create work center?

1) Step 1 – T code CR01


a) Enter plant
b) Enter work center name

If you want to copy another work center details, then maintained work center in copy from and plant

Created by
Sidhant Dhone
SAP PP Consultant
How to Create Work Center

2) Step 2- maintained below details in basic data tab


a) Work center category
b) Person responsible
c) Usage
d) Standard value key

If required auto backflush, then tick on backflush

Created by
Sidhant Dhone
SAP PP Consultant
How to Create Work Center

3) Step 3 - maintained below details in default value tab


a) Control key
b) Unit of measurement of standard values

4) Step 4 – Maintained below details in capacities


a) Capacity category
b) Processing formula

Created by
Sidhant Dhone
SAP PP Consultant
How to Create Work Center

5) Step 5 – Maintain Processing duration in scheduling view

Created by
Sidhant Dhone
SAP PP Consultant
How to Create Work Center

6) Step 6 –
a) Enter controlling area
b) Cost center

How to change work center –

Change work center using t code – COR2

How to display work center –

Display work center using t code- COR3