You are on page 1of 8

Presentation

By
Niaz Construction works

Date- 25-07-2023
1. Borewell Depth
2. Pipe
3. Gravel
4. Bore washing & Water test report
Borewell Size&Depth
After boring machine placement, boring activity started. Protocols followed in all
aspects. All activity performed under continuous supervision of EHS and Site
Supervisor. Bore excavated till 500 fits depth and the borewell size 8 inch.
Pipe
Best quality Pipes (Alpha company D class) used in borewell. Pipes jointed with one another using
glue & screw to avoid DE-attachment and any kind of leaking.Pipe diameter (8 inch).
Gravel
Best quality gravel (from Attock) put outside of pipe in borewell in
10 inch round area for the better filtration of water.
Bore washing & Water test report
After bore completion, Borewell washing activity started till 5 days continuous bore washing.
After that sample of water collected and send it to be Lab for testing.
Water test report is according to the PSQCA Slandard 2010(Drinking Water)
report attached bellow.....

Remarks:-On the basis of test report all the parameters of the provided water sample lie within the permissible
limits of PSQCA Standards.