come
0092-311-4396983
You can also Customize Resource Table Columns
Right Click in resource window ……..>Columns ….>Customize ……> Make Your Choice of Columns
But Keep it as simple as you can see in my window
Resources at Activity Level (Resource Assigning To activities)
Go To activity Details …….> Resources …….>Add Resource …..>Resources Window at Project level
will open ….>Select your require Resources and assign
You can also customize Resources Columns at activity level
Resource Analysis:
As we have limited screen so we can make maximum optimized options of columns to
understand concept.
Now at Activity Level Resources window you can see two Columns
Budgeted Units and Budgeted Unit/Time
Third Component of Equation Duration (Days) you can see in Activity Table
These three factors are interlinked.
When we assign resources at activity level we need to make input of our Budgeted Units of Each
resource and Per Day effort (Budgeted Unit/Time) as well
65 H/Day?
We can hire 6 Roller Each one of them working 11 Hours /Days can give us this effort.
If we Deploy Single Resource think how many days this activity will take to complete this activity?
If 10 Hours each day effort as per single resource deployment we need 26 Days to Complete this activity.
Duration Types:
Fixed Duration
Fixed units
Once You will Select Fixed Duration Your Duration will remain fixed whatever you make changes in
resources window at activity level in Budgeted Unit or Budgeted Unit/Time .
I select Duration Type Fixed Duration
Budgeted Unit/Time also Changed but Duration is still 26 Days as budgeted unit/Time adjusted its value
to consume 1000 Hrs (Total Budgeted Units) in Fixed Duration of 26 Days
If we chose fixed units Duration type now duration will be changed whereas Per day Required Effort will
be fixed
We have 26 Days Budgeted Units 2000 Hours Budgeted unit/time 77hr/Day Effort Approximately
Required
With Fixed Units Duration type at back end how equation will react
I will Change Budgeted Units from 2000 to 3500 Hours
Best Duration Types in EPC industry are Fixed Duration whereas Fixed Units can also be used where
mostly activities are resource Dependent.
By assigning Rates to Each Resource and assigning resources to each activity you will get Cost Break
down Structure
Add Columns
Budgeted Labor Cost, Budgeted Non Labor Cost, and Budgeted Material Cost, Budgeted Total Cost.
You can analyze effectively at what level you have how much cost in which category.
You can save it as layout.