1. Duration Types in Primavera P6 Duration Type is a setting which allows the user to control how the duration, resource units, and resource units/time are
synchronized for activities, so that the following equation is always true: Original, Remaining or Planned Duration = (Budgeted, Remaining or Planned Units) /
(Budgeted, Remaining or Planned Units/Time) If the activity is not started, the names of the values are : Original Duration x Budgeted Units/Time = Budgeted Units
If the activity has started, the names of the values are : Remaining Duration x Remaining Units/Time = Remaining Units The following table lists the value that
changes to balance the equation Duration x Units/Time = Units The following table illustrates how the variables in the above equation changes when you change
one among them in each of the Activity duration types. Duration Type Fixed Units/Time Fixed Duration and Units/Time Fixed Units Fixed Duration and Units When
You Change Duration, what changes? Units Units When you change units/time, what changes? Duration Units When you change units, what changes? Duration
Units/Time When you add a resource, what changes? Duration Units Units/Time Units/Time Duration Units Duration Units/Time Duration Units/Time Table 1.
Activity duration types
2. The duration type is set at the Project Details level for the Project, but can be modified per activity. Your organizations project needs will help to determine which
duration type to use. Well be discussing in the following section as of what situation forces you to choose a particular Duration type. As a hint, if you are adding
resources to activities and you do NOT want P6 to recalculate the existing resources units, duration and units/time, go to Edit, User Preferences from
the Menu bar, select the Calculations tab and select the Preserve the Units, Duration and Units/Time for existing assignments radio button. Example:Now let us
consider a Case and work on it to get a better understanding on the Activity duration types. Given Case :Consider a software company where a resource is
assigned design work of a particular WEBSITE . It is estimated that the design work would be completed within 5 working days of the resource. The particular
resource has a regular shift duration of 8 hours /day. Find what happens to values of the Original duration, budgeted units/time and Budgeted units when i. Original
duration changes to 10 days ii. Budgeted units/time changes to 10hours/day iii. Budgeted units of work changes to 20 hours In each of the activity duration types.
3. Findings: Original Duration =5 days , Budgeted units/time = 8h/d From the formula we know Budgeted units = Original Duration X Budgeted units/time = 8 x 5 = 40
hours Type I :-Fixed Units / Time Units/time for the resources remains fixed; Even when activity duration or budgeted units changes. Used when resources with
productivity output per time period is fixed. Mostly used when Activity type is Resource Dependent. This option is selected if your organization is concerned with
leveling resources and you assign resources specific hours per day on activities. Original Duration = Budgeted Units / Budgeted Units/Time Duration Type When
You Change Duration, When you change units/time, When you change units, what what what changes? changes? Duration Duration changes? Fixed Units/Time
Units Table 1.1.1 Fixes Units / Time
4. Coming back to our case Where Original Duration =5 days ; Budgeted units/time = 8h/d And Budgeted units = 40 hours. i.e. Original Duration = units / (units/time)
5= 40 / 8 We were asked to analyze what would happen if Changes made (i) Original Duration Changes duration (Units )/ (Units/time) from 40 to 20 Budgeted
Original Budgeted Original Budgeted units units/time Duration units Duration units/time 80h => from 8 to 10 Budgeted Original (iii) Units changes from 5 to 10 days
Values changed (ii) Units / time changes 8h/d 4d 40h 2.5d 8h/d 10=> 80/8 4 => 40/10 Table 1.1.2 Fixes Units / Time Workout 2.5 => 20/8
5. Type II: Fixed Duration & Units/Time Activity duration and units / time remains fixed; even if remaining units changes. Mostly used when Activity type is Task
Dependent Activity. Organizations which have the project deadline fixed and is also concerned with leveling resources used this activity duration type.
Organization may consider increasing number of resources to keep the resources leveled. Since this activity is Task dependant and activity duration type is fixed
duration & Units/time there would be no layoff in duration time. Original Duration = Budgeted Units / Budgeted Units/Time Duration Type When You Change
Duration, When you change units/time, When you change units, what what what changes? changes? Units Units/Time changes? Fixed Duration and Units
Units/Time Table 1.2.1 Fixed Duration & Units/Time
6. Given Original Duration =5 days ; Budgeted units/time = 8h/d And Budgeted units = 40 hours. Changes made (i) Original Duration Changes duration (Units )/
(Units/time) from 40 to 20 Budgeted Original Budgeted Original Budgeted units units/time Duration units Duration units/time 80h => 8 to 10 Budgeted Original (iii)
Units changes from 5 to 10 days Values changed (ii) Units / time changes from 8h/d 5d 50h 5d 4h/d 10=> 80/8 5 => 50/10 Table 1.2.2 Fixed Duration & Units/Time
Workout 5 => 20/4*
7. Type III :-Fixed Units This duration type is chosen if you want the activity units to be fixed even when duration or resource units per time changes. Total amount of
Work is fixed. Used when Activity type is Resource Dependent Activities. Unlike previous Duration types increasing resources decreases the activity duration.
Generally used when you have resource under contract basis and you have X units of work to get to be done from that particular resource. Original Duration =
Budgeted Units / Budgeted Units/Time Duration Type When You Change Duration, When you change units/time, When you change units, what what what
changes? changes? Duration Duration changes? Fixed Units Units/Time Table 1.3.1 Fixed Units
8. Given Original Duration =5 days ; Budgeted units/time = 8h/d And Budgeted units = 40 hours. Changes made (i) Original Duration Changes duration (Units )/
(Units/time) from 40 to 20 Budgeted Original Budgeted Original Budgeted units units/time Duration units Duration units/time 40h => 8 to 10 Budgeted Original (iii)
Units changes from 5 to 10 days Values changed (ii) Units / time changes from 4h/d 4d 40h 2.5d 8h/d 10=> 40/4 4 => 40/4 2.5 => 20/8 Table 1.3.2 Fixed Units
Workout Type IV :-Fixed Duration & Units Activity duration and Units to remain constant even when the units/time changes. Mostly used when time period and the
total amount of work are fixed. Used when Activity type is Task Dependent Activities. Rate at which a resource can work on the activity can be changed. You could
use this if your organization is more concerned about coming in on the schedule date and within the costs (which are usually associated with the units) Original
Duration = Budgeted Units / Budgeted Units/Time
9. Duration Type When You Change Duration, When you change units/time, When you change units, what what what changes? changes? Units Units/Time
changes? Fixed Duration and Units Units/Time Table 1.4.1 Fixed Duration & Units Given Original Duration =5 days ; Budgeted units/time = 8h/d And Budgeted
units = 40 hours. Changes made (i) Original Duration Changes duration (Units )/ (Units/time) from 40 to 20 Budgeted Original Budgeted Original Budgeted units
units/time Duration units Duration units/time 40h => 8 to 10 Budgeted Original (iii) Units changes from 5 to 10 days Values changed (ii) Units / time changes from
4h/d 5 50 5d 4h/d 10=> 40/4 5 => 50/5* Table 1.4.2 Fixed Duration & Units Workout 5 => 20/4
10. Summary Given Original Duration 5days; Budgeted Units 40hours; Budgeted Units/ time 8hours/day. The following table summarizes as of what happens to the
variables in each of the activity duration types. Units / time changes from 8 to 10 Units changes from 40 to 20 Budgeted units Budgeted Original Duration
Budgeted units Original Duration Budgeted (Or. Val:- 40h) Type Duration Original Duration Changes from 5 to 10 units/time(Or. Val:- (Or. Val:- 5d) (Or. Val:- 40h)
(Or. Val:- 5d) units/time 8h/d) Fixed Units / Time (Or. Val:- 8h/d) 80h 8h/d 4d 40h 2.5d 8h/d 80h 8h/d 5d 50h 5d 4h/d* Fixed Units 40h 4h/d 4d 40h 2.5d 8h/d Fixed
Duration & Units 40h 4h/d 5d 50h* 5d 4h/d Fixed Duration & Units/Time Table 2: Activity duration table chart Or.Val - Original Value * - in certain cases original
duration remains fixed and the other fixed variable is forced to changed. Reference:https://ccsspl123-
public.sharepoint.com/Support%20Documents/duration%20types-Activity.pd