Professional Documents
Culture Documents
using
Microsoft Project
(August 02 - 04, 2022)
Yalam Vaidya
M. Engg., PMP
1
Monitoring Tools : Tracking Data,
Entering Actuals
Using Microsoft Project
(Day 2)
Monitoring a Project
Record the Actual Start Date, Actual Finish Date, Actual Work,
and Actual and Remaining Duration for each Task or Assignment.
Another way to indicate that just certain Tasks (not Entire Plan)
have been completed as scheduled is to use the MARK ON TRACK
command (TASK Tab, SCHEDULE Group).
This command applies only to the selected Tasks, and it sets them
as complete through till the Status Date (if you set a Status Date on
the PROJECT Tab, STATUS Group, STATUS DATE Command).
Or if you have not set a Status Date, the command applies through
the Current Date.
Entering ACTUALS – Task’s Completion Percentages
After work begins on a task, you can quickly record its progress as
a percentage.
Use the 0%, 25%, 50%, 75%, and 100% Complete Buttons in the
SCHEDULE Group of the TASK Tab, OR
Enter any Percentage value you want in the UPDATE TASKS Dialog
Box. (To Access this Dialog Box, on the TASK Tab, in the SCHEDULE
Group, Click the Down Arrow to the Right of MARK ON TRACK, and
then Click UPDATE TASKS), OR
You can record each task’s actual Start, Finish, Work, and
Duration values.
Option 2:
On TASK Tab, in SCHEDULE Group, Click Down Arrow to right of
MARK ON TRACK Button, and then Click UPDATE TASKS.
Tracking Actual/Remaining Values for Tasks/Assignments
For tasks that have resources assigned to them, you can enter actual
and remaining work values for the task as a whole or for specific
assignments to that task.
To help you understand how MS-Project handles the actual values
you enter, consider the following:
If a task has a single resource assigned to it, the actual work values you
enter for the task or assignment apply equally to both the task and the
resource.
If a task has multiple resources assigned to it, the actual work values you
enter for the task are distributed among or rolled down to the
assignments according to their assignment units.
If a task has multiple resources assigned to it, the actual work values you
enter for one assignment are rolled up to the task. However, the new
actual work values do not affect the other assignments’ work values on
the task.
Tracking Actual/Remaining Values for Tasks/Assignments
On the VIEW Tab, in the TASK VIEWS Group, Click TASK USAGE.
On the VIEW Tab, in the DATA Group, Click TABLES and then Click
WORK. The Work table appears.
On the FORMAT Tab, in the DETAILS Group, Click ACTUAL WORK.
For each Task and Assignment, Project now displays the Work and Actual
Work rows on the Time-Phased Grid on the Right Side of the View.
In the Time-Phased Grid, you see the Scheduled Work values per Day.
If you add up the Daily Work values for a Specific Task or Assignment, the
total equals the value in the Work Column for that Task or Assignment
Next, you’ll Enter Task-level and Assignment-level Actual Work values and
see how they are reflected in the Time-Phased details.
In either View, you can enter Actual Work values for individual
Assignments daily, weekly, or at whatever time period you want (by
adjusting the Timescale).
For example, if a task has three resources assigned to it and you know
that two resources worked on the task for eight hours one day and the
third resource worked for six hours, you can enter these as three
separate values on a Time-Phased Grid.
Entering Actual Costs Manually
Whenever you’ve entered actual work values, MS-Project has
calculated actual cost values for the affected task, its summary
task, the resources assigned to the task, and the entire project.
By default, MS-Project calculates actual costs and does not allow
you to enter them directly.
However, if you want to enter actual cost values yourself in your
own plans, follow these steps.
On the FILE Tab, Click OPTIONS.
The Project Options dialog box appears.
Click SCHEDULE Tab, Under CALCULATION OPTIONS FOR THIS
PROJECT label, clear ACTUAL COSTS ARE ALWAYS CALCULATED
BY PROJECT Check Box.