Create and Present a Graphical Monitoring Status Report for Building

Construction Example Project with the following tracking data:

a. The Project is monitored at the halfway mark.

b. EXCAVATION took 3 days to complete.

c. LEVELLING finished on planned time but the actual cost of the task escalated
by 10%.

d. ANTI-TERMITE finished on August 10, and the material cost increased by 20%.

e. INSPECTION took 3 days to complete.

f. FOUNDATION took 6 days to complete but the material cost increased by 10%.

g. GROUND SLAB was only 25% complete.

h. ROUGH PLUMBING was only 75% complete by that time.