2.5
7 Days
Instruction in Writing
6.3 Within a
Disruption of Progress Reasonable Time
8.1
Contractor’s General Immediately
responsibilities (for errors or
defects in design)
12.2
Not Foreseeable
Immediately
Physical Obstructions
or Conditions
25.1
Evidence and Terms 84 Days
of Insurances
27.1
Immediately
Fossils
30.3
Transport of Materials Immediately
or Plant
38.1
Within a
Examination of Work
Reasonable Time
before Covering up
40.3
Suspension lasting 28 Days
more than 84 Days
42.1
Within a
Possesion of Site Reasonable Time
Access Thereto
44.2
a. 28 Days
Contractor to Provide
Notification and Detailed
b. 28 Days
Particulars
44.3
Interim Determination 28 Days
of Extension
48.1
Taking - Over Immediately
Certificates
Page 1 of 2
STIPULATED TIME FRAME FOR NOTICE TO BE SERVED
48.2
Taking Over of Immediately
Sections or Parts
52.2
Power of Engineer to 14 Days
Fix Rates
53.1
28 Days
Notice of Claims
53.3 28 Days by
Substantion of Claims Practice
63.1
Default of Contractor
Not relevant as a site instrument
65.5
Increased Costs arising Immediately
from Special Risks
67
Arbitration
Not relevant as a site instrument
69.4
28 Days from the
Contractor's Entitlement 69.1 Notice
to Suspend Work
Page 2 of 2