Professional Documents
Culture Documents
Lacture Note ND2
Lacture Note ND2
(CEC 214)
Prepared By:
Ahmad Abubakar
1
ENGINEERING MEASUREMENT AND EVALUATION
CHAPTER 1: PROJECT
INTRODUCTION
A project is an endeavor that is undertaken to deliver a product, service or result.
Project contract
A project contact is a legal agreement between two parties that will be working on
a project that outline the obligation, duties, and expectation of both parties. It is
imperative to have a project contract in place when starting any new work with an
outside company.
Construction project
The organization effort to create a building or structure is known as a construction
project. Construction project in civil engineering and architecture refer to
physically putting together infrastructure or a building.
2
ENGINEERING MEASUREMENT AND EVALUATION
2. Private project
3. Commercial project
4. Industrial project
Residential housing project are usually designed by the engineers and architect,
with the mechanical, structure and electrical work completed by subcontractor
hired by construction companies. in the case of single _family homes, however,
builder often handle all parts of the project, including design and construction.
2. Private project
3. Commercial project
3
ENGINEERING MEASUREMENT AND EVALUATION
4. Industrial project
For examples chemical company can build oil refineries, whereas a power
generation company can build hydroelectric power plant and nuclear power plants,
both are industrial structure.
State funded a construction project come in a range of shape and sizes. it could
be something as a simple as constructing a public school or a government building
(like a courtroom). these projects can also be quite complex, such as building a
bridge, sewer line, motorways. While federal construction project is very similar
with federal they can take several shapes, much like state project, and are very
simple, conventional and complicated. The distinction is not in which organization
funds the project as federal money is used in state project if construction on a state
courtroom is done with federal funds.
4
ENGINEERING MEASUREMENT AND EVALUATION
2. Architect
3. Quantity surveyor
4. Structure engineer
5. Builder
6. Artisans
1. Client
The client is the building owner for whom the project is carried out. He or she
provide the money which is used for the purchase of building materials, works
payment,etc. Clients express their ideas to architects.
2. Architect
3. Quantity surveyor
Quantity surveyor manage all cost associated with building project. They check the
building plan and materials specified and prepare an estimate for the construction
project.
4. Structure engineer
5
ENGINEERING MEASUREMENT AND EVALUATION
Structure engineer determine the load to be carried by the building and prepare
drawing of structure to ensure they are strong enough to avoid collapse when
loaded. Structure can include building, bridge etc.
5. Builder
6. Artisans
These are the real workmen on site, they are mostly technicians and they
included bricklayers, carpenters, electricians, iron fixers, plumbers, etc.
PROJECT PARTIES/STAKEHOLDERS
Owner/employer
Consultant/Engineer
Contractor
Other parties
1. OWNER/EMPLOYER
Defining the needs and criteria of the project (e.g Construction of a House)
Defining any special requirement of the project (e.g Nominated
Subcontractor).
6
ENGINEERING MEASUREMENT AND EVALUATION
-Owner can choose to contract the project to one prime contractor or several
work package contractors.
7
ENGINEERING MEASUREMENT AND EVALUATION
B. GOVERNMENT
Provide regulations and a legal, political and economic environment for
the project.
C. SUPPLIERS
Provide specific material or equipment.
PROJECT PHASES
a. Idea (feasibility study) – study technical report, finance, cash flow and
so on. (By owner)
b. Design (By consultant/engineer)
c. Tender (project) documents
Invitation to bid
Bid form (information and constraints)
Drawings and specifications
Bill of quantities (B.O.Q) and so on
d. Construction (By contractor)
e. Closing of the project
8
ENGINEERING MEASUREMENT AND EVALUATION
2.1 INTRODUCTION
The term Bills of Quantities (BOQ) is defined in the SMM as a list of items
giving brief identifying descriptions and estimated quantities of the works to be
performed. The BOQ forms a part of the contract documents, and is the basis of
payment to the Contractor.
2.1.1 OBJECTIVES
Preliminaries
Preambles
Prime Cost sums and Provisional sums
Measured items
Provisional Quantities
2.2.1 PRELIMINARIES
9
ENGINEERING MEASUREMENT AND EVALUATION
2.2.2 PREAMBLES
Preambles for each work section are grouped together and inserted either
at the beginning of that particular work section or combined with preambles for
other work sections and inserted after the preliminaries bill, but before the “bill
proper”.
Example:
All cement used in the works shall be ordinary Portland cement complying
with BS 12
Aggregate shall be obtained from an approved source and shall comply
with BS 882
The contractor shall make allowances in his rates for sampling of
aggregates.
10
ENGINEERING MEASUREMENT AND EVALUATION
Provisional Sum
The measured items make up what is known as the “Bill Proper”. These are
items taken-off from drawings which have been squared and sorted. In the bill,
each measured item will comprise:
A reference symbol
A prose description
An associated quantity
11
ENGINEERING MEASUREMENT AND EVALUATION
General rule provides for the inclusion in the BOQ of work which for some
reason or other cannot be measured accurately at pre contract stage. Unlike
provisional sums (for work which cannot be measured) provisional quantities are
for the quantity of work that cannot be accurately determined.
12
ENGINEERING MEASUREMENT AND EVALUATION
ADVANTAGES OF BOQ
DISADVANTAGES OF BOQ
The Project cost may exceed the estimated cost if there were errors in
quantities mentioned in the BOQ
The final billed quantities may exceed the specified quantities (in the lump
sum contract the variation in cost is borne by the Contractor).
13
ENGINEERING MEASUREMENT AND EVALUATION
Take off
Squaring
Abstracting
Billing
Taking off is the procedure by which dimensions of the works are calculated
or scaled off from the drawings and entered onto dimension papers or other
similar computerized formats.
Figure 3.1
Column A is the ‘time sing’ and ‘dotting on’ column where multiplication
and addition of the dimensions can be recorded (Figure 3.2).The practice of
‘dotting-on’ should be used only where absolutely necessary because of the
dangers of mistaking the dot for a decimal point.
14
ENGINEERING MEASUREMENT AND EVALUATION
Figure 3.2
Figure 3.3
15
ENGINEERING MEASUREMENT AND EVALUATION
aa
Figure 3.4
Ample space should be left between all items on the dimension sheets so
that it is possible to follow the dimensions with ease and to enable any items,
which may have been omitted when the dimensions were first taken off, to be
inserted subsequently.
16
ENGINEERING MEASUREMENT AND EVALUATION
Figure 3.5
Each dimension sheet should be headed with the contract number, and the
abbreviated contract title, section of the job and the drawing number(s) to which
the taking-off sheet referred at the head of each sheet. Each sheet should be
numbered consecutively at the bottom.
17
ENGINEERING MEASUREMENT AND EVALUATION
At the top of the first dimension sheet for each main section of works the
list of drawings from which the measurement is taken should be entered.
Revisions to the drawing used should be precisely stated so that in the event of
any change being made to work as originally planned it can be clearly seen what
was measured in the BOQ.
Figure 3.6
18
ENGINEERING MEASUREMENT AND EVALUATION
3.1.3MENSURATION
3.2 SQUARING
19
ENGINEERING MEASUREMENT AND EVALUATION
column on the dimension paper. Squaring should be carried out to two decimal
places, with the final squared quantities rounded off.
3.3 ABSTRACTING
Entries in the abstract should be well spaced. The items should be entered
in the same order as they will appear in the bill, since the primary function of the
abstracting is to classify and group the various items preparatory to billing, and to
reduce the dimensions to the recognized unit of measurement.
20
ENGINEERING MEASUREMENT AND EVALUATION
It is usual to adopt the order of cubic, square, linear and finally enumerated
items, with smaller items preceding larger ones, and cheaper items preceding
more expensive ones in each group.
3.4 BILLING
Billing is the final stage in the bill preparation process in which the items
and their associated quantities are transferred from the abstract onto the
standard billing sheets or other similar computerized formats that are in a format
that enables the tendered to price each item and arrive at a total tender sum.
21
ENGINEERING MEASUREMENT AND EVALUATION
(a) The taking-off is carried out to the same procedures as described in traditional
method, but the dimensions are entered on special `cut and shuffle' paper. Each
sheet comprises a white original and a yellow carbon copy, and is ruled in such a
manner that it forms three separate small dimension sheets, which are commonly
referred to as `slips'. Each `slip' should be numbered, and have the job number
stamped on the top. Taking-off then proceeds in the usual manner, except that a
separate `slip' must be used for each individual item. An example of a `cut and
shuffle' page fully completed is shown in Figure 4.1
(b) When the taking-off is completed, or in the case of a large job, substantial
sections are completed, the dimensions on each `slip' are squared and checked.
(c) The person who carries out the taking off retains the yellow carbon copy as a
record, but the white original sheets are cut into three separate `slips', each
containing one item or part of an item.
(d) The `slips' are shuffled, or sorted, into sections, such as Earthworks, Drainage,
Concrete, etc., similar items are collected and stapled together, and the whole of
the slips placed, as near as possible, in bill order.
(e) The slips are then edited to form the preliminary draft bill, with further slips
inserted as necessary to provide headings. The correct unit is entered in the box
provided on each slip, or on the top slip where a number of similar items are
stapled together.
(f) The total quantity for each item is calculated and inserted in the box provided
on the slip. This process must be independently checked and ticked in red ink or
ball pen.
(g) Once completed, these slips are attached together in bill order by a treasury
tag from the draft bill, and can be passed directly for typing onto billing paper.
(h) The typed bill must be closely checked with the draft to ensure that all
descriptions, quantities and units have been transferred correctly.
22
ENGINEERING MEASUREMENT AND EVALUATION
(i) As a final check, the cut slips should be counted and compared to the yellow
carbon copy sheet to ensure that all slips are accounted for.
Although this system takes a longer time during the taking-off stage owing
to the need to write descriptions out in full, the time saved in the bill preparation
process means a considerable reduction in overall time spent on pre-contract
measurement.
Used correctly, it can result in great savings in time in the bill preparation
process, as it omits both the abstracting and billing stages.
2. Direct Billing
This method should be adopted where the number of similar items is not
too extensive, and the job is not too complex in character.
3. Computer Billing
Computer aided bill production systems provide the facility to check
accuracy, but care is needed in the coding of dimensions and entry of data.
Modern computerized billing systems can however, print out errors in the form of
tables. The coding can be double checked, although a random check may be
considered adequate.
23
ENGINEERING MEASUREMENT AND EVALUATION
Figure 4.1
24
ENGINEERING MEASUREMENT AND EVALUATION
CHAPTER 5: SPECIFICATION
5.1 INTRODUCTION
Specifications are detailed descriptions prepared by a consulting engineer
or architect to tell the contractor everything about the quality of material and
workmanship required which cannot be shown on the drawing.
25
ENGINEERING MEASUREMENT AND EVALUATION
ILLUSTRATION
Cement:
Cement for use in the works shall be obtained from an approved
manufacturer and shall conform in all respects to BS12 for Portland cement. For
the purpose of BS12, the site shall be decried to have a tropical climate.
26
ENGINEERING MEASUREMENT AND EVALUATION
Workmanship Clauses
These are generally drafted in the imperative e.g. ‘lay manhole bases in
concrete’ or alternatively ‘The contractor shall lay etc’.
Workmanship example
Block work
“Blocks shall be laid in stretcher bond with 10mm joints properly bedded in
cement mortar and with joints flushed up as the work proceeds”.
5.4 Sources of information
(1) Previous Specification
Specifications for past jobs are used as a basis in the preparation of a
new specification for a job of similar type. Care must be taken however to
update the clauses by incorporating recent development and techniques’,
and to allow for differences of design, construction or site conditions of the
current job. Also to omit details which are not applicable?
(2) Contract Drawings
These show the character and extent to the works. And the
specification writer will work systematically through the drawings to extract
information when compiling the specification.
27
ENGINEERING MEASUREMENT AND EVALUATION
28
ENGINEERING MEASUREMENT AND EVALUATION
Surface Soil: Surface soil shall be stripped and deposited in temporary storage
heaps, preparatory to being used for the preparation of beds to receive trees and
shrubs.
Excavation: The excavation shall be carried out to the dimensions, levels, lines
and profiles indicated on the contract Drawings or to such dimensions as may be
directed in writing by the supervising officer.
The excavations are to be performed in whatever material may be found,
but extra payment will be made for excavation in rock. Rock is defined as material
which in the opinion of the Architect/supervising officer can be removed only by
the use of compressed – air plant, wedges or explosives and is found in
continuous beds exceeding 75mm in thickness or in isolated stones exceeding
0.06m3 in volume.
The contractor shall include for getting out the excavated material by hand
or machine and for leveling and compacting surfaces prior to commencing
constructional work.
The faces and beds of all excavations after being excavated to the required
dimensions shall be carefully trimmed to required profiles and cleaned of all loose
mud, dirt or other debris.
Trench excavation shall be assumed to be not exceeding 1.50m deep.
Disposal of Surplus Excavated Material:
All surplus excavated material is to be deposited, spread and leveled where
directed or removed from site as required, the contractor being responsible for
finding a deposit and paying all fees and charges which may be demanded.
Backfilling of Trenches:
Filling around foundations in trenches is to be of selected earth obtained
from the excavating free from roots and all vegetable matter and it is to be filled
in layers not exceeding 225mm in thickness each layer well rammed and
consolidated by rolling or ramming and well-watered.
Filling:
Approved filling to make up levels shall be in soft laterite or other such
materials approved by the Architect/supervising officer and shall be deposited in
layers not exceeding 300mm thick and well-watered and consolidated. If material
obtained from excavation is approved for use in filling.
29
ENGINEERING MEASUREMENT AND EVALUATION
CONCRETE WORK
Generally:
All materials used in the concrete work, and the mixing, placing and curing
of the concrete and the workmanship generally are to comply with the latest
British Standard and code of practice applicable.
Concrete Materials
Cement:
Cement for use in the works shall be obtained from an approved
manufacturer and shall conform in all respects to B.S. 12 for Portland cement. For
the purpose of B.S.12, the site shall be deemed to have a tropical climate.
The cement shall be delivered to the site in approved sealed bags or
containers which are to be clearly marked with the name of the manufacturer.
Cement is to be stored in a water–proof shed having a timber floor raised
above the ground. Each consignment of cement shall be stacked separately and
marked so as to be easily identifiable, and shall be used in order of delivery. Any
cement rejected by the Architect or Engineer shall be immediately removed from
the site and if requested, all other cement from the same consignment shall also
be removed.
Aggregate:
Fine aggregate shall be well washed and shall be sharp and free from clay,
chalk, organic matter and other impurities. It shall comply with the requirements
of B.S. 882 and shall be graded in accordance with Table 2, zone 2.
Coarse aggregate shall be gravel or other suitable material and shall be well
washed and free from sand, clay, quarry refuse and other impurities. It shall
comply with the requirements of B.S. 882 and shall be graded in accordance with
Table 1.
Aggregates generally shall be stored in proper stockpiles and in such a
manner that they do not mix with the underlying soil or come into contact with
impurities, or mix with each other.
All aggregates shall be clean and free from chemical organic and
mineralogical Constituents which react unfavorably with cement, reduce the
strength and durability of the concrete or attack the steel reinforcement.
30
ENGINEERING MEASUREMENT AND EVALUATION
Water
Water shall be clean, pure and free from impurities in suspension or
solution.
Workmanship
Proportions of Concrete:
Concrete in foundation trenches shall be 1:3:6 mix concrete in bed, beams
and lintels shall be1:2:4 mix. These indicate the volumetric proportions of
cement, fine aggregate and coarse aggregate respectively.
Unless otherwise stated the coarse aggregate for concrete shall be 38mm
for 1:3:6 mix and19mm for 1:2:4 mix.
Concrete for reinforced work generally shall comply with the requirement
of British Code of Practice CP114; Structural Use of Reinforced Concrete in
Buildings.
Mixing of Concrete:
Concrete for reinforced concrete must be mechanically mixed. Mixing shall
be done in an approved mechanical batch mixer. The volume of materials
inserted per batch shall not exceed the manufacturer’s rated capacity and the
volume of each batch shall be such that only whole bags of cement will be used.
The mixer drum shall be emptied completely before being refilled. All
materials shall be mixed until the concrete is uniform in color and consistency and
in no case shall it take less than two minutes.
Where hand mixing is approved for other qualities of concrete, the
ingredients shall be mixed dry on a watertight platform until a uniform color is
obtained. Clean water shall then bead gradually through a rose head and the
whole mass turned over at least three times in awet state until it attains a slightly
wet consistency.
Water must not be added later to facilitate handling or other purposes.
Testing Concrete:
Price of concrete shall include for carrying out all tests in accordance with
the requirement of B.S. code of practice 114 as and when required by the
Architect or supervising officer including supplying all test cubes, slump cones etc
and paying all fees and charges incurred. The minimum crushing strengths on
150mm test cubes of ordinary Portland cement shall be:
31
ENGINEERING MEASUREMENT AND EVALUATION
Placing Concrete:
Concrete shall be used as soon as it has been mixed and shall be conveyed
in and deposited directly in the work from proper metal concreting barrows. Care
must be taken to prevent workmen placing concrete from introducing clay or
other harmful matter on their boots. Before any concrete is placed in position, the
formwork and other adjoining surfaces shall be clean and free from all foreign
matter.
In placing concrete, it shall not be dropped into its final position from a
height of more than900mm nor shall it be deposited in water.
Only sufficient concrete shall be prepared as is required for immediate use
and concrete shall be placed within 30 minutes of being mixed and once placed
and consolidated shall not be disturbed. The use of “revived” concrete is
prohibited.
The concrete shall be thoroughly worked in to all parts of the formwork and
between and around steel reinforcement, and compacted by approved methods
to give a dense and compact concrete free from honeycombs or voids of any kind.
Great care should be taken to prevent the displacement or deformation of
the steel reinforcement during concreting.
Reinforced concrete shall be vibrated by use of an approved mechanical
poker vibrator.
Protection
Curing of concrete shall be in accordance with the recommendations set
out in the B.S. Code of practice and all surfaces shall be kept continually wet after
concreting and protected from the sun and drying winds by covering with wet
sacking for not less than one week.
Concrete floors shall be protected from damage by traffic by covering with
sand or timber strips or other approved means.
Concrete is not to have weight put on it for one week after laying. During
periods of heavy rainfall, surfaces of concrete just deposited are to be
satisfactorily protected by sacking, felt,etc.
32
ENGINEERING MEASUREMENT AND EVALUATION
Bar reinforcement in beams and lintels shall be mild steel bars complying
with B.S. 4449.
Mesh reinforcement in ground floor slab shall comply with B.S. 1221. All
mesh shall be delivered in flat sheets.
All reinforcement shall immediately prior to placing, be free from loose
mile scale, loose rust, oil, grease, dirt or other foreign matter.
Placing Reinforcement:
All reinforcement shall be set out exactly as shown on the working
drawings and is to be securely wired with and including soft pliable mild steel wire
of approved gauge at all intersections and adequately supported in such a
manner that no movement takes place before concrete has set.
Cover to Reinforcement:
The minimum concrete cover to reinforcement shall be as follows:
Bar reinforcement: The diameter of the bar or 20mm in beams and lintels
whichever is the greater.
Mesh reinforcement in ground floor slab – 40mm
All bars are to be bent cold on the site in a suitable and approved bar
bending machine and accurately shaped to the shapes and profiles
indicated in the drawings.
Prices for bar reinforcement should include for the following:
· Cutting of any description, notching, bending tying wires and distance
blocks.
· The extra malarial at laps
· Protection
Formwork:
All formwork shall be true to line and of suitable thickness and sufficiently
strutted and braced to be free from deflection under the load of concrete
to be placed on it.
The joint shall be so tight as to prevent leakages of liquid cement.
Formwork shall be so erected that in striking, the sides of beams may be
exposed first and independently and the undersides of beams last. After
removal of formwork the faces of the exposed concrete shall be rubbed
down immediately to remove fins or other irregularities.
33