Professional Documents
Culture Documents
Questions Answers
7.1, page 137 a) -1%, b) total return=-5% + 4%
7.2 Rate of return =9%, b) find breakup on your own
7.3 $66 expected current price
7.4 $150
7.5 $20 and $25
7.6 Expected Dividend at the end of the 1 st year $2.1 and Current Price $ 30
7.7 $52 expected current price
7.8, page 138 $ 9.84
7.9 Requires rate of return on stock = 14% and expected current price 13.25
7.10 $23.72
7.11 $5.4825
7.12 $22.54
7.13 Current price $10.35
7.14 Current price $ 17.39
7.15 Current price $31.38
7.16 Current price $ 15.17
7.17 $70.30
7.18 $120
7.19 -5,000
7.20 $1.3 million
9-1 $160,926.88
9-2 a.) 292,130.06 b.) 317,099.27
9-3 NPV=$ -66,460.79 and IRR= 10.56% as per NPV we cannot undertake this project
and NPV is in negative. Also, as per IRR we must not undertake the project
because IRR in not greater than required rate of return i.e., 11%
9-4 Investment is acceptable according to NPV and IRR techniques. Find your own
number as by this time you should be confident in finding right NPV and IRR
values. If not then do previous questions and compare your answers first with
them.
9-5 IRR=12.99%
9-6 IRR=9.01% (similar to 9-5 Question)
9-7 a.) 756.62, b.) 14.49% c.) answer yourself whether project is acceptable or
not.
9-8 Similar to 9-7 so do yourself.
9-9 Find NPV at different discount rates
yourself and plot the NPV profile in excel.
9-10 MIRR= 11%, investment is not acceptable as MIRR<r =12%
9-11 MIRR=10.19%
9-12 MIRR=11.98%
9-13 PB= 3.6 years and DPB= 4.84 years if you have used the discount rate of 11%
otherwise it is 4.69 years if you use the discount rate of 10%. I have mistakenly
used the rate of 10% while attempting this question but advise you to use the
rate (11%) as mentioned in the question.
9-14 PB= 4 years and DPB=5.78 years
9-15 NPV= 2,139.17, IRR= 13.48% and MIRR=13.33%
9-16 a.) NPV =8,595.84, b.) IRR=15.89%, c.) DBP= 2.89 years for Aplha project.
For Beta project:
a.) NPV= 13,051.79, b.) IRR= 15.53%, and c.) 2.97 years
9-17 Project AB
a.) NPV=2,084.95, b.) IRR=14.36%, c.) MIRR=13.87%, and d.) 2.92 years
Find yourself for the LM and UV projects.
9-18 NPV s=527.94 , NPV T =546.97 and IRR= 18.22%
9-19 Do it yourself.
Answers to the practice/ core questions-Combined
9-20 Critically think about it and discuss it on discussion forum if such forum is
available.
Topic Project Cash Flows and Risk