Professional Documents
Culture Documents
THIS IS TO CERTIFY, that on instructions from Messrs. “SSET”, we attended on the 3rd
of February 2022 onboard the steel, single screw, LPG Tanker vessel:
“SUMMER”
(IMO No.: 9040883)
of the port of Port Vila, Vanuatu flag, 4822 gross register tons, whilst she was lying afloat at
Piraeus anchorage, Greece, for the purpose of carrying out a
PRE-PURCHASE INSPECTION
TABLE OF CONTENTS
1.0 INTRODUCTION / SURVEY CIRCUMSTANCES………………………………………………………………. p.3
2.0 HULL & MACHINERY PARTICULARS ……………………………………………………………………………. p.4
3.0 CERTIFICATES & SURVEY STATUS ………………………………………………………………………………. p.7
4.0 INSPECTION NARRATIVE …………………………………………………………………………………………… p.11
5.0 VESSEL PERFORMANCE AND CONSUMPTIONS ………………………………………………………….. p.19
6.0 GENERAL REMARKS ………………………………………………………………………………………………….. p.20
7.0 ATTACHMENTS …………………………………………………………………………………………………………. p.20
Page 2 of 20
XXII – 01012
“SUMMER”
1.1 The undersigned surveyors, on instructions received on 22nd of January 2022 from Messrs.
SSET, attended onboard subject vessel on the 3rd February 2022 whilst she lay
anchored, in fully ballast condition, at Piraeus anchorage, Greece for the purpose of carrying
out a superficial inspection pre-purchase inspection of Messrs. GATOR SHIPPING ALPHA INC.
1.4 Cargo tanks were not gas free and could not be examined in this instance.
1.5 Ballast tanks, being full with water for stability purposes, were not made available for
internal examination.
1.6 The inspection was carried out without making removals to expose parts concealed at the
time of our attendance and/or carrying out close-up survey/operational tests, except as
noted within the main body of this report.
1.7 Age and trade of the vessel were taken into consideration for the purpose of this report.
Normal wear and tear excluded unless otherwise stated.
Page 3 of 20
XXII – 01012
“SUMMER”
2.1. General
Page 4 of 20
XXII – 01012
“SUMMER”
The “SUMMER” (the Vessel) is a double bottom hull, LPG Type IIG Tanker, of all welded steel
construction, with raised forecastle deck, with bulbous bow and transom stern.
She was built in 1993 at Pattje Shipyards, Holland, in compliance with Rules and Regulations
of Germanischer Lloyd.
The Vessel is arranged with four (4) cylindrical (type C) cargo tanks, which are located below
the weather deck, installed in cargo hold spaces (two tanks per cargo hold). Each tank is
supported by two bearings (fixed and sliding bearings). Anti-floating devices are also provided
in order to keep the tanks down on their foundations in case of cargo hold flooding.
The cargo tanks, which are provided with cryogenical insulation of polystyrene slabs of 145mm
thickness glued/attached to the tanks’ surfaces, are connected to cross over systems including
booster pump (SVANEHOJ 260 m3/hr capacity) and reliquefication units.
Page 5 of 20
XXII – 01012
“SUMMER”
Reliquefaction System
The vessel is arranged with two(2) identical reliquefaction systems, each provided with one
cargo condenser/evaporator, suction separator and intermediate flash drum (economizer).
Three(3) SULZER type 2K 120-2A cargo compressors, each of 665 m3/hr capacity, are provided
- one(1) compressor for each individual reliquefaction system and a spare compressor which
can be connected to or replace either cargo compressor.
Vent System
There are nine (9) independent venting stacks with vent head:
- One(1) for each cargo tank
- One(1) for each purge collector
- Two(2) for the reliquefaction system
- One(1) for the heat exchangers
One (1) NMF type PK5013 x 5 MT SWL (outreach 3-12m) electro-hydraulic hose handling deck
crane.
The thirteen (13) ballast tanks comprise of the Forepeak and Afterpeak tanks, one double
bottom center tank (No.2) and five (5) pairs of double bottom tanks (Nos. 3-7 port &
starboard).
Crew complement consists of a total of 15 persons, in excess of the Minimum Safe Manning
Certificate requirements of 11 crew.
Propulsion power is provided by one MAK, type 9M453C, 4-stroke, turbocharged, medium
speed, nine (9) cylinders in-line, 320/420 mm bore/stroke, trunk piston type, diesel engine,
Page 6 of 20
XXII – 01012
“SUMMER”
developing 3300 kW at 600 rpm, running on HFO & MGO, driving a 4-bladed CPP propeller
(LIPS type HPP-46) through a reduction gearbox (LOHMANN & STOLTERFOHT, type GWK710P).
- Two (2) x 894 kVA/715 KW, 440 V AC, 60 Hz, CATERPILLAR type SR-4 self-excited AC
generators, each driven by a CATERPILLAR type 3508 DITA turbocharged diesel engine at
1800 rpm.
- One (1) x 1200 KW, 440 V AC, INDAR type LCB500S shaft generator
- One (1) x 81 kVA/65 KW , 440 V AC, 60 Hz CATERPILLAR type SR-4 self-excited AC generator
driven by a CATERPILLAR type 3304 B diesel engine at 1800 rpm (emergency genset).
The two(2) diesel generators and the emergency genset run on MGO.
The vessel is fitted with one (1) KONUS type KH 0,5/50 thermal oil boiler, operated on MGO.
Steering gear consists of one (1) FRYDENBO type HS 90D, rotary vane electro-hydraulic
steering gear.
The vessel is equipped with a 220 KW electric-driven bow thruster (JASTRAM type BU 40F).
Page 7 of 20
XXII – 01012
“SUMMER”
Thermal Oil heater No.1 – internal 25 Apr 2021 31 May 2023 ---
Thermal Oil heater No.2 – internal 25 Apr 2021 31 May 2023 - ---
Page 8 of 20
XXII – 01012
“SUMMER”
MARPOL Annex VI-EE – initial/renewal 11 Mar 2018 31 May 2023 28 Feb 2023 -
31 May 2023
MARPOL Annex VI-EE – additional 05 May 2021 --- ---
- Following memoranda MO6 (Class) & MO7 (Statutory) at DVNGL status are transferred to
PRS
Page 9 of 20
XXII – 01012
“SUMMER”
1. By 31 December 2020, EU flagged existing ships and Non-EU flagged ships calling at
port or anchorage of an EU member state, of more than 500 gross tonnes, shall be
provided with an approved by PRS H.O. or Flag State Inventory of Hazardous Materials
(IHM).
An initial survey shall be conducted by 31 December 2020. The survey shall verify that
Part I of the inventory of hazardous materials complies with the requirements of the
Regulation of the European Parliament and of the Council (EU) No. 1257/2013 of
November 20, 2013 on ship recycling and amending Regulation (EC) No. 1013/2006
and Directive 2009/16/EC.
More details can be found on:
https://www.prs.pl/offer-16/ship-surveys-1/offer-2/recycling-of-ships-ihm.
2. After the first IOPP renewal survey, completed after 2019-09-08, all ships have to
comply with BWM Convention Regulation D-2 (ballast water treatment plant).
To fulfil of D-2 Standard (ballast water performance standard) of International BWM
Convention, following steps needs to be taken:
2.1. The chosen BWMS has to be Type Approved by PRS;
2.2. Before installation takes place onboard the ship, retrofit documentation including
details of the intended system should be approved by PRS Head Office;
2.3. Installation process should be confirmed by shipyard and if needed with BWMS
manufacturer;
2.4. After installation, commissioning and operational testing has to be done in PRS
witness. Additional Flag requirements should be fulfilled if needed.
2.5. BWMP should be revised and approved by PRS or if needed by Flag.
This Information for Owner (IO) supersedes IO Report (61/KN/17) dated 2017-06-01
and (111/KN/17) dated 2017-08-23.
If the vessel already complies with D-2 Standard or is exempted, than this IO shall be
deleted from the status at first PRS attendance on board.
Page 10 of 20
XXII – 01012
“SUMMER”
The vessel was found lying anchored, in full ballast condition, at Piraeus anchorage, awaiting
orders for next charter.
The vessel has been under the present Management/Ownership since April 2021.
Following acquisition, the vessel was brought at a shipyard in Yalova, Turkey, where she
underwent drydocking and major maintenance upgrading works, including complete overhaul
of main engine, shaft and diesel generators. Class was transferred from DNV to Polish Register
(PR) on that occasion.
It was reported that during the last 6 months the vessel has been carrying solely butane and
propane liquid cargoes between ports in the Black, Aegean & Adriatic Seas.
The hull structure appeared to be sound overall. External side shell plating (above the
waterline) was noted free of noteworthy indentations. Weather decks noted sound overall.
Protective coating on shell plating and on weather decks in good condition.
As previously stated, no ballast tanks were made available for internal examination on this
occasion.
Per Class records as indicated in the PRS Survey Status, all ballast tanks were internally
inspected by Class on 05 May 2021, and condition of coating (hard type) is stated “Fair”,
with the exception of the forepeak tank in which the condition of coating is stated “Poor”
(Note: the forepeak tank is stated requiring annual examination).
Air vent pipes, ventilators, railings etc. were found in generally good condition.
Bow thruster room structurally sound, dry, clean and tidy. Electric heater in place found in
good condition.
Latest UTM report of the hull structure, dated April 2021, was sighted and briefly perused.
Excessive diminutions of thicknesses beyond Class allowable limits, were not noted.
Page 11 of 20
XXII – 01012
“SUMMER”
Cargo tanks were not gas free and could not be internally examined in this instance.
Per Class records as indicated in the PRS Survey Status, the cargo tanks were internally
inspected by Class on 05 May 2021 (close-up examination) – no remarks.
No.1 & 2 cargo holds/void spaces, where the cargo tanks are located (2 tanks per hold), were
internally examined in this instance and found in sound condition overall with protective
coating in fair condition. Support bearings of the cylindrical cargo tanks appeared to be in
good order overall.
Sounding pipe of No.3 starboard Double bottom ballast tank, passing through No.1 cargo
hold/void space, found corroded and leaking – presence of water was evident in No.1 cargo
hold/void space.
As previously stated the vessel can carry 2 different/compatible cargoed simultaneously and
there are two(2) cross-over systems installed for such purpose, each consisting of one vapour
and one liquid line. Both Cross-overs can be connected to the cargo booster pump. In addition
to the cargo cross-overs there is one nitrogen cross-over line, equipped with a flow meter.
Two (2) manifold stations provided on main deck at port & starboard side, amidships, were
found in good condition - with fixed save-alls / drip trays in good apparent condition. Manifold
arrangement as follows:
Cargo lines : Liquid x 2, Vapour x 2
Manifold flanges : L1 = 6”/300 lbs/in2, L2 = 6”/300 lbs/in2, V1&2 = 4”/300 lbs/in2
Manifold location : 11.40m to keel / 1.70 m to deck / 2.30 m to rail
Tank domes including rubber seal rings, cargo lines and associated fittings and valves in
apparent satisfactory condition.
Pressure test records of cargo piping, P/V valves, buffer tanks and deck tank found in order.
Cargo compressors, heaters, piping etc. in the cargo compressor room in good apparent order.
Last overhauling reports of cargo deepwell pumps, compressors and condensers (reportedly
carried out in May 2021 at Yalova by external workshop) were not available/not sighted.
Page 12 of 20
XXII – 01012
“SUMMER”
Cargo tank temperature gauges and pressure sensors calibration certificates, dated
01/05/2021, sighted and found in order.
Note:
Two (2) centrifugal type ballast pumps, each of 80 m³/hr capacity are provided in the engine
room dedicated for ballast operations. There are no interconnections between the ballast and
cargo piping.
Vessel’s Maximum permissible discharging Ballast rate: Simultaneously with two (2) pumps:
160 m³/h – filling/discharge time 9 hrs.
4.3 Machinery
Main and auxiliary machinery appeared to be in general good working order. Repairs of a
“makeshift” nature were not noted. Very clean and tidy engine room spaces.
Monitoring and control panels of the main engines and auxiliary engines/machinery noted in
good apparent order.
No.1 diesel generator was seen running, without abnormalities. Reverse current trips on the
main switchboard and parallel operation of diesel generators were not tested, as the two
generators were not running in parallel. The Chief Engineer reported that there is water
leakage from one cylinder unit of No.2 diesel generator.
Records of machinery running hours were sighted and noted as follows (no overdue items for
overhaul):
A report regarding complete overhaul of the main engine, carried out end of April 2021 at
Yalova by external workshop, was sighted and the following are noted:
Page 13 of 20
XXII – 01012
“SUMMER”
Page 14 of 20
XXII – 01012
“SUMMER”
Last LO analysis reports, dated 09/12/2021, of main engine, main engine gearbox, diesel
generators, CCP and stern tube were sighted and noted as follows:
Switchboards, electrical equipment and cables were generally examined and no defects were
noted. Last Megger test report, carried out by an external workshop on 01/05/2021, was
sighted and considered satisfactory.
Piping, sea suctions and overboard discharges were generally examined and noted in good
apparent order. Boiler overboard valve in satisfactory condition.
Fuel transfer system appeared in general good order. The FO/LO purifiers were found free of
apparent leakages (reportedly opened up/overhauled back in April 2021). FO heaters and
respective piping/valves well insulated and without leakages/oil traces, in a general
satisfactory condition overall. The FO/DO Service and Settling tanks valves, thermometers,
level gauges free of apparent defects – sight glass in good condition.
The oil-fired boiler was noted in good order externally. The oil burner flame failure
shutdown/alarm tested satisfactorily on this occasion. Auxiliary Boiler Internal Examination &
hydraulic testing was carried out/credited by the Class during vessel’s drydocking in April-May
2021.
Page 15 of 20
XXII – 01012
“SUMMER”
E/R bilge high level alarm (floater type) was satisfactorily tested on this occasion.
The rotary vane electro-hydraulic steering gear was tested satisfactorily on the main and
emergency modes.
Main and auxiliary machinery manuals and spare parts books noted available onboard in
English language.
Rudder clearances (neck bearing) -: Fore 0.80 mm / Aft 0.20 mm / PS 0.50 mm / SS 0.60 mm
An adequate supply of main spare parts for the main engine and auxiliary engines noted
available on board. The following major spares were noted available:
Main Engine
- 2 pcs cylinder head
- 1 pc liner
- 1 pc piston crown
- 1 pc connecting rod
- 11 sets bearings
- 9 pcs fuel injectors
Diesel Generators
- 1 pc cylinder head
- 1 pc liner
- 1 pc piston crown
- 1 pc connecting rod
- 2 sets bearings
- 8 pcs fuel injectors
Anchor windlasses and mooring winches noted in generally satisfactory condition. Anchor
chain cables’ accessible/visible lengths noted in good condition. Port and starboard chain
lockers in sound condition.
Anchor chain calibration reports, dated 27/04/2021, were sighted. Original length/diameter 9
shackles / 42 mm – average wear 7%.
Fairlead rollers/bitts in good condition. Rollers randomly checked and found turning freely.
Page 16 of 20
XXII – 01012
“SUMMER”
Firefighting and lifesaving equipment were generally examined and noted in good order.
Service certificates for the fire-fighting and lifesaving equipment were sighted and found in
order.
Fire hose stations, fire hydrants and fire line in good condition overall.
Copies of the Fire Plan were found posted internally and placed in external weather tight
containers.
The Free fall lifeboat (17 persons capacity) and davit were noted in generally good apparent
condition. Wires were noted greased and slideway in order. Release hooks and supports (to
the extent accessible/visible) were generally noted in good apparent condition.
The rescue boat (6 persons) and its davit were noted in generally good apparent condition.
Wires were noted greased. Release hooks and supports (to the extent accessible/visible) were
generally noted in good condition.
Life-rafts (2 in total each of 16 persons capacity) and their cradles were noted in good apparent
condition. Certificates in order.
Emergency generator:
- The emergency generator room is located in the accommodation superstructure, on
the port side.
- Primary means of starting is by battery - well charged. Secondary (air) provided-piping
and associated couplings in good apparent condition. Air leaks were not noted.
- The engine was started manually and noted operating steadily.
- Shore connection box provided.
- Two (2) space heaters available.
Firefighting means consist of the following, all noted in good apparent order:
- Fixed CO2 system in engine room spaces, emergency generator room, compressor room
- last serviced on 26/04/2021
- Foam and fire line on main deck (last foam test on 26/04/2021)
- Single CO2 bottle serving the Galley.
- Drencher system serving the paint store - last serviced on 26/04/2021
Page 17 of 20
XXII – 01012
“SUMMER”
Navigation Bridge noted properly equipped with navigational and radio equipment, which
appeared to be in general good working order. Equipment randomly tested satisfactorily.
List of equipment as follows:
Noted in an overall good state of maintenance. Fairly clean and tidy and well lit. WC flushing
systems randomly tested and noted working properly.
External bulkheads were noted in good apparent condition and generally clean. Paint
generally holding well.
Officers and crew mess rooms noted fairly clean and tidy.
Page 18 of 20
XXII – 01012
“SUMMER”
4.8 Preparations for compliance with IMO 2020 FO sulphur cap regulations
No information was available regarding this subject. To the extent known, no preparations
have been made.
No information was available regarding this subject. To the extent known, no preparations
have been made in this respect.
Last PSC inspection (PARIS MOU) took place in Bakar, Croatia on 13/05/2021 - 7 deficiencies
imposed (not detainable).
According to records from Equasis website, the vessel has not been detained by PSC.
The below consumptions were verbally provided by the Master and Chief Engineer:
In ballast : abt 12.5 knots – abt 7.5 Mt/day HFO with shaft generator (+1.5 MT with
one(1) diesel generator running)
Laden : abt 11.5 knots – abt 7.5 Mt/day HFO with shaft generator (+1.5 MT with
one(1) diesel generator running)
Page 19 of 20
XXII – 01012
“SUMMER”
On the basis of our superficial inspection, the vessel was found in good condition overall.
The following deficiencies/observations were noted during the inspection:
- No.2 diesel generator was not seen in operation - the Chief Engineer reported that
there is water leakage from one cylinder unit.
- The emergency fire pump, located at the bow thruster compartment, found leaking
(water leaking from the packing gland).
- Sounding pipe of No.3 starboard Double bottom ballast tank corroded and leaking –
water was evident in No.1 void space
- From perusal of the analysis report of gearbox lub oil, dd 9/12/2021 (sample taken on
12/11/2021), presence of high content of wear metals (iron, copper & lead) was noted
suggesting abnormal wear of the rotating parts
The installation of a Ballast Water Treatment plant is a considerable expenditure which will
inevitably be incurred for the renewal of the IOPP certificate.
7.0 ATTACHMENTS
Complete photographic record taken during our inspection onboard together with copies of
ship’s certificates, plans and documentation.
---------------------------ooooOoooo-------------------------
ORIGINAL SIGNED
___________________
Attending Surveyors
DISCLAIMER: The information that is included in this document is given in good faith. While every effort has
been made to ensure the accuracy of the information contained in this document, Mentor Marine
Consultants and its representatives, agents, employees, and/or affiliates accept no liability for any findings
or determinations contained herein, or for any error or omission, alleged to be contained herein.
The information contained in this document, and any accompanying documentation or photographs, is not
exhaustive as to the general condition of the ship and should not be relied upon by clients or by any other
party as any assurance, representation or warranty as to the condition of the ship.
Mentor Marine Consultants expressly disclaim any liability or responsibility of any type, direct or indirect,
including for damage or loss resulting from the use, or misuse, or non-use of this document or information
contained in it.
No portion of this document and/or associated attachments is offered as a warranty, express or implied, of
the condition, life expectancy, seaworthiness or value of the vessel.
Page 20 of 20