Professional Documents
Culture Documents
Estimate of Work - Final Nabin Shrestha SYuchatar
Estimate of Work - Final Nabin Shrestha SYuchatar
Tinkune, Kathmandu
BILL OF QUANTITY
Terms & Conditions Client
1 The price is exclusive of vat. Project: Residential Building
2 Items not mentioned in this cost will be extra & actual quantity my vary as per site Condition. Date
3 Water and eletricity should be provided by owner during construction work.
4 Transportation Cost: Loading and Un-loading, lifting; Included. In Figure: रु 3,985,586.78
Total
In words:
S.N. DESCRIPTION OF WORKS Quantity Unit Rate (NRs.) Amount (Rs.) Remarks
A FOUNDATION WORKS
1 Site Clearance
Site Clearance sft 5.40 as per site
-
2 Earthwork Excavation -
Earthwork in excavation in trenches in all kinds of soil including dressing of sides, ramming of
bottom, watering, shoring, dewatering including lead upto a distance of 10m and lift 1m, all 3687.29 cuft 12.00 44,247.46
complete as per drawing, specification and approval of Engineer.
-
3 Earthwork in Filling -
Earthwork in filling in foundation including ramming of filled earth in 15cm layers with
sprinkling of water, lead upto 10m all complete with compaction and final level as per drawing, 2457.21 cuft 10.00 24,572.10
specification and approval of Engineer.
Earthwork in filling in foundation including ramming of filled earth in 15cm layers with
sprinkling of water, lead upto 10m all complete with compaction and final level as per drawing, 4990.00 cuft 27.00 134,730.00
specification and approval of Engineer.
-
4 Flat Brick Soiling -
Supplying and laying of one layer flat brick soling all complete in perfect line and level as per the
1320.93 sft 76.00 100,390.59
drawing, specification and approval of Engineer.
-
5 PCC Works -
Supplying and laying 3" cement concrete work M15 (1 cement: 2 sand: 4 aggregate) on
a foundation including proper mixing, sufficient use of vibrators, curing all complete as per 384.07 cuft 350.00 134,425.99
drawing, specification and approvation of Engineer.
Supplying and laying cement concrete work M20 (1 cement: 1.5 sand: 3 aggregate) on floor slab,
beam Stair Case excluding the cost of reeinforcement bars & formwork whereas, including proper
b 1632.80 cuft 400.00 653,121.73
mixing, sufficient use of vibrators, curing all complete as per drawing, specification and
approvation of Engineer.
Good quality of local chimmeny made Brickworkes in 1:6 C/S mortar up to Plinth in perfect line
level finishing including wetting the bricks racking the joints and curing the works for at least 7 625.91 cuft 340.00 212,808.98
days all complete as per drawing, specification and approvation of Engineer.
7 Formworks -
Supply and laying of wooden/waterproof plywood/steel formwork for PCC works with necessary
cutting, nailing, propping, scaffolding, staging, supporting, etc. including providing final surface
4447.61 sqft 85.00 378,047.02
in correct line, level, cleaning the surface and removal of forms all complete as per drawing,
specification and approval of Engineer.
8 Reinforcement bars -
Supplying & placing of Fe: 500 reinforcement bar for column beams, slab etc. placed in position
and binding with 14 gauge binding wire including cutting , binding , carrying etc.all complete as 6402.49 kg 140.00 896,349.30
per drawing, specification and instruction of Engineer.
9 Plastering Works
12.5mm thick cement sand plaster in (1:4) ratio on inner wall of good finish including racking
the joint, wetting of surfaces & curing the work all complete as per drawing, specification and 3227.94 sqft 40.00 129,117.54
instruction of Engineer.
12.5mm thick cement sand plaster in (1:4) ratio on outer wall of good finish including racking
the joint, wetting of surfaces & curing the work all complete as per drawing, specification and 1493.83 sqft 50.00 74,691.58
instruction of Engineer.
Providing and fixing uPVC doors and windows including screws, sliding locks, joining elements,
etc., joining to the LGS wall Panels all complete with all the other necessary fittings as per the
drawing, specification and instruction of site-incharge
11 Painting Works
Applying two or more coats of Emulsion paint along the primer in the internal wall & ceiling
inside surface to give an even & uniform shade including the cost of scaffolding all complete as 3227.94 sqft 32.00 103,294.03
per drawing & specifications and approval of Engineer.
Applying two or more coats of Weather-coat paint along the primer in outer wall & outer ceiling
surface to give an even & uniform shade including the cost of scaffolding all complete as per 746.92 sqft 32.00 23,901.30
drawing & specifications and approval of Engineer.
38mm thick screeding work in 1:2:4 c/s/a ratio including cement punning all complete as per the
1500.00 sqft 90.00 135,000.00
drawing, specification and instruction of Engineer.
13 9"Brick Wall Works
Good quality of local chimmeny made Brickworkes in 1:6 C/S mortar up to Plinth in perfect line
level finishing including wetting the bricks racking the joints and curing the works for at least 7 716.57 cuft 420.00 300,957.62
days all complete as per drawing, specification and approvation of Engineer.
Good quality of local chimmeny made Brickworkes in 1:6 C/S mortar up to Plinth in perfect line
level finishing including wetting the bricks racking the joints and curing the works for at least 7 378.16 sqft 150.00 56,723.93
days all complete as per drawing, specification and approvation of Engineer.
15 Flooring Works
i
Providing and laying Marble (approved color and pattern) in 1:4 cement sand mortar including
the cost of cutting, grinding, polishing, groove making, moulding, placing and filling with grout
326.15 sqft 350.00 114,150.89
and screeding of required thickness in 1:6 cement mortar as required all complete as per drawing,
specification and approved of engineer.
ii
Providing and laying toilet Wall tile (approved color and pattern) in 1:4 cement sand mortar
including the cost of cutting, grinding, polishing, groove making, moulding, placing and filling Base rate of the
161.28 sqft 250.00 40,320.00
with grout and screeding of required thickness in 1:6 cement mortar as required all complete as material : -100/ sft
per drawing, specification and approved of engineer.
iii
Providing and laying toilet Floor tile (approved color and pattern) in 1:4 cement sand mortar
including the cost of cutting, grinding, polishing, groove making, moulding, placing and filling Base rate of the
115.34 sqft 300.00 34,600.95
with grout and screeding of required thickness in 1:6 cement mortar as required all complete as material : -120/ sft
per drawing, specification and approved of engineer.
v
Providing and laying Terrace and Balcony Floor tile (approved color and pattern) in 1:4 cement
sand mortar including the cost of cutting, grinding, polishing, groove making, moulding, placing Base rate of the
22.50 sqft 300.00 6,750.00
and filling with grout and screeding of required thickness in 1:6 cement mortar as required all material : -130/ sft
complete as per drawing, specification and approved of engineer.
Submitted By
Structures Nepal P. Ltd.
Detailed Estimate
S.N. Particulars Unit Rate Total Qty Amount
A Cost Summary 4,012,920.709
1 Earthwork Excavation Cft 12.000 3,687.288 44,247.456
2 Earthwork in filling Cft 10.000 2,457.210 24,572.099
Earthwork in filling (from outside) cft 27.000 4,990.000 134,730.000
3 Mix Gravel filling Cft 90.702 - -
4 100micron DPM Sft 10.000 80.000 800.000
5 Brick soling sft 80.000 1,320.929 105,674.307
6 M10 (PCC) Cft 350.000 384.074 134,425.989
7 M20 (RCC) Cft 400.000 1,632.804 653,121.728
8 Normal Formwork (12 mm Ply) Sft 85.000 4,447.612 378,047.019
9 Reinforcement Work Kg 130.000 6,402.495 832,324.349
9" brickwork
Sub Structure cft 340.000 625.909 212,808.975
Super Structure cft 420.000 716.566 300,957.615
4" brickwork sft 150.00 378.160 56,723.925
10 Plaster work
Outside plaster sft 50.000 1,493.832 74,691.575
Inside plaster sft 40.000 3,227.939 129,117.540
Inside plaster on jamb and sill rft 50.000 - -
11 IPS sft 95.000 1,500.000 142,500.000
12 Woodwork -
Saalwood door frame cft 7,500.000 8.214 61,606.823
Door Shutter (3x7) nos 7,500.000 3.000 22,500.000
Door Shutter (MD) nos 30,000.000 2.000 60,000.000
13 Tile works nos 276.617 220.000 60,855.630
14 Marble Works nos 350.000 326.145 114,150.886
15 Window works (Aluminium) sft 700.000 159.750 111,825.000
1 Paint and Putting Works
Outside paint (Weather coat) sft 746.916 32.000 23,901.304
Inside paint (Emulsion) sft 3,227.939 32.000 103,294.032
17 Electrical works 98,590.48
18 Sanitary and plumbing 131,453.98
GF 772.500
Foundation 193.125
Staircase cover 149.276
Total Area 1,114.901
Total Cost 4,012,920.709
Cost per sft 3,599.35
Detailed Estimate
S.N. Particulars Unit No L B H Qty Total Qty
Earthwork in excavation cft 3687.288
1 Footing 2352.000
1.1 A1 1 7.000 7.000 4 196.000
1.2 A2 1 7.000 7.000 4 196.000
1.3 A3 1 7.000 7.000 4 196.000
1.4 B1 1 7.000 7.000 4 196.000
1.6 B2 1 7.000 7.000 4 196.000
1.7 B3 1 7.000 7.000 4 196.000
1.8 C1 1 7.000 7.000 4 196.000
1.9 C2 1 7.000 7.000 4 196.000
1.1 C3 1 7.000 7.000 4 196.000
1.11 D1 1 7.000 7.000 4 196.000
1.12 D2 1 7.000 7.000 4 196.000
1.13 D3 1 7 7 4 196.000
2 Wall Trench
2.1 Along Grid 1-1,2-2 & 3-3 3 33.749 2 4 809.976
2.2 Along Grid A-A,B-B,C-C & D-D 4 16.416 2 4 525.312
Remarks
Detailed Estimate plot 12
S.N. Particulars Unit Quantity Remarks
EARTHWORK IN BACKFILLING cft 7447.21
Excavation 3687.29
Deduct
Brick Soling (220.60)
PCC (384.07)
Substructure b/w (625.91)
4 Columns 608.000
GF 12 9.5 4 456.000
HR 4 9.5 4 152.000
6 FF beam 542.461
6.1 Along Grid 1-1,2-2 & 3-3 3 33.749 3.25 329.053
6.2 Along Grid A-A,B-B,C-C & D-D 4 16.416 3.25 213.408
6 FF beam 156.479
6.1 Along Grid 1-1,2-2 & 3-3 3 33.749 0.75 1.25 94.919
6.2 Along Grid A-A,B-B,C-C & D-D 4 16.416 0.75 1.25 61.560
7 Slabs 451.23946067
GF cover 1 38.677 19.416 0.416 312.39629
Staircase headroom 1 20.33 16.417 0.416 138.84317
9 Stairs
15 3.167 0.916 0.583 25.369 25.36900014
1 14 3.167 0.416 18.444608 18.444608
Remarks
1 Footing L B do D d/2
S.N. Particulars Unit No L B H Qty R.C.C qty
Rebar works kg 1632.80
1 Footing R.C.C kg 358.56
2 Bottom Tie Beam (9"x14") kg 125.18
4 Pedestal kg 84.00
5 Plinth Beam kg 156.48
6 GF column kg 152.00
8 FF Beam kg 232.72
7 FF Slab kg 451.24
9 Staircase GF-FF kg 43.81
10 Lintel Band kg 28.81
Pt Wt(kg) Total Remarks
6402.49
1.00 796.91
1.20 333.87
4.00 746.77
2.00 695.56 #REF!
4.00 1351.30
2.00 1034.44
1.00 1002.90
4.00 389.51
0.80 51.23
Detailed Estimate plot 12
S.N. Particulars Unit No L B H Qty Total Qty Remarks
Brickwork 9" cft
Substructure Brickwork 625.909
Along 1-1 1 33.747 0.75 7 177.1718
Along 2-2 1 33.747 0.75 1 25.31025
Along 3-3 1 33.747 0.75 7 177.1718
Along A-A 1 16.417 0.75 7 86.18925
Along B-B 1 16.417 0.75 1 12.31275
Along C-C 1 16.417 0.75 5 61.56375
Along D-D 1 16.417 0.75 7 86.18925
7 Along Grid DD
1 8.416 0.75 8.25 52.074
1 8 0.75 8.25 49.500
First Floor
1 Along Grid 11 76.310438
1 12.333 0.75 8.25 76.31044
2 Door 2 3 7
3 Main door(Living Room) 1 3.5 7
4 Door(toilet) 1.000 2.5 7
5 W1 3.000 5 4.5
6 W2 1.000 3 4.5
7 W3 1.000 2.5 4.5
8V 1.000 3 2
9 V1 2 1.5 4.5
Detailed Estimate plot 12
S.N. Particulars Unit No L B H Qty Total Qty
Brickwork 4" sft 378.160
1 Toilet Wall 1 9.416 9.000 84.74
Deduct -
V1 (1) 2.000 4.500 (9.00)
D1 (1) 2.500 7.000 (17.50)
2 Grid 2-2
Wall 1 12.330 8.250 101.72
1 11.250 8.250 92.81
Deuct (1) 3.500 7.000 (24.50)
(1) 3.000 7.000 (21.00)
(1) 4.500 4.500 (20.250)
3 Grid B-B
1 9.417 8.250 77.690
Deduct (1) 3.000 7.000 (21.000)
6 Along CC
2 8.416 9.5 159.904
11 Ceiling 1 750.000
B First Floor
Lobby 1 4 12.33 49.32
1.3 Tread
GF-TF 15 3.5 1 52.5
121.984
32
52.500
56
63.661
FF-SF
GF-FF
Detailed Estimate Plot 12
S.N. Particulars Unit No L B Qty Total Qty
WATER PROOFING sft 187.88
1 Terrace Wall
1.1 Lower terrace 1 0 0.75 0.000
1.2 Upper terrace 1 0 0.75 0.000
2 Toilet walls
2.1 GF common toilet 1 22.5 1 22.500
2.2 FF common toilet 1 22.834 1 22.834
3 Toilet Floor
2.1 GF common toilet 1 8 4.5 36.000
2.2 FF common toilet 1 8.167 4.5 36.752
4 Laundry
4.1 Floor 1 11.417 3.5 39.960
4.2 Wall 1 29.834 1 29.834
Remarks
Detailed Estimate Plot 12
S.N. Particulars Unit No L H Qty Total Qty
Culture Stone Cladding sft 217.136
Grid D12 1.00 13.500 8.792 118.692
Grid D23 1.00 10.500 8.792 92.316
Grid 2CD 1.00 11.500 8.792 101.108
Deduction
D1 (1.00) 4.000 7.000 (28.000)
W1 (1.00) 8.000 6.000 (48.000)
W5 (1.00) 1.830 6.000 (10.980)
W6 (1.00) 2.000 4.000 (8.000)
Remarks
Detailed Estimate Plot 12
S.N. Particulars Unit No L B or H Qty Total Qty
POP WORKS
A POP on ceiling sft 1,241.113
B POP on walls sft 3,436.457
C POP on jamb on sill rft 433.565
2 First Floor
2.1 D2 3 3.25 7 51.75
2.2 D3 2 2.5 7 33
2.3 D4 1 3 7 17
2.4 SD 1 6 7 20
2.5 W6 1 2 4 10
2.6 W4 1 4 6 16
2.7 W7 1 4.333 4.83 13.993
2.8 W2 1 2.083 3.667 9.417
2.9 W1 1 8 6 20
2.10 W5 1 1.83 6 13.83
3 Top floor
3.1 D2 1 3.25 7 17.25
3.2 D4 1 3 7 17
3.3 W8 1 2.667 5.167 13.001
3.4 W4 1 4 6 16
3.5 W7 1 4.333 4.83 13.993
Remarks
Towards staircase
Towards common toilet
24.750
Already include in staircase headroom
Detailed Estimate Plot 12
S.N. Particulars Unit No L Qty Total Qty Remarks
Precast coping rft 43.042
1 Lower terrace
1.1 East 1 16.375 16.375
1.2 South 1 26.667 26.667
Detailed Estimate Plot 12
S.N. Particulars Unit No L B or H Qty Total Qty
Polyplaster work sft 1,210.322
2 First Floor
2.1 D2 3 3.25 7 68.25
2.2 D3 2 2.5 7 35
2.3 D4 1 3 7 21
2.4 SD 1 6 7 42
2.5 W6 1 2 4 8
2.6 W4 1 4 6 24
2.7 W7 1 4.333 4.83 20.93
2.8 W2 1 2.083 3.667 7.64
2.9 W1 1 8 6 48
2.10 W5 1 1.83 6 10.98
3 Top floor
3.1 D2 1 3.25 7 17.25
3.2 D4 1 3 7 17
3.3 W8 1 2.667 5.167 13.001
3.4 W4 1 4 6 16
3.5 W7 1 4.333 4.83 13.993
Horizontals
Verticals
Horizontals
Verticals
4.2 FF BR balcony
1.5"Ø Round pipe 1 15.833 15.833 1.050 16.625
3/4"Ø Round pipe (horizontal) 3 15.500 46.500 0.570 26.505
1"Ø Round pipe (vertical) 4 3.000 12.000 0.740 8.880
Hooves
Legs
Upper horizontals
Lower horizontals
Platform
Horizontal railing
Horizontal railing
Vertical railing
Ladder verticals
Ladder steps
Ladder vertical's support
Horizontals
Verticals
Horizontals
Verticals
Horizontal Latch
Behind Horizontal Latch
Around Horizontal Latch
Bush
Hinge
Vertical latch stopper
Behind Vertical latch
Circular for vertical latch
Notch for Horizontal Latch
Vertical latch
Vertical notch
North
South
S.N Description Unit Quantity Rate Amount
SANITARY WORKS (Material+Labor) 246,503.89
A Sanitary Materials 170,799.11
1 PPR Pipe
20mm Mtr. 35.00 38.62 1,351.61
25mm Mtr. 70.00 44.37 3,105.90
32mm Mtr. 30.00 99.75 2,992.50
40mm Mtr. 112.50 -
50mm Mtr. 169.49 -
63mm Mtr. 270.00 -
75mm Mtr. 494.25 -
2 Ball Valve -
15mm Nos. 2.00 601.00 1,202.00
20mm Nos. 2.00 669.00 1,338.00
25mm Nos. 2.00 1,124.00 2,248.00
32mm Nos. 2.00 1,465.00 2,930.00
3 Pex Insulation -
15mm insulation Mtr. 86.00 -
20mm insulation Mtr. 110.00 -
4 PVC Pipes -
110mm Mtr. 96.00 221.11 21,226.24
75mm Mtr. 25.00 123.00 3,075.00
50mm Mtr. 10.00 68.33 683.33
5 PVC Fittings -
Cowel 75 mm dai Nos. 2.00 98.00 196.00
Plug 15mm dia Nos. 27.00 20.00 540.00
6 Sanitary Fixture -
Commode with cistern Set 2.00 13,031.00 26,062.00
Wash basin with pedestal Set 2.00 6,700.00 13,400.00
W/C pan with cistern Set 1.00 5,771.00 5,771.00
Wall mixture with sliding shower Pcs 2.00 10,000.00 20,000.00
Basin mixture Pcs 3.00 4,200.00 12,600.00
Laundry mixture Pcs 1.00 4,200.00 4,200.00
Long body bibcock Pcs 1.00 1,065.00 1,065.00
Short body bibcock Pcs 2.00 750.00 1,500.00
Bath accessories Set 3.00 6,350.00 19,050.00
Commode spray Pcs 3.00 650.00 1,950.00
Angle Valve Pcs 16.00 250.00 4,000.00
Mirror Pcs 3.00 700.00 2,100.00
Mirror shelf Pcs 3.00 1,250.00 3,750.00
Brass tap Pcs 2.00 250.00 500.00
Floor trap (Cockroach or nilkantha) Pcs 8.00 650.00 5,200.00
Floor trap (Multifloor or nani) Pcs 8.00 123.44 987.52
Float valve Pcs 1.00 450.00 450.00
Water meter Pcs 1.00 200.00 200.00
Overhead tank Pcs 1.00 7,125.00 7,125.00
B Labor charge 38,102.50
1 Installation of PPR Pipe
20mm Mtr. 35.00 79.00 2,765.00
25mm Mtr. 70.00 86.00 6,020.00
32mm Mtr. 30.00 92.00 2,760.00
40mm Mtr. 99.00 -
50mm Mtr. 105.00 -
63mm Mtr. 112.00 -
75mm Mtr. 118.00 -
2 Ball Valve -
15mm Nos. 2.00 36.00 72.00
20mm Nos. 2.00 44.00 88.00
25mm Nos. 2.00 58.00 116.00
32mm Nos. 2.00 61.00 122.00
3 Pex Insulation -
15mm insulation Mtr. -
20mm insulation Mtr. 60.00 -
4 PVC Pipes -
110mm Mtr. 96.00 153.00 14,688.00
75mm Mtr. 25.00 131.00 3,275.00
50mm Mtr. 10.00 117.00 1,170.00
5 PVC Fittings -
Cowel 75 mm dai Nos. 2.00 -
Plug 15mm dia Nos. 27.00 -
6 Installation of Sanitary Fixtures -
Commode with cistern Set 2.00 729.00 1,458.00
Wash basin with pedestal Set 2.00 507.00 1,014.00
Wall mixture Pcs 2.00 254.00 508.00
Basin mixture Pcs 2.00 254.00 508.00
Sink mixture Pcs 1.00 254.00 254.00
Long body bibcock Pcs 1.00 32.00 32.00
Short body bibcock Pcs 2.00 32.00 64.00
Bath accessories Set 2.00 317.00 634.00
Commode spray Pcs 2.00 63.00 126.00
Angle Valve Pcs 12.00 32.00 384.00
Mirror Pcs 2.00 127.00 254.00
Mirror shelf Pcs 2.00 100.00 200.00
Brass tap Pcs 2.00 50.00 100.00
Floor trap (Cockroach or nilkantha) Pcs 6.00 44.00 264.00
Floor trap (Multifloor or nani) Pcs 6.00 44.00 264.00
Float valve Pcs 1.00 50.00 50.00
Water meter Pcs 1.00 200.00 200.00
Overhead tank Pcs 1.00 712.50 712.50
Remarks
S.N Desciption Unit Quantity Rate Amount
ELECTRIC WORKS (Material+Labor) 147,461.96
A Electric Materials 112,767.76
1 Copper wire
1/18 coil 3.00 885.00 2,655.00
3/20 coil 2.00 1,966.00 3,932.00
3/22 coil 9.00 1,186.00 10,674.00
7/18 coil 0.60 6,115.53 3,669.32
7/20 coil 1.00 3,387.00 3,387.00
7/22 coil 5.00 2,416.00 12,080.00
2 TV Wire Coil 1.00 875.00 875.00
3 Telephone Wire 2 Pair Coil 1.00 2,050.00 2,050.00
4 Telephone Wire 5 Pair Coil 0.50 2,989.98 1,494.99
5 HDPE Pipe -
20mm Mtr. 570.00 32.00 18,240.00
25mm Mtr. 35.00 43.37 1,517.95
6 Meter Box Nos. 1.00 1,916.00 1,916.00
7 Sub meter Nos. 1.00 1,150.00 1,150.00
8 Letter Box Nos. 1.00 1,480.00 1,480.00
9 DB box with Baseplate set 2.00 12,783.00 25,566.00
10 3x3 metal Box Nos. 43.00 25.00 1,075.00
11 3x5 metal Box Nos. 14.00 35.00 490.00
12 4x6 Junction Box Nos. 4.00 62.00 248.00
13 TV/Tel Box Nos. 2.00 1,550.00 3,100.00
14 Switch and socket -
Telephone socket Nos. 6.00 275.00 1,650.00
T.V. socket Nos. 4.00 275.00 1,100.00
1 gang 1 way switch Nos. 6.00 65.00 390.00
1 gang 2 way switch Nos. 1.00 78.31 78.31
2 gang 1 way switch Nos. 3.00 78.31 234.93
2 gang 2 way switch Nos. 2.00 138.43 276.85
3 gang 1 way switch Nos. 2.00 245.21 490.42
3 gang 2 way switch Nos. 260.00 -
4 gang 1 way switch Nos. 4.00 487.00 1,948.00
5 gang 1 way switch Nos. 1.00 1,186.00 1,186.00
6 gang 1 way switch Nos. 1.00 1,080.00 1,080.00
6 gand 2 way switch Nos. 650.00 -
3 gang 1 way + 2 pin socket Nos. - 1,672.00 -
1 gang 2 way switch+bell Nos. 1.00 418.00 418.00
Power Socket (15 Amp local) Nos. 5.00 150.00 750.00
15 Amp. Power socket(clipsal) Nos. 17.00 445.00 7,565.00
13 Amp Power Socket Nos. 400.00 -