You are on page 1of 59

Block 3 Unit 1 37% Block 3 Unit 2 62%

Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 57% STRUCTURAL 79%
Ground Floor 88% Ground Floor 100%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 50% Service Area and Comfort Room 100%
Carport and Septic tank 0% Carport and Septic tank 0%
2nd Floor 94% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 75% Comfort Room 100%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 75% Ground (Plumbing ang Fixtures) 75%
2nd Floor (Plumbing and Fixtures) 75% 2nd Floor (Plumbing and Fixtures) 75%
Plastering and Clearing 25% Plastering and Clearing 100%
Roof 60% Roof 100%
Roof Framing 100% Roof Framing 100%
Roofing 20% Roofing 100%

ARCHITECTURAL 11% ARCHITECTURAL 24%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 0% Staircase (Contractor) 50%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 0% Celing 50%
2nd Floor Partition 0% 2nd Floor Partition 20%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 0% Painting 0%

ELECTRICAL 42% ELECTRICAL 83%


Wiring and Provision 0% Wiring and Provision 100%
Box setting and Piping 100% Box setting and Piping 100%
Fixtures (Outlet and Switch) 25% Fixtures (Outlet and Switch) 50%
Block 3 Unit 5 57% Block 3 Unit 6 59%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 79% STRUCTURAL 79%
Ground Floor 100% Ground Floor 100%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 100% Service Area and Comfort Room 100%
Carport and Septic tank 0% Carport and Septic tank 0%
2nd Floor 100% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 100%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 75% Ground (Plumbing ang Fixtures) 75%
2nd Floor (Plumbing and Fixtures) 75% 2nd Floor (Plumbing and Fixtures) 75%
Plastering and Clearing 100% Plastering and Clearing 100%
Roof 100% Roof 100%
Roof Framing 100% Roof Framing 100%
Roofing 100% Roofing 100%

ARCHITECTURAL 17% ARCHITECTURAL 22%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 0% Staircase (Contractor) 0%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 50% Celing 70%
2nd Floor Partition 0% 2nd Floor Partition 25%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 0% Painting 0%

ELECTRICAL 75% ELECTRICAL 75%


Wiring and Provision 100% Wiring and Provision 100%
Box setting and Piping 100% Box setting and Piping 100%
Fixtures (Outlet and Switch) 25% Fixtures (Outlet and Switch) 25%
Block 3 Unit 9 57% Block 3 Unit 10 55%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 79% STRUCTURAL 78%
Ground Floor 100% Ground Floor 100%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 100% Service Area and Comfort Room 100%
Carport and Septic tank 0% Carport and Septic tank 0%
2nd Floor 100% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 100%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 75% Ground (Plumbing ang Fixtures) 75%
2nd Floor (Plumbing and Fixtures) 75% 2nd Floor (Plumbing and Fixtures) 75%
Plastering and Clearing 100% Plastering and Clearing 90%
Roof 100% Roof 100%
Roof Framing 100% Roof Framing 100%
Roofing 100% Roofing 100%

ARCHITECTURAL 16% ARCHITECTURAL 25% 13%


Doors 25% Doors 25%
Windows 25% Windows 0%
Staircase (Contractor) 0% Staircase (Contractor) 0%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 20% Celing 20%
2nd Floor Partition 20% 2nd Floor Partition 20%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 0% Painting 0%

ELECTRICAL 75% ELECTRICAL 75%


Wiring and Provision 100% Wiring and Provision 100%
Box setting and Piping 100% Box setting and Piping 100%
Fixtures (Outlet and Switch) 25% Fixtures (Outlet and Switch) 25%
Block 3 Unit 13 40% Block 3 Unit 14 39%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 58% STRUCTURAL 56%
Ground Floor 88% Ground Floor 88%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 50% Service Area and Comfort Room 50%
Carport and Septic tank 0% Carport and Septic tank 0%
2nd Floor 100% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 100%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 75% Ground (Plumbing ang Fixtures) 75%
2nd Floor (Plumbing and Fixtures) 75% 2nd Floor (Plumbing and Fixtures) 75%
Plastering and Clearing 20% Plastering and Clearing 10%
Roof 63% Roof 63%
Roof Framing 100% Roof Framing 100%
Roofing 25% Roofing 25%

ARCHITECTURAL 15% ARCHITECTURAL 12%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 0% Staircase (Contractor) 0%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 25% Celing 0%
2nd Floor Partition 10% 2nd Floor Partition 10%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 0% Painting 0%
ELECTRICAL 48% ELECTRICAL 50%
Wiring and Provision 20% Wiring and Provision 25%
Box setting and Piping 100% Box setting and Piping 100%
Fixtures (Outlet and Switch) 25% Fixtures (Outlet and Switch) 25%
Block 3 Unit 17 38% Block 3 Unit 18 38%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 56% STRUCTURAL 56%
Ground Floor 88% Ground Floor 88%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 50% Service Area and Comfort Room 50%
Carport and Septic tank 0% Carport and Septic tank 0%
2nd Floor 100% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 100%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 75% Ground (Plumbing ang Fixtures) 75%
2nd Floor (Plumbing and Fixtures) 75% 2nd Floor (Plumbing and Fixtures) 75%
Plastering and Clearing 10% Plastering and Clearing 10%
Roof 63% Roof 63%
Roof Framing 100% Roof Framing 100%
Roofing 25% Roofing 25%

ARCHITECTURAL 12% ARCHITECTURAL 12%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 0% Staircase (Contractor) 0%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 0% Celing 0%
2nd Floor Partition 10% 2nd Floor Partition 10%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 0% Painting 0%
ELECTRICAL 47% ELECTRICAL 47%
Wiring and Provision 20% Wiring and Provision 20%
Box setting and Piping 100% Box setting and Piping 100%
Fixtures (Outlet and Switch) 20% Fixtures (Outlet and Switch) 20%
Block 3 Unit 3 63% Block 3 Unit 4 58%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 79% STRUCTURAL 79%
Ground Floor 100% Ground Floor 100%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 100% Service Area and Comfort Room 100%
Carport and Septic tank 0% Carport and Septic tank 0%
2nd Floor 100% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 100%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 75% Ground (Plumbing ang Fixtures) 75%
2nd Floor (Plumbing and Fixtures) 75% 2nd Floor (Plumbing and Fixtures) 75%
Plastering and Clearing 100% Plastering and Clearing 100%
Roof 100% Roof 100%
Roof Framing 100% Roof Framing 100%
Roofing 100% Roofing 100%

ARCHITECTURAL 34% ARCHITECTURAL 21%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 0% Staircase (Contractor) 0%
Tile Works (Contractor) 90% Tile Works (Contractor) 0%
Celing 100% Celing 70%
2nd Floor Partition 20% 2nd Floor Partition 20%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 0% Painting 0%

ELECTRICAL 75% ELECTRICAL 75%


Wiring and Provision 100% Wiring and Provision 100%
Box setting and Piping 100% Box setting and Piping 100%
Fixtures (Outlet and Switch) 25% Fixtures (Outlet and Switch) 25%
Block 3 Unit 7 57% Block 3 Unit 8 56%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 79% STRUCTURAL 79%
Ground Floor 100% Ground Floor 100%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 100% Service Area and Comfort Room 100%
Carport and Septic tank 0% Carport and Septic tank 0%
2nd Floor 100% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 100%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 75% Ground (Plumbing ang Fixtures) 75%
2nd Floor (Plumbing and Fixtures) 75% 2nd Floor (Plumbing and Fixtures) 75%
Plastering and Clearing 100% Plastering and Clearing 100%
Roof 100% Roof 100%
Roof Framing 100% Roof Framing 100%
Roofing 100% Roofing 100%

ARCHITECTURAL 16% ARCHITECTURAL 14%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 0% Staircase (Contractor) 0%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 25% Celing 25%
2nd Floor Partition 20% 2nd Floor Partition 0%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 0% Painting 0%

ELECTRICAL 75% ELECTRICAL 75%


Wiring and Provision 100% Wiring and Provision 100%
Box setting and Piping 100% Box setting and Piping 100%
Fixtures (Outlet and Switch) 25% Fixtures (Outlet and Switch) 25%
Block 3 Unit 11 52% Block 3 Unit 12 43%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 71% STRUCTURAL 63%
Ground Floor 100% Ground Floor 88%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 100% Service Area and Comfort Room 50%
Carport and Septic tank 0% Carport and Septic tank 0%
2nd Floor 100% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 100%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 75% Ground (Plumbing ang Fixtures) 75%
2nd Floor (Plumbing and Fixtures) 75% 2nd Floor (Plumbing and Fixtures) 75%
Plastering and Clearing 50% Plastering and Clearing 50%
Roof 100% Roof 63%
Roof Framing 100% Roof Framing 100%
Roofing 100% Roofing 25%

ARCHITECTURAL 14% ARCHITECTURAL 12%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 0% Staircase (Contractor) 0%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 20% Celing 0%
2nd Floor Partition 10% 2nd Floor Partition 10%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 0% Painting 0%

ELECTRICAL 72% ELECTRICAL 55%


Wiring and Provision 90% Wiring and Provision 40%
Box setting and Piping 100% Box setting and Piping 100%
Fixtures (Outlet and Switch) 25% Fixtures (Outlet and Switch) 25%
Block 3 Unit 15 38% Block 3 Unit 16 38%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 54% STRUCTURAL 56%
Ground Floor 100% Ground Floor 88%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 100% Service Area and Comfort Room 50%
Carport and Septic tank 0% Carport and Septic tank 0%
2nd Floor 88% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 50% Comfort Room 100%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 75% Ground (Plumbing ang Fixtures) 75%
2nd Floor (Plumbing and Fixtures) 75% 2nd Floor (Plumbing and Fixtures) 75%
Plastering and Clearing 0% Plastering and Clearing 10%
Roof 63% Roof 63%
Roof Framing 100% Roof Framing 100%
Roofing 25% Roofing 25%

ARCHITECTURAL 12% ARCHITECTURAL 12%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 0% Staircase (Contractor) 0%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 0% Celing 0%
2nd Floor Partition 10% 2nd Floor Partition 10%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 0% Painting 0%
ELECTRICAL 47% ELECTRICAL 47%
Wiring and Provision 20% Wiring and Provision 20%
Box setting and Piping 100% Box setting and Piping 100%
Fixtures (Outlet and Switch) 20% Fixtures (Outlet and Switch) 20%
Block 4 Unit 19 37% Block 4 Unit 20 35%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 59% STRUCTURAL 53%
Ground Floor 88% Ground Floor 88%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 50% Service Area and Comfort Room 50%
Carport and Septic tank 20% Carport and Septic tank 20%
2nd Floor 100% 2nd Floor 88%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 50%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 75% Ground (Plumbing ang Fixtures) 75%
2nd Floor (Plumbing and Fixtures) 75% 2nd Floor (Plumbing and Fixtures) 75%
Plastering and Clearing 10% Plastering and Clearing 10%
Roof 63% Roof 38%
Roof Framing 100% Roof Framing 50%
Roofing 25% Roofing 25%

ARCHITECTURAL 11% ARCHITECTURAL 11%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 0% Staircase (Contractor) 0%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 0% Celing 0%
2nd Floor Partition 0% 2nd Floor Partition 0%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 0% Painting 0%

ELECTRICAL 40% ELECTRICAL 40%


Wiring and Provision 20% Wiring and Provision 20%
Box setting and Piping 80% Box setting and Piping 80%
Fixtures (Outlet and Switch) 20% Fixtures (Outlet and Switch) 20%
Block 4 Unit 23 33% Block 4 Unit 24 31%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 47% STRUCTURAL 47%
Ground Floor 88% Ground Floor 88%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 50% Service Area and Comfort Room 50%
Carport and Septic tank 20% Carport and Septic tank 20%
2nd Floor 88% 2nd Floor 88%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 50% Comfort Room 50%
Plumbing 50% Plumbing 50%
Ground (Plumbing ang Fixtures) 50% Ground (Plumbing ang Fixtures) 50%
2nd Floor (Plumbing and Fixtures) 50% 2nd Floor (Plumbing and Fixtures) 50%
Plastering and Clearing 10% Plastering and Clearing 10%
Roof 25% Roof 25%
Roof Framing 50% Roof Framing 50%
Roofing 0% Roofing 0%

ARCHITECTURAL 11% ARCHITECTURAL 6%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 0% Staircase (Contractor) 0%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 0% Celing 0%
2nd Floor Partition 0% 2nd Floor Partition 0%
Terrace 50% Terrace 0%
Stone laying 0% Stone laying 0%
Painting 0% Painting 0%

ELECTRICAL 40% ELECTRICAL 40%


Wiring and Provision 20% Wiring and Provision 20%
Box setting and Piping 80% Box setting and Piping 80%
Fixtures (Outlet and Switch) 20% Fixtures (Outlet and Switch) 20%
Block 4 Unit 27 31% Block 4 Unit 28 31%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 41% STRUCTURAL 41%
Ground Floor 88% Ground Floor 88%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 50% Service Area and Comfort Room 50%
Carport and Septic tank 20% Carport and Septic tank 20%
2nd Floor 68% 2nd Floor 68%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 20% Shear Wall 20%
Comfort Room 50% Comfort Room 50%
Plumbing 50% Plumbing 50%
Ground (Plumbing ang Fixtures) 50% Ground (Plumbing ang Fixtures) 50%
2nd Floor (Plumbing and Fixtures) 50% 2nd Floor (Plumbing and Fixtures) 50%
Plastering and Clearing 10% Plastering and Clearing 10%
Roof 10% Roof 10%
Roof Framing 20% Roof Framing 20%
Roofing 0% Roofing 0%

ARCHITECTURAL 11% ARCHITECTURAL 11%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 0% Staircase (Contractor) 0%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 0% Celing 0%
2nd Floor Partition 0% 2nd Floor Partition 0%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 0% Painting 0%

ELECTRICAL 40% ELECTRICAL 40%


Wiring and Provision 20% Wiring and Provision 20%
Box setting and Piping 80% Box setting and Piping 80%
Fixtures (Outlet and Switch) 20% Fixtures (Outlet and Switch) 20%
Block 4 Unit 31 21% Block 4 Unit 32 21%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 40% STRUCTURAL 40%
Ground Floor 81% Ground Floor 81%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 25% Service Area and Comfort Room 25%
Carport and Septic tank 20% Carport and Septic tank 20%
2nd Floor 68% 2nd Floor 68%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 20% Shear Wall 20%
Comfort Room 50% Comfort Room 50%
Plumbing 50% Plumbing 50%
Ground (Plumbing ang Fixtures) 50% Ground (Plumbing ang Fixtures) 50%
2nd Floor (Plumbing and Fixtures) 50% 2nd Floor (Plumbing and Fixtures) 50%
Plastering and Clearing 10% Plastering and Clearing 10%
Roof 10% Roof 10%
Roof Framing 20% Roof Framing 20%
Roofing 0% Roofing 0%

ARCHITECTURAL 11% ARCHITECTURAL 11%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 0% Staircase (Contractor) 0%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 0% Celing 0%
2nd Floor Partition 0% 2nd Floor Partition 0%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 0% Painting 0%
ELECTRICAL 13% ELECTRICAL 13%
Wiring and Provision 0% Wiring and Provision 0%
Box setting and Piping 20% Box setting and Piping 20%
Fixtures (Outlet and Switch) 20% Fixtures (Outlet and Switch) 20%
Block 4 Unit 35 21% Block 4 Unit 36 21%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 40% STRUCTURAL 40%
Ground Floor 81% Ground Floor 81%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 25% Service Area and Comfort Room 25%
Carport and Septic tank 20% Carport and Septic tank 20%
2nd Floor 68% 2nd Floor 68%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 20% Shear Wall 20%
Comfort Room 50% Comfort Room 50%
Plumbing 50% Plumbing 50%
Ground (Plumbing ang Fixtures) 50% Ground (Plumbing ang Fixtures) 50%
2nd Floor (Plumbing and Fixtures) 50% 2nd Floor (Plumbing and Fixtures) 50%
Plastering and Clearing 10% Plastering and Clearing 10%
Roof 10% Roof 10%
Roof Framing 20% Roof Framing 20%
Roofing 0% Roofing 0%

ARCHITECTURAL 11% ARCHITECTURAL 11%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 0% Staircase (Contractor) 0%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 0% Celing 0%
2nd Floor Partition 0% 2nd Floor Partition 0%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 0% Painting 0%
ELECTRICAL 13% ELECTRICAL 13%
Wiring and Provision 0% Wiring and Provision 0%
Box setting and Piping 20% Box setting and Piping 20%
Fixtures (Outlet and Switch) 20% Fixtures (Outlet and Switch) 20%
Block 4 Unit 39 21% Block 4 Unit 40 4%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 40% STRUCTURAL 13%
Ground Floor 81% Ground Floor 75%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 25% Service Area and Comfort Room 0%
Carport and Septic tank 20% Carport and Septic tank 0%
2nd Floor 68% 2nd Floor 0%
Steel Deck 100% Steel Deck 0%
Slab 100% Slab 0%
Shear Wall 20% Shear Wall 0%
Comfort Room 50% Comfort Room 0%
Plumbing 50% Plumbing 0%
Ground (Plumbing ang Fixtures) 50% Ground (Plumbing ang Fixtures) 0%
2nd Floor (Plumbing and Fixtures) 50% 2nd Floor (Plumbing and Fixtures) 0%
Plastering and Clearing 10% Plastering and Clearing 0%
Roof 10% Roof 0%
Roof Framing 20% Roof Framing 0%
Roofing 0% Roofing 0%

ARCHITECTURAL 11% ARCHITECTURAL 0%


Doors 25% Doors 0%
Windows 25% Windows 0%
Staircase (Contractor) 0% Staircase (Contractor) 0%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 0% Celing 0%
2nd Floor Partition 0% 2nd Floor Partition 0%
Terrace 50% Terrace 0%
Stone laying 0% Stone laying 0%
Painting 0% Painting 0%

ELECTRICAL 13% ELECTRICAL 0%


Wiring and Provision 0% Wiring and Provision 0%
Box setting and Piping 20% Box setting and Piping 0%
Fixtures (Outlet and Switch) 20% Fixtures (Outlet and Switch) 0%
Block 4 Unit 21 35% Block 4 Unit 22 35%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 53% STRUCTURAL 53%
Ground Floor 88% Ground Floor 88%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 50% Service Area and Comfort Room 50%
Carport and Septic tank 20% Carport and Septic tank 20%
2nd Floor 88% 2nd Floor 88%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 50% Comfort Room 50%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 75% Ground (Plumbing ang Fixtures) 75%
2nd Floor (Plumbing and Fixtures) 75% 2nd Floor (Plumbing and Fixtures) 75%
Plastering and Clearing 10% Plastering and Clearing 10%
Roof 38% Roof 38%
Roof Framing 50% Roof Framing 50%
Roofing 25% Roofing 25%

ARCHITECTURAL 11% ARCHITECTURAL 11%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 0% Staircase (Contractor) 0%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 0% Celing 0%
2nd Floor Partition 0% 2nd Floor Partition 0%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 0% Painting 0%

ELECTRICAL 40% ELECTRICAL 40%


Wiring and Provision 20% Wiring and Provision 20%
Box setting and Piping 80% Box setting and Piping 80%
Fixtures (Outlet and Switch) 20% Fixtures (Outlet and Switch) 20%
Block 4 Unit 25 31% Block 4 Unit 26 31%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 41% STRUCTURAL 41%
Ground Floor 88% Ground Floor 88%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 50% Service Area and Comfort Room 50%
Carport and Septic tank 20% Carport and Septic tank 20%
2nd Floor 68% 2nd Floor 68%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 20% Shear Wall 20%
Comfort Room 50% Comfort Room 50%
Plumbing 50% Plumbing 50%
Ground (Plumbing ang Fixtures) 50% Ground (Plumbing ang Fixtures) 50%
2nd Floor (Plumbing and Fixtures) 50% 2nd Floor (Plumbing and Fixtures) 50%
Plastering and Clearing 10% Plastering and Clearing 10%
Roof 10% Roof 10%
Roof Framing 20% Roof Framing 20%
Roofing 0% Roofing 0%

ARCHITECTURAL 11% ARCHITECTURAL 11%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 0% Staircase (Contractor) 0%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 0% Celing 0%
2nd Floor Partition 0% 2nd Floor Partition 0%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 0% Painting 0%

ELECTRICAL 40% ELECTRICAL 40%


Wiring and Provision 20% Wiring and Provision 20%
Box setting and Piping 80% Box setting and Piping 80%
Fixtures (Outlet and Switch) 20% Fixtures (Outlet and Switch) 20%
Block 4 Unit 29 31% Block 4 Unit 30 31%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 41% STRUCTURAL 41%
Ground Floor 88% Ground Floor 88%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 50% Service Area and Comfort Room 50%
Carport and Septic tank 20% Carport and Septic tank 20%
2nd Floor 68% 2nd Floor 68%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 20% Shear Wall 20%
Comfort Room 50% Comfort Room 50%
Plumbing 50% Plumbing 50%
Ground (Plumbing ang Fixtures) 50% Ground (Plumbing ang Fixtures) 50%
2nd Floor (Plumbing and Fixtures) 50% 2nd Floor (Plumbing and Fixtures) 50%
Plastering and Clearing 10% Plastering and Clearing 10%
Roof 10% Roof 10%
Roof Framing 20% Roof Framing 20%
Roofing 0% Roofing 0%

ARCHITECTURAL 11% ARCHITECTURAL 11%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 0% Staircase (Contractor) 0%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 0% Celing 0%
2nd Floor Partition 0% 2nd Floor Partition 0%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 0% Painting 0%

ELECTRICAL 40% ELECTRICAL 40%


Wiring and Provision 20% Wiring and Provision 20%
Box setting and Piping 80% Box setting and Piping 80%
Fixtures (Outlet and Switch) 20% Fixtures (Outlet and Switch) 20%
Block 4 Unit 33 21% Block 4 Unit 34 21%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 40% STRUCTURAL 40%
Ground Floor 81% Ground Floor 81%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 25% Service Area and Comfort Room 25%
Carport and Septic tank 20% Carport and Septic tank 20%
2nd Floor 68% 2nd Floor 68%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 20% Shear Wall 20%
Comfort Room 50% Comfort Room 50%
Plumbing 50% Plumbing 50%
Ground (Plumbing ang Fixtures) 50% Ground (Plumbing ang Fixtures) 50%
2nd Floor (Plumbing and Fixtures) 50% 2nd Floor (Plumbing and Fixtures) 50%
Plastering and Clearing 10% Plastering and Clearing 10%
Roof 10% Roof 10%
Roof Framing 20% Roof Framing 20%
Roofing 0% Roofing 0%

ARCHITECTURAL 11% ARCHITECTURAL 11%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 0% Staircase (Contractor) 0%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 0% Celing 0%
2nd Floor Partition 0% 2nd Floor Partition 0%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 0% Painting 0%
ELECTRICAL 13% ELECTRICAL 13%
Wiring and Provision 0% Wiring and Provision 0%
Box setting and Piping 20% Box setting and Piping 20%
Fixtures (Outlet and Switch) 20% Fixtures (Outlet and Switch) 20%
Block 4 Unit 37 21% Block 4 Unit 38 21%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 40% STRUCTURAL 40%
Ground Floor 81% Ground Floor 81%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 25% Service Area and Comfort Room 25%
Carport and Septic tank 20% Carport and Septic tank 20%
2nd Floor 68% 2nd Floor 68%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 20% Shear Wall 20%
Comfort Room 50% Comfort Room 50%
Plumbing 50% Plumbing 50%
Ground (Plumbing ang Fixtures) 50% Ground (Plumbing ang Fixtures) 50%
2nd Floor (Plumbing and Fixtures) 50% 2nd Floor (Plumbing and Fixtures) 50%
Plastering and Clearing 10% Plastering and Clearing 10%
Roof 10% Roof 10%
Roof Framing 20% Roof Framing 20%
Roofing 0% Roofing 0%

ARCHITECTURAL 11% ARCHITECTURAL 11%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 0% Staircase (Contractor) 0%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 0% Celing 0%
2nd Floor Partition 0% 2nd Floor Partition 0%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 0% Painting 0%
ELECTRICAL 13% ELECTRICAL 13%
Wiring and Provision 0% Wiring and Provision 0%
Box setting and Piping 20% Box setting and Piping 20%
Fixtures (Outlet and Switch) 20% Fixtures (Outlet and Switch) 20%
2 Storey Residential Row House As of:
Note:
Projecting the general progress of the whole
DATE: August 17, 2022 project. This includes delays (lack of human
resources and Weather condition, etc...)
General Progress of the Project
Green Represents (Finished)
Red represents (Unfinished)

BLOCK 3 BLOCK 4 Structural Architectural Electrical


Unit No. Finish Work(%) Unit No. Finish Work(%)
1 42.00% 19 38.00%
2 69.00% 20 37.00%
3 70.00% 21 37.00%
4 63.00% 22 37.00%
5 63.00% 23 36.00%
6 64.00% 24 36.00% Percentage of the whole Project
7 62.00% 25 36.00% A 41.00%
8 61.00% 26 36.00% B 59.00%
9 61.00% 27 36.00%
10 61.00% 28 36.00% 2 Storey Residential Row House
11 57.00% 29 36.00%
12 50.00% 30 35.00%
13 48.00% 31 25.00%
14 47.00% 32 24.00%
41%
15 45.00% 33 24.00% A
16 44.00% 34 23.00% 59% B

17 40.00% 35 23.00%
18 39.00% 36 23.00%
37 23.00%
38 23.00%
39 23.00%
40 0.00%
Note:
2 Storey Residential Row House Projecting the general progress of the whole
project. This includes delays (lack of human
resources and Weather condition, etc...)
General Progress of the Project
Green Represents (Finished)
BLOCK 3 As of: Red represents (Unfinished)
Unit No. Finish Work(%)
Structural
Architectural Electrical DATE: August 17, 2022
1 0.00%
2 0.00%
3 0.00%
4 0.00% Structural Architectural Electrical
5 0.00%
6 0.00%
7 0.00%
8 0.00%
9 0.00%
10 0.00%
11 0.00% Percentage of the whole Project
12 0.00% A 0.00%
13 0.00% B 100.00%
14 0.00%
15 0.00% 2 Storey Residential Row House
16 0.00%
17 0.00%
18 0.00%

41%
A
59% B
LOT 49 42% LOT 50 69%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 72% STRUCTURAL 83%
Ground Floor 100% Ground Floor 100%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 100% Service Area and Comfort Room 100%
Carport and Septic tank 20% Carport and Septic tank 20%
2nd Floor 100% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 100%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 75% Ground (Plumbing ang Fixtures) 75%
2nd Floor (Plumbing and Fixtures) 75% 2nd Floor (Plumbing and Fixtures) 75%
Plastering and Clearing 75% Plastering and Clearing 100%
Roof 60% Roof 100%
Roof Framing 100% Roof Framing 100%
Roofing 20% Roofing 100%

ARCHITECTURAL 11% ARCHITECTURAL 40%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 0% Staircase (Contractor) 50%
Tile Works (Contractor) 0% Tile Works (Contractor) 90%
Celing 0% Celing 50%
2nd Floor Partition 0% 2nd Floor Partition 20%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 0% Painting 50%

ELECTRICAL 42% ELECTRICAL 83%


Wiring and Provision 0% Wiring and Provision 100%
Box setting and Piping 100% Box setting and Piping 100%
Fixtures (Outlet and Switch) 25% Fixtures (Outlet and Switch) 50%
LOT 53 63% LOT 54 64%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 83% STRUCTURAL 83%
Ground Floor 100% Ground Floor 100%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 100% Service Area and Comfort Room 100%
Carport and Septic tank 20% Carport and Septic tank 20%
2nd Floor 100% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 100%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 75% Ground (Plumbing ang Fixtures) 75%
2nd Floor (Plumbing and Fixtures) 75% 2nd Floor (Plumbing and Fixtures) 75%
Plastering and Clearing 100% Plastering and Clearing 100%
Roof 100% Roof 100%
Roof Framing 100% Roof Framing 100%
Roofing 100% Roofing 100%

ARCHITECTURAL 31% ARCHITECTURAL 33%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 50% Staircase (Contractor) 50%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 50% Celing 70%
2nd Floor Partition 25% 2nd Floor Partition 25%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 50% Painting 50%

ELECTRICAL 75% ELECTRICAL 75%


Wiring and Provision 100% Wiring and Provision 100%
Box setting and Piping 100% Box setting and Piping 100%
Fixtures (Outlet and Switch) 25% Fixtures (Outlet and Switch) 25%
LOT 57 61% LOT 58 61%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 83% STRUCTURAL 83%
Ground Floor 100% Ground Floor 100%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 100% Service Area and Comfort Room 100%
Carport and Septic tank 20% Carport and Septic tank 20%
2nd Floor 100% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 100%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 75% Ground (Plumbing ang Fixtures) 75%
2nd Floor (Plumbing and Fixtures) 75% 2nd Floor (Plumbing and Fixtures) 75%
Plastering and Clearing 100% Plastering and Clearing 100%
Roof 100% Roof 100%
Roof Framing 100% Roof Framing 100%
Roofing 100% Roofing 100%

ARCHITECTURAL 26% ARCHITECTURAL 0% 26%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 50% Staircase (Contractor) 50%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 20% Celing 20%
2nd Floor Partition 10% 2nd Floor Partition 10%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 50% Painting 50%

ELECTRICAL 75% ELECTRICAL 75%


Wiring and Provision 100% Wiring and Provision 100%
Box setting and Piping 100% Box setting and Piping 100%
Fixtures (Outlet and Switch) 25% Fixtures (Outlet and Switch) 25%
LOT 61 48% LOT 62 47%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 76% STRUCTURAL 74%
Ground Floor 100% Ground Floor 95%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 100% Service Area and Comfort Room 80%
Carport and Septic tank 20% Carport and Septic tank 20%
2nd Floor 100% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 100%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 75% Ground (Plumbing ang Fixtures) 75%
2nd Floor (Plumbing and Fixtures) 75% 2nd Floor (Plumbing and Fixtures) 75%
Plastering and Clearing 100% Plastering and Clearing 90%
Roof 63% Roof 63%
Roof Framing 100% Roof Framing 100%
Roofing 25% Roofing 25%

ARCHITECTURAL 18% ARCHITECTURAL 18%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 0% Staircase (Contractor) 0%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 50% Celing 50%
2nd Floor Partition 10% 2nd Floor Partition 10%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 0% Painting 0%
ELECTRICAL 50% ELECTRICAL 50%
Wiring and Provision 25% Wiring and Provision 25%
Box setting and Piping 100% Box setting and Piping 100%
Fixtures (Outlet and Switch) 25% Fixtures (Outlet and Switch) 25%
LOT 65 40% LOT 66 39%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 59% STRUCTURAL 59%
Ground Floor 88% Ground Floor 88%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 50% Service Area and Comfort Room 50%
Carport and Septic tank 20% Carport and Septic tank 20%
2nd Floor 100% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 100%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 75% Ground (Plumbing ang Fixtures) 75%
2nd Floor (Plumbing and Fixtures) 75% 2nd Floor (Plumbing and Fixtures) 75%
Plastering and Clearing 10% Plastering and Clearing 10%
Roof 63% Roof 63%
Roof Framing 100% Roof Framing 100%
Roofing 25% Roofing 25%

ARCHITECTURAL 15% ARCHITECTURAL 12%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 0% Staircase (Contractor) 0%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 25% Celing 0%
2nd Floor Partition 10% 2nd Floor Partition 10%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 0% Painting 0%
ELECTRICAL 47% ELECTRICAL 47%
Wiring and Provision 20% Wiring and Provision 20%
Box setting and Piping 100% Box setting and Piping 100%
Fixtures (Outlet and Switch) 20% Fixtures (Outlet and Switch) 20%
LOT 51 70% LOT 52 63%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 83% STRUCTURAL 83%
Ground Floor 100% Ground Floor 100%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 100% Service Area and Comfort Room 100%
Carport and Septic tank 20% Carport and Septic tank 20%
2nd Floor 100% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 100%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 75% Ground (Plumbing ang Fixtures) 75%
2nd Floor (Plumbing and Fixtures) 75% 2nd Floor (Plumbing and Fixtures) 75%
Plastering and Clearing 100% Plastering and Clearing 100%
Roof 100% Roof 100%
Roof Framing 100% Roof Framing 100%
Roofing 100% Roofing 100%

ARCHITECTURAL 52% ARCHITECTURAL 32%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 50% Staircase (Contractor) 50%
Tile Works (Contractor) 90% Tile Works (Contractor) 0%
Celing 100% Celing 70%
2nd Floor Partition 75% 2nd Floor Partition 20%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 50% Painting 50%

ELECTRICAL 75% ELECTRICAL 75%


Wiring and Provision 100% Wiring and Provision 100%
Box setting and Piping 100% Box setting and Piping 100%
Fixtures (Outlet and Switch) 25% Fixtures (Outlet and Switch) 25%
LOT 55 62% LOT 56 61%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 83% STRUCTURAL 83%
Ground Floor 100% Ground Floor 100%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 100% Service Area and Comfort Room 100%
Carport and Septic tank 20% Carport and Septic tank 20%
2nd Floor 100% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 100%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 75% Ground (Plumbing ang Fixtures) 75%
2nd Floor (Plumbing and Fixtures) 75% 2nd Floor (Plumbing and Fixtures) 75%
Plastering and Clearing 100% Plastering and Clearing 100%
Roof 100% Roof 100%
Roof Framing 100% Roof Framing 100%
Roofing 100% Roofing 100%

ARCHITECTURAL 27% ARCHITECTURAL 26%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 50% Staircase (Contractor) 50%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 25% Celing 25%
2nd Floor Partition 20% 2nd Floor Partition 10%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 50% Painting 50%

ELECTRICAL 75% ELECTRICAL 75%


Wiring and Provision 100% Wiring and Provision 100%
Box setting and Piping 100% Box setting and Piping 100%
Fixtures (Outlet and Switch) 25% Fixtures (Outlet and Switch) 25%
LOT 59 57% LOT 60 50%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 83% STRUCTURAL 76%
Ground Floor 100% Ground Floor 100%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 100% Service Area and Comfort Room 100%
Carport and Septic tank 20% Carport and Septic tank 20%
2nd Floor 100% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 100%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 75% Ground (Plumbing ang Fixtures) 75%
2nd Floor (Plumbing and Fixtures) 75% 2nd Floor (Plumbing and Fixtures) 75%
Plastering and Clearing 100% Plastering and Clearing 100%
Roof 100% Roof 63%
Roof Framing 100% Roof Framing 100%
Roofing 100% Roofing 25%

ARCHITECTURAL 17% ARCHITECTURAL 18%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 0% Staircase (Contractor) 0%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 20% Celing 50%
2nd Floor Partition 10% 2nd Floor Partition 10%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 20% Painting 0%

ELECTRICAL 72% ELECTRICAL 55%


Wiring and Provision 90% Wiring and Provision 40%
Box setting and Piping 100% Box setting and Piping 100%
Fixtures (Outlet and Switch) 25% Fixtures (Outlet and Switch) 25%
LOT 63 45% LOT 64 44%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 71% STRUCTURAL 71%
Ground Floor 100% Ground Floor 88%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 100% Service Area and Comfort Room 50%
Carport and Septic tank 20% Carport and Septic tank 20%
2nd Floor 88% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 50% Comfort Room 100%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 75% Ground (Plumbing ang Fixtures) 75%
2nd Floor (Plumbing and Fixtures) 75% 2nd Floor (Plumbing and Fixtures) 75%
Plastering and Clearing 80% Plastering and Clearing 80%
Roof 63% Roof 63%
Roof Framing 100% Roof Framing 100%
Roofing 25% Roofing 25%

ARCHITECTURAL 18% ARCHITECTURAL 15%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 0% Staircase (Contractor) 0%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 50% Celing 25%
2nd Floor Partition 10% 2nd Floor Partition 10%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 0% Painting 0%
ELECTRICAL 47% ELECTRICAL 47%
Wiring and Provision 20% Wiring and Provision 20%
Box setting and Piping 100% Box setting and Piping 100%
Fixtures (Outlet and Switch) 20% Fixtures (Outlet and Switch) 20%

INDIVIDUAL PROGRESS OF BLOCK 3


BLOCK 3 LOT (49 - 66)
LOT 68 38% LOT 69 37%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 61% STRUCTURAL 60%
Ground Floor 88% Ground Floor 88%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 50% Service Area and Comfort Room 50%
Carport and Septic tank 20% Carport and Septic tank 20%
2nd Floor 100% 2nd Floor 94%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 75%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 75% Ground (Plumbing ang Fixtures) 75%
2nd Floor (Plumbing and Fixtures) 75% 2nd Floor (Plumbing and Fixtures) 75%
Plastering and Clearing 20% Plastering and Clearing 20%
Roof 63% Roof 63%
Roof Framing 100% Roof Framing 100%
Roofing 25% Roofing 25%

ARCHITECTURAL 12% ARCHITECTURAL 11%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 0% Staircase (Contractor) 0%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 0% Celing 0%
2nd Floor Partition 10% 2nd Floor Partition 0%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 0% Painting 0%

ELECTRICAL 40% ELECTRICAL 40%


Wiring and Provision 20% Wiring and Provision 20%
Box setting and Piping 80% Box setting and Piping 80%
Fixtures (Outlet and Switch) 20% Fixtures (Outlet and Switch) 20%
LOT 72 36% LOT 73 36%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 57% STRUCTURAL 57%
Ground Floor 88% Ground Floor 88%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 50% Service Area and Comfort Room 50%
Carport and Septic tank 20% Carport and Septic tank 20%
2nd Floor 88% 2nd Floor 88%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 50% Comfort Room 50%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 75% Ground (Plumbing ang Fixtures) 75%
2nd Floor (Plumbing and Fixtures) 75% 2nd Floor (Plumbing and Fixtures) 75%
Plastering and Clearing 20% Plastering and Clearing 20%
Roof 50% Roof 50%
Roof Framing 100% Roof Framing 100%
Roofing 0% Roofing 0%

ARCHITECTURAL 11% ARCHITECTURAL 11%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 0% Staircase (Contractor) 0%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 0% Celing 0%
2nd Floor Partition 0% 2nd Floor Partition 0%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 0% Painting 0%

ELECTRICAL 40% ELECTRICAL 40%


Wiring and Provision 20% Wiring and Provision 20%
Box setting and Piping 80% Box setting and Piping 80%
Fixtures (Outlet and Switch) 20% Fixtures (Outlet and Switch) 20%
LOT 76 36% LOT 77 36%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 57% STRUCTURAL 57%
Ground Floor 88% Ground Floor 88%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 50% Service Area and Comfort Room 50%
Carport and Septic tank 20% Carport and Septic tank 20%
2nd Floor 88% 2nd Floor 88%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 50% Comfort Room 50%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 75% Ground (Plumbing ang Fixtures) 75%
2nd Floor (Plumbing and Fixtures) 75% 2nd Floor (Plumbing and Fixtures) 75%
Plastering and Clearing 20% Plastering and Clearing 20%
Roof 50% Roof 50%
Roof Framing 100% Roof Framing 100%
Roofing 0% Roofing 0%

ARCHITECTURAL 11% ARCHITECTURAL 11%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 0% Staircase (Contractor) 0%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 0% Celing 0%
2nd Floor Partition 0% 2nd Floor Partition 0%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 0% Painting 0%

ELECTRICAL 40% ELECTRICAL 40%


Wiring and Provision 20% Wiring and Provision 20%
Box setting and Piping 80% Box setting and Piping 80%
Fixtures (Outlet and Switch) 20% Fixtures (Outlet and Switch) 20%
LOT 80 25% LOT 81 24%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 52% STRUCTURAL 47%
Ground Floor 81% Ground Floor 81%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 25% Service Area and Comfort Room 25%
Carport and Septic tank 20% Carport and Septic tank 20%
2nd Floor 88% 2nd Floor 88%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 50% Comfort Room 50%
Plumbing 50% Plumbing 50%
Ground (Plumbing ang Fixtures) 50% Ground (Plumbing ang Fixtures) 50%
2nd Floor (Plumbing and Fixtures) 50% 2nd Floor (Plumbing and Fixtures) 50%
Plastering and Clearing 20% Plastering and Clearing 20%
Roof 50% Roof 25%
Roof Framing 100% Roof Framing 50%
Roofing 0% Roofing 0%

ARCHITECTURAL 11% ARCHITECTURAL 11%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 0% Staircase (Contractor) 0%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 0% Celing 0%
2nd Floor Partition 0% 2nd Floor Partition 0%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 0% Painting 0%
ELECTRICAL 13% ELECTRICAL 13%
Wiring and Provision 0% Wiring and Provision 0%
Box setting and Piping 20% Box setting and Piping 20%
Fixtures (Outlet and Switch) 20% Fixtures (Outlet and Switch) 20%
LOT 84 23% LOT 85 23%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 45% STRUCTURAL 45%
Ground Floor 81% Ground Floor 81%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 25% Service Area and Comfort Room 25%
Carport and Septic tank 20% Carport and Septic tank 20%
2nd Floor 88% 2nd Floor 88%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 50% Comfort Room 50%
Plumbing 50% Plumbing 50%
Ground (Plumbing ang Fixtures) 50% Ground (Plumbing ang Fixtures) 50%
2nd Floor (Plumbing and Fixtures) 50% 2nd Floor (Plumbing and Fixtures) 50%
Plastering and Clearing 20% Plastering and Clearing 20%
Roof 13% Roof 13%
Roof Framing 25% Roof Framing 25%
Roofing 0% Roofing 0%

ARCHITECTURAL 11% ARCHITECTURAL 11%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 0% Staircase (Contractor) 0%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 0% Celing 0%
2nd Floor Partition 0% 2nd Floor Partition 0%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 0% Painting 0%
ELECTRICAL 13% ELECTRICAL 13%
Wiring and Provision 0% Wiring and Provision 0%
Box setting and Piping 20% Box setting and Piping 20%
Fixtures (Outlet and Switch) 20% Fixtures (Outlet and Switch) 20%
LOT 88 23% LOT 89 0%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 45% STRUCTURAL 0%
Ground Floor 81% Ground Floor 0%
Foundation 100% Foundation 0%
Flooring 100% Flooring 0%
Walling 100% Walling 0%
Service Area and Comfort Room 25% Service Area and Comfort Room 0%
Carport and Septic tank 20% Carport and Septic tank 0%
2nd Floor 88% 2nd Floor 0%
Steel Deck 100% Steel Deck 0%
Slab 100% Slab 0%
Shear Wall 100% Shear Wall 0%
Comfort Room 50% Comfort Room 0%
Plumbing 50% Plumbing 0%
Ground (Plumbing ang Fixtures) 50% Ground (Plumbing ang Fixtures) 0%
2nd Floor (Plumbing and Fixtures) 50% 2nd Floor (Plumbing and Fixtures) 0%
Plastering and Clearing 20% Plastering and Clearing 0%
Roof 13% Roof 0%
Roof Framing 25% Roof Framing 0%
Roofing 0% Roofing 0%

ARCHITECTURAL 11% ARCHITECTURAL 0%


Doors 25% Doors 0%
Windows 25% Windows 0%
Staircase (Contractor) 0% Staircase (Contractor) 0%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 0% Celing 0%
2nd Floor Partition 0% 2nd Floor Partition 0%
Terrace 50% Terrace 0%
Stone laying 0% Stone laying 0%
Painting 0% Painting 0%

ELECTRICAL 13% ELECTRICAL 0%


Wiring and Provision 0% Wiring and Provision 0%
Box setting and Piping 20% Box setting and Piping 0%
Fixtures (Outlet and Switch) 20% Fixtures (Outlet and Switch) 0%
LOT 70 37% LOT 71 37%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 59% STRUCTURAL 59%
Ground Floor 88% Ground Floor 88%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 50% Service Area and Comfort Room 50%
Carport and Septic tank 20% Carport and Septic tank 20%
2nd Floor 88% 2nd Floor 88%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 50% Comfort Room 50%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 75% Ground (Plumbing ang Fixtures) 75%
2nd Floor (Plumbing and Fixtures) 75% 2nd Floor (Plumbing and Fixtures) 75%
Plastering and Clearing 20% Plastering and Clearing 20%
Roof 63% Roof 63%
Roof Framing 100% Roof Framing 100%
Roofing 25% Roofing 25%

ARCHITECTURAL 11% ARCHITECTURAL 11%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 0% Staircase (Contractor) 0%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 0% Celing 0%
2nd Floor Partition 0% 2nd Floor Partition 0%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 0% Painting 0%

ELECTRICAL 40% ELECTRICAL 40%


Wiring and Provision 20% Wiring and Provision 20%
Box setting and Piping 80% Box setting and Piping 80%
Fixtures (Outlet and Switch) 20% Fixtures (Outlet and Switch) 20%
LOT 74 36% LOT 75 36%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 57% STRUCTURAL 57%
Ground Floor 88% Ground Floor 88%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 50% Service Area and Comfort Room 50%
Carport and Septic tank 20% Carport and Septic tank 20%
2nd Floor 88% 2nd Floor 88%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 50% Comfort Room 50%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 75% Ground (Plumbing ang Fixtures) 75%
2nd Floor (Plumbing and Fixtures) 75% 2nd Floor (Plumbing and Fixtures) 75%
Plastering and Clearing 20% Plastering and Clearing 20%
Roof 50% Roof 50%
Roof Framing 100% Roof Framing 100%
Roofing 0% Roofing 0%

ARCHITECTURAL 11% ARCHITECTURAL 11%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 0% Staircase (Contractor) 0%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 0% Celing 0%
2nd Floor Partition 0% 2nd Floor Partition 0%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 0% Painting 0%

ELECTRICAL 40% ELECTRICAL 40%


Wiring and Provision 20% Wiring and Provision 20%
Box setting and Piping 80% Box setting and Piping 80%
Fixtures (Outlet and Switch) 20% Fixtures (Outlet and Switch) 20%
LOT 78 36% LOT 79 35%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 57% STRUCTURAL 53%
Ground Floor 88% Ground Floor 88%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 50% Service Area and Comfort Room 50%
Carport and Septic tank 20% Carport and Septic tank 20%
2nd Floor 88% 2nd Floor 88%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 50% Comfort Room 50%
Plumbing 75% Plumbing 50%
Ground (Plumbing ang Fixtures) 75% Ground (Plumbing ang Fixtures) 50%
2nd Floor (Plumbing and Fixtures) 75% 2nd Floor (Plumbing and Fixtures) 50%
Plastering and Clearing 20% Plastering and Clearing 20%
Roof 50% Roof 50%
Roof Framing 100% Roof Framing 100%
Roofing 0% Roofing 0%

ARCHITECTURAL 11% ARCHITECTURAL 11%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 0% Staircase (Contractor) 0%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 0% Celing 0%
2nd Floor Partition 0% 2nd Floor Partition 0%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 0% Painting 0%

ELECTRICAL 40% ELECTRICAL 40%


Wiring and Provision 20% Wiring and Provision 20%
Box setting and Piping 80% Box setting and Piping 80%
Fixtures (Outlet and Switch) 20% Fixtures (Outlet and Switch) 20%
LOT 82 24% LOT 83 23%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 47% STRUCTURAL 45%
Ground Floor 81% Ground Floor 81%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 25% Service Area and Comfort Room 25%
Carport and Septic tank 20% Carport and Septic tank 20%
2nd Floor 88% 2nd Floor 88%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 50% Comfort Room 50%
Plumbing 50% Plumbing 50%
Ground (Plumbing ang Fixtures) 50% Ground (Plumbing ang Fixtures) 50%
2nd Floor (Plumbing and Fixtures) 50% 2nd Floor (Plumbing and Fixtures) 50%
Plastering and Clearing 20% Plastering and Clearing 20%
Roof 25% Roof 13%
Roof Framing 50% Roof Framing 25%
Roofing 0% Roofing 0%

ARCHITECTURAL 11% ARCHITECTURAL 11%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 0% Staircase (Contractor) 0%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 0% Celing 0%
2nd Floor Partition 0% 2nd Floor Partition 0%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 0% Painting 0%
ELECTRICAL 13% ELECTRICAL 13%
Wiring and Provision 0% Wiring and Provision 0%
Box setting and Piping 20% Box setting and Piping 20%
Fixtures (Outlet and Switch) 20% Fixtures (Outlet and Switch) 20%
LOT 86 23% LOT 87 23%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 45% STRUCTURAL 45%
Ground Floor 81% Ground Floor 81%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 25% Service Area and Comfort Room 25%
Carport and Septic tank 20% Carport and Septic tank 20%
2nd Floor 88% 2nd Floor 88%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 50% Comfort Room 50%
Plumbing 50% Plumbing 50%
Ground (Plumbing ang Fixtures) 50% Ground (Plumbing ang Fixtures) 50%
2nd Floor (Plumbing and Fixtures) 50% 2nd Floor (Plumbing and Fixtures) 50%
Plastering and Clearing 20% Plastering and Clearing 20%
Roof 13% Roof 13%
Roof Framing 25% Roof Framing 25%
Roofing 0% Roofing 0%

ARCHITECTURAL 11% ARCHITECTURAL 11%


Doors 25% Doors 25%
Windows 25% Windows 25%
Staircase (Contractor) 0% Staircase (Contractor) 0%
Tile Works (Contractor) 0% Tile Works (Contractor) 0%
Celing 0% Celing 0%
2nd Floor Partition 0% 2nd Floor Partition 0%
Terrace 50% Terrace 50%
Stone laying 0% Stone laying 0%
Painting 0% Painting 0%
ELECTRICAL 13% ELECTRICAL 13%
Wiring and Provision 0% Wiring and Provision 0%
Box setting and Piping 20% Box setting and Piping 20%
Fixtures (Outlet and Switch) 20% Fixtures (Outlet and Switch) 20%

INDIVIDUAL PROGRESS OF BLOCK 3


BLOCK 3 LOT (68 - 89)
2 Storey Residential Row House
As of:
General Progress of the Project AUGUST 16, 2022
BLOCK 3 Finish Work (Per Week) Note:
Lot No. Structural Architectural Electrical Previos Current Progress Projecting the general progress of the
whole project. This includes delays (lack
49 72% 11% 42% 42.00% 72.00% of human resources and Weather
50 83% 40% 83.00% 69.00% condition, etc...)
51 83% 52% 75.00% 70.00%
Green Represents (Finished)
52 83% 32% 75.00% 63.00% Red represents (Unfinished)
53 83% 31% 75.00% 63.00%
54 83% 33% 75.00% 63.00%
55 83% 27% 75.00% 62.00%
56 83% 26% 75.00% 61.00%
57 83% 26% 75.00% 61.00%
58 83% 26% 75.00% 61.00%
59 83% 17% 72.00% 57.00%
60 76% 18% 55.00% 50.00%
61 76% 18% 50.00% 48.00% Sector percentage of the project
62 74% 18% 50.00% 47.00% Structural Architectural Electrical
63 71% 18% 47.00% 45.00% 62.00% 17.00% 44.00%
64 71% 15% 47.00% 44.00%
65 59% 15% 47.00% 40.00%
66 59% 12% 47.00% 39.00%

BLOCK 3 Finish Work (Per Week)


Lot No. Structural Architectural Electrical Previos Current Progress
68 61% 12% 40% 38.00% Percentage of the whole Project
69 60% 11% 40% 37.00% A 40.80%
70 59% 11% 40% 37.00% B 59.200%
71 59% 11% 40% 37.00%
72 57% 11% 40% 36.00%
73 57% 11% 40% 36.00% 2 Storey Residential Row
74 57% 11% 40% 36.00% House
75 57% 11% 40% 36.00%
76 57% 11% 40% 36.00%
77 57% 11% 40% 36.00%
41%
78 57% 11.00% 40% 36.00%
59%
79 53% 11.00% 40% 35.00%
80 52% 11% 45% 25.00%
81 47% 11% 13% 24.00%
82 47% 11% 13% 24.00%
83 45% 11% 13% 23.00%
A B
84 45% 11% 13% 23.00%
85 45% 11% 13% 23.00%
86 45% 11% 13% 23.00%
87 45% 11% 13% 23.00%
88 45% 11% 13% 23.00%
89 0% 0% 0% 0.00%
ck
2 Storey Residential Row House
General Progress of the Project
BLOCK 3
Current Finish Work (August 17 - 23, 2022) Previous Finish Work (June 03 - August 16, 2022) As of: AUGUST 17 - 23, 2022
Lot No. Structural Architectural Electrical Finish Work(%) Structural Architectural Electrical Finish Work(%) General Progress(+,-)
49 72.00% 11.00% 42.00% 42.00% 57% 11% 42% 37.00% 5.00%
50 83.00% 40.00% 83.00% 69.00% 79% 24% 83.00% 62.00% 7.00%
51 83.00% 52.00% 75.00% 70.00% 79% 34% 75.00% 63.00% 7.00%
52 83.00% 32.00% 75.00% 63.00% 79% 21% 75.00% 58.00% 5.00%
53 83.00% 31.00% 75.00% 63.00% 79% 17% 75.00% 57.00% 6.00%
54 83.00% 33.00% 75.00% 64.00% 79% 22% 75.00% 59.00% 5.00%
55 83.00% 27.00% 75.00% 62.00% 79% 16% 75.00% 57.00% 5.00%
56 83.00% 26.00% 75.00% 61.00% 79% 14% 75.00% 56.00% 5.00%
57 83.00% 26.00% 75.00% 61.00% 79% 16% 75.00% 57.00% 4.00%
58 83.00% 26.00% 75.00% 61.00% 78% 13% 75.00% 55.00% 6.00%
59 83.00% 17.00% 72.00% 57.00% 71% 14% 72.00% 52.00% 5.00%
60 76.00% 18.00% 55.00% 50.00% 63% 12% 55.00% 43.00% 7.00%
61 76.00% 18.00% 50.00% 48.00% 58% 15% 48.00% 40.00% 8.00%
62 74.00% 18.00% 50.00% 47.00% 56% 12% 50.00% 39.00% 8.00%
63 71.00% 18.00% 47.00% 45.00% 54% 12% 47.00% 38.00% 7.00%
64 71.00% 15.00% 47.00% 44.00% 56% 12% 47.00% 38.00% 6.00%
65 59.00% 15.00% 47.00% 40.00% 56% 12% 47.00% 38.00% 2.00%
66 59.00% 12.00% 47.00% 39.00% 56% 12% 47.00% 38.00% 1.00%

Note:
Projecting the general progress of the whole project. This
includes delays:
* Lack of Human power
* Weather Condition (Heavy Rainfall)
* Unable to provide some Parts of the Unit(Pre-Cast)

Green Represents (Finished Work)


Red Represents (Unfinished Work)
`
Current Finish Work (August 17 - 23, 2022) Previous Finish Work (June 03 - August 16, 2022) As of: AUGUST 17 - 23, 2022
Lot No. Structural Architectural Electrical Finish Work(%) Structural Architectural Electrical Finish Work(%) General Progress(+,-)
68 61.00% 12.00% 40.00% 38.00% 59.00% 11.00% 40.00% 37.00% 1.00%
69 60.00% 11.00% 40.00% 37.00% 53.00% 11.00% 40.00% 35.00% 2.00%
70 59.00% 11.00% 40.00% 37.00% 53.00% 11.00% 40.00% 35.00% 2.00%
71 59.00% 11.00% 40.00% 37.00% 53.00% 11.00% 40.00% 35.00% 2.00%
72 57.00% 11.00% 40.00% 36.00% 47.00% 11.00% 40.00% 33.00% 3.00%
73 57.00% 11.00% 40.00% 36.00% 47.00% 11.00% 40.00% 33.00% 3.00%
74 57.00% 11.00% 40.00% 36.00% 41.00% 11.00% 40.00% 31.00% 5.00%
75 57.00% 11.00% 40.00% 36.00% 41.00% 11.00% 40.00% 31.00% 5.00%
76 57.00% 11.00% 40.00% 36.00% 41.00% 11.00% 40.00% 31.00% 5.00%
77 57.00% 11.00% 40.00% 36.00% 41.00% 11.00% 40.00% 31.00% 5.00%
78 57.00% 11.00% 40.00% 36.00% 41.00% 11.00% 40.00% 31.00% 5.00%
79 53.00% 11.00% 40.00% 35.00% 41.00% 11.00% 40.00% 31.00% 4.00%
80 52.00% 11.00% 45.00% 36.00% 40.00% 11.00% 40.00% 30.00% 6.00%
81 47.00% 11.00% 13.00% 24.00% 40.00% 11.00% 13.00% 21.00% 3.00%
82 47.00% 11.00% 13.00% 24.00% 40.00% 11.00% 13.00% 21.00% 3.00%
83 45.00% 11.00% 13.00% 23.00% 40.00% 11.00% 13.00% 21.00% 2.00%
84 45.00% 11.00% 13.00% 23.00% 40.00% 11.00% 13.00% 21.00% 2.00%
85 45.00% 11.00% 13.00% 23.00% 40.00% 11.00% 13.00% 21.00% 2.00%
86 45.00% 11.00% 13.00% 23.00% 40.00% 11.00% 13.00% 21.00% 2.00%
87 45.00% 11.00% 13.00% 23.00% 40.00% 11.00% 13.00% 21.00% 2.00%
88 45.00% 11.00% 13.00% 23.00% 40.00% 11.00% 13.00% 21.00% 2.00%
89 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

SECTOR PERCENTAGE OF THE PROJECT 2 Storey Residential Row House


BLOCK 3
Structural Architectural Electrical

62% 17% 44.00% 41%

59%
A 41%
B 59.00%
59%

General Progress per Department (+,-) General Progress per Department (+,-)
Lot No. Structural Architectural Electrical Lot No. Structural Architectural Electrical
49 15.00% 0.00% 0.00% 68 2.00% 1.00% 0.00%
50 4.00% 16.00% 0.00% 69 7.00% 0.00% 0.00%
51 4.00% 18.00% 0.00% 70 6.00% 0.00% 0.00%
52 4.00% 11.00% 0.00% 71 6.00% 0.00% 0.00%
53 4.00% 14.00% 0.00% 72 10.00% 0.00% 0.00%
54 4.00% 11.00% 0.00% 73 10.00% 0.00% 0.00%
55 4.00% 11.00% 0.00% 74 16.00% 0.00% 0.00%
56 4.00% 12.00% 0.00% 75 16.00% 0.00% 0.00%
57 4.00% 10.00% 0.00% 76 16.00% 0.00% 0.00%
58 5.00% 13.00% 0.00% 77 16.00% 0.00% 0.00%
59 12.00% 3.00% 0.00% 78 16.00% 0.00% 0.00%
60 13.00% 6.00% 0.00% 79 12.00% 0.00% 0.00%
61 18.00% 3.00% 2.00% 80 12.00% 0.00% 5.00%
62 18.00% 6.00% 0.00% 81 7.00% 0.00% 0.00%
63 17.00% 6.00% 0.00% 82 7.00% 0.00% 0.00%
64 15.00% 3.00% 0.00% 83 5.00% 0.00% 0.00%
65 3.00% 3.00% 0.00% 84 5.00% 0.00% 0.00%
66 3.00% 0.00% 0.00% 85 5.00% 0.00% 0.00%
86 5.00% 0.00% 0.00%
87 5.00% 0.00% 0.00%
88 5.00% 0.00% 0.00%
89 0.00% 0.00% 0.00%

You might also like