Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 57% STRUCTURAL 79%
Ground Floor 88% Ground Floor 100%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 50% Service Area and Comfort Room 100%
Carport and Septic tank 0% Carport and Septic tank 0%
2nd Floor 94% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 75% Comfort Room 100%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 75% Ground (Plumbing ang Fixtures) 75%
2nd Floor (Plumbing and Fixtures) 75% 2nd Floor (Plumbing and Fixtures) 75%
Plastering and Clearing 25% Plastering and Clearing 100%
Roof 60% Roof 100%
Roof Framing 100% Roof Framing 100%
Roofing 20% Roofing 100%
17 40.00% 35 23.00%
18 39.00% 36 23.00%
37 23.00%
38 23.00%
39 23.00%
40 0.00%
Note:
2 Storey Residential Row House Projecting the general progress of the whole
project. This includes delays (lack of human
resources and Weather condition, etc...)
General Progress of the Project
Green Represents (Finished)
BLOCK 3 As of: Red represents (Unfinished)
Unit No. Finish Work(%)
Structural
Architectural Electrical DATE: August 17, 2022
1 0.00%
2 0.00%
3 0.00%
4 0.00% Structural Architectural Electrical
5 0.00%
6 0.00%
7 0.00%
8 0.00%
9 0.00%
10 0.00%
11 0.00% Percentage of the whole Project
12 0.00% A 0.00%
13 0.00% B 100.00%
14 0.00%
15 0.00% 2 Storey Residential Row House
16 0.00%
17 0.00%
18 0.00%
41%
A
59% B
LOT 49 42% LOT 50 69%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 72% STRUCTURAL 83%
Ground Floor 100% Ground Floor 100%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 100% Service Area and Comfort Room 100%
Carport and Septic tank 20% Carport and Septic tank 20%
2nd Floor 100% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 100%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 75% Ground (Plumbing ang Fixtures) 75%
2nd Floor (Plumbing and Fixtures) 75% 2nd Floor (Plumbing and Fixtures) 75%
Plastering and Clearing 75% Plastering and Clearing 100%
Roof 60% Roof 100%
Roof Framing 100% Roof Framing 100%
Roofing 20% Roofing 100%
Note:
Projecting the general progress of the whole project. This
includes delays:
* Lack of Human power
* Weather Condition (Heavy Rainfall)
* Unable to provide some Parts of the Unit(Pre-Cast)
59%
A 41%
B 59.00%
59%
General Progress per Department (+,-) General Progress per Department (+,-)
Lot No. Structural Architectural Electrical Lot No. Structural Architectural Electrical
49 15.00% 0.00% 0.00% 68 2.00% 1.00% 0.00%
50 4.00% 16.00% 0.00% 69 7.00% 0.00% 0.00%
51 4.00% 18.00% 0.00% 70 6.00% 0.00% 0.00%
52 4.00% 11.00% 0.00% 71 6.00% 0.00% 0.00%
53 4.00% 14.00% 0.00% 72 10.00% 0.00% 0.00%
54 4.00% 11.00% 0.00% 73 10.00% 0.00% 0.00%
55 4.00% 11.00% 0.00% 74 16.00% 0.00% 0.00%
56 4.00% 12.00% 0.00% 75 16.00% 0.00% 0.00%
57 4.00% 10.00% 0.00% 76 16.00% 0.00% 0.00%
58 5.00% 13.00% 0.00% 77 16.00% 0.00% 0.00%
59 12.00% 3.00% 0.00% 78 16.00% 0.00% 0.00%
60 13.00% 6.00% 0.00% 79 12.00% 0.00% 0.00%
61 18.00% 3.00% 2.00% 80 12.00% 0.00% 5.00%
62 18.00% 6.00% 0.00% 81 7.00% 0.00% 0.00%
63 17.00% 6.00% 0.00% 82 7.00% 0.00% 0.00%
64 15.00% 3.00% 0.00% 83 5.00% 0.00% 0.00%
65 3.00% 3.00% 0.00% 84 5.00% 0.00% 0.00%
66 3.00% 0.00% 0.00% 85 5.00% 0.00% 0.00%
86 5.00% 0.00% 0.00%
87 5.00% 0.00% 0.00%
88 5.00% 0.00% 0.00%
89 0.00% 0.00% 0.00%