You are on page 1of 30

LOT 48 64% LOT 49 64%

Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 100% STRUCTURAL 100%
Ground Floor 100% Ground Floor 100%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 100% Service Area and Comfort Room 100%
Carport and Septic tank 100% Carport and Septic tank 100%
2nd Floor 100% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 100%
Plumbing 100% Plumbing 100%
Ground (Plumbing ang Fixtures) 100% Ground (Plumbing ang Fixtures) 100%
2nd Floor (Plumbing and Fixtures) 100% 2nd Floor (Plumbing and Fixtures) 100%
Plastering and Clearing 100% Plastering and Clearing 100%
Roof 100% Roof 100%
Roof Framing 100% Roof Framing 100%
Roofing 100% Roofing 100%

ARCHITECTURAL 0% ARCHITECTURAL 0%
Doors Doors
Windows Windows
Staircase (Contractor) Staircase (Contractor)
Tile Works (Contractor) Tile Works (Contractor)
Celing Celing
2nd Floor Partition 2nd Floor Partition
Terrace Terrace
Stone laying Stone laying
Painting Painting

ELECTRICAL 92% ELECTRICAL 92%


Wiring and Provision 100% Wiring and Provision 100%
Box setting and Piping 100% Box setting and Piping 100%
Fixtures (Outlet and Switch) 75% Fixtures (Outlet and Switch) 75%
LOT 52 64% LOT 53 64%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 100% STRUCTURAL 100%
Ground Floor 100% Ground Floor 100%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 100% Service Area and Comfort Room 100%
Carport and Septic tank 100% Carport and Septic tank 100%
2nd Floor 100% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 100%
Plumbing 100% Plumbing 100%
Ground (Plumbing ang Fixtures) 100% Ground (Plumbing ang Fixtures) 100%
2nd Floor (Plumbing and Fixtures) 100% 2nd Floor (Plumbing and Fixtures) 100%
Plastering and Clearing 100% Plastering and Clearing 100%
Roof 100% Roof 100%
Roof Framing 100% Roof Framing 100%
Roofing 100% Roofing 100%

ARCHITECTURAL 0% ARCHITECTURAL 0%
Doors Doors
Windows Windows
Staircase (Contractor) Staircase (Contractor)
Tile Works (Contractor) Tile Works (Contractor)
Celing Celing
2nd Floor Partition 2nd Floor Partition
Terrace Terrace
Stone laying Stone laying
Painting Painting

ELECTRICAL 92% ELECTRICAL 92%


Wiring and Provision 100% Wiring and Provision 100%
Box setting and Piping 100% Box setting and Piping 100%
Fixtures (Outlet and Switch) 75% Fixtures (Outlet and Switch) 75%
LOT 56 64% LOT 57 64%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 100% STRUCTURAL 100%
Ground Floor 100% Ground Floor 100%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 100% Service Area and Comfort Room 100%
Carport and Septic tank 100% Carport and Septic tank 100%
2nd Floor 100% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 100%
Plumbing 100% Plumbing 100%
Ground (Plumbing ang Fixtures) 100% Ground (Plumbing ang Fixtures) 100%
2nd Floor (Plumbing and Fixtures) 100% 2nd Floor (Plumbing and Fixtures) 100%
Plastering and Clearing 100% Plastering and Clearing 100%
Roof 100% Roof 100%
Roof Framing 100% Roof Framing 100%
Roofing 100% Roofing 100%

ARCHITECTURAL 0% ARCHITECTURAL 0%
Doors Doors
Windows Windows
Staircase (Contractor) Staircase (Contractor)
Tile Works (Contractor) Tile Works (Contractor)
Celing Celing
2nd Floor Partition 2nd Floor Partition
Terrace Terrace
Stone laying Stone laying
Painting Painting

ELECTRICAL 92% ELECTRICAL 92%


Wiring and Provision 100% Wiring and Provision 100%
Box setting and Piping 100% Box setting and Piping 100%
Fixtures (Outlet and Switch) 75% Fixtures (Outlet and Switch) 75%
LOT 60 64% LOT 61 64%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 100% STRUCTURAL 100%
Ground Floor 100% Ground Floor 100%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 100% Service Area and Comfort Room 100%
Carport and Septic tank 100% Carport and Septic tank 100%
2nd Floor 100% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 100%
Plumbing 100% Plumbing 100%
Ground (Plumbing ang Fixtures) 100% Ground (Plumbing ang Fixtures) 100%
2nd Floor (Plumbing and Fixtures) 100% 2nd Floor (Plumbing and Fixtures) 100%
Plastering and Clearing 100% Plastering and Clearing 100%
Roof 100% Roof 100%
Roof Framing 100% Roof Framing 100%
Roofing 100% Roofing 100%

ARCHITECTURAL 0% ARCHITECTURAL 0%
Doors Doors
Windows Windows
Staircase (Contractor) Staircase (Contractor)
Tile Works (Contractor) Tile Works (Contractor)
Celing Celing
2nd Floor Partition 2nd Floor Partition
Terrace Terrace
Stone laying Stone laying
Painting Painting
ELECTRICAL 92% ELECTRICAL 92%
Wiring and Provision 100% Wiring and Provision 100%
Box setting and Piping 100% Box setting and Piping 100%
Fixtures (Outlet and Switch) 75% Fixtures (Outlet and Switch) 75%
LOT 64 64% LOT 65 64%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 100% STRUCTURAL 100%
Ground Floor 100% Ground Floor 100%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 100% Service Area and Comfort Room 100%
Carport and Septic tank 100% Carport and Septic tank 100%
2nd Floor 100% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 100%
Plumbing 100% Plumbing 100%
Ground (Plumbing ang Fixtures) 100% Ground (Plumbing ang Fixtures) 100%
2nd Floor (Plumbing and Fixtures) 100% 2nd Floor (Plumbing and Fixtures) 100%
Plastering and Clearing 100% Plastering and Clearing 100%
Roof 100% Roof 100%
Roof Framing 100% Roof Framing 100%
Roofing 100% Roofing 100%

ARCHITECTURAL 0% ARCHITECTURAL 0%
Doors Doors
Windows Windows
Staircase (Contractor) Staircase (Contractor)
Tile Works (Contractor) Tile Works (Contractor)
Celing Celing
2nd Floor Partition 2nd Floor Partition
Terrace Terrace
Stone laying Stone laying
Painting Painting
ELECTRICAL 92% ELECTRICAL 92%
Wiring and Provision 100% Wiring and Provision 100%
Box setting and Piping 100% Box setting and Piping 100%
Fixtures (Outlet and Switch) 75% Fixtures (Outlet and Switch) 75%
LOT 50 64% LOT 51 64%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 100% STRUCTURAL 100%
Ground Floor 100% Ground Floor 100%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 100% Service Area and Comfort Room 100%
Carport and Septic tank 100% Carport and Septic tank 100%
2nd Floor 100% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 100%
Plumbing 100% Plumbing 100%
Ground (Plumbing ang Fixtures) 100% Ground (Plumbing ang Fixtures) 100%
2nd Floor (Plumbing and Fixtures) 100% 2nd Floor (Plumbing and Fixtures) 100%
Plastering and Clearing 100% Plastering and Clearing 100%
Roof 100% Roof 100%
Roof Framing 100% Roof Framing 100%
Roofing 100% Roofing 100%

ARCHITECTURAL 0% ARCHITECTURAL 0%
Doors Doors
Windows Windows
Staircase (Contractor) Staircase (Contractor)
Tile Works (Contractor) Tile Works (Contractor)
Celing Celing
2nd Floor Partition 2nd Floor Partition
Terrace Terrace
Stone laying Stone laying
Painting Painting

ELECTRICAL 92% ELECTRICAL 92%


Wiring and Provision 100% Wiring and Provision 100%
Box setting and Piping 100% Box setting and Piping 100%
Fixtures (Outlet and Switch) 75% Fixtures (Outlet and Switch) 75%
LOT 54 64% LOT 55 64%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 100% STRUCTURAL 100%
Ground Floor 100% Ground Floor 100%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 100% Service Area and Comfort Room 100%
Carport and Septic tank 100% Carport and Septic tank 100%
2nd Floor 100% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 100%
Plumbing 100% Plumbing 100%
Ground (Plumbing ang Fixtures) 100% Ground (Plumbing ang Fixtures) 100%
2nd Floor (Plumbing and Fixtures) 100% 2nd Floor (Plumbing and Fixtures) 100%
Plastering and Clearing 100% Plastering and Clearing 100%
Roof 100% Roof 100%
Roof Framing 100% Roof Framing 100%
Roofing 100% Roofing 100%

ARCHITECTURAL 0% ARCHITECTURAL 0%
Doors Doors
Windows Windows
Staircase (Contractor) Staircase (Contractor)
Tile Works (Contractor) Tile Works (Contractor)
Celing Celing
2nd Floor Partition 2nd Floor Partition
Terrace Terrace
Stone laying Stone laying
Painting Painting

ELECTRICAL 92% ELECTRICAL 92%


Wiring and Provision 100% Wiring and Provision 100%
Box setting and Piping 100% Box setting and Piping 100%
Fixtures (Outlet and Switch) 75% Fixtures (Outlet and Switch) 75%
LOT 58 64% LOT 59 64%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 100% STRUCTURAL 100%
Ground Floor 100% Ground Floor 100%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 100% Service Area and Comfort Room 100%
Carport and Septic tank 100% Carport and Septic tank 100%
2nd Floor 100% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 100%
Plumbing 100% Plumbing 100%
Ground (Plumbing ang Fixtures) 100% Ground (Plumbing ang Fixtures) 100%
2nd Floor (Plumbing and Fixtures) 100% 2nd Floor (Plumbing and Fixtures) 100%
Plastering and Clearing 100% Plastering and Clearing 100%
Roof 100% Roof 100%
Roof Framing 100% Roof Framing 100%
Roofing 100% Roofing 100%
1%
ARCHITECTURAL 0% ARCHITECTURAL 0%
Doors Doors
Windows Windows
Staircase (Contractor) Staircase (Contractor)
Tile Works (Contractor) Tile Works (Contractor)
Celing Celing
2nd Floor Partition 2nd Floor Partition
Terrace Terrace
Stone laying Stone laying
Painting Painting

ELECTRICAL 92% ELECTRICAL 92%


Wiring and Provision 100% Wiring and Provision 100%
Box setting and Piping 100% Box setting and Piping 100%
Fixtures (Outlet and Switch) 75% Fixtures (Outlet and Switch) 75%
LOT 62 64% LOT 63 64%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 100% STRUCTURAL 100%
Ground Floor 100% Ground Floor 100%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 100% Service Area and Comfort Room 100%
Carport and Septic tank 100% Carport and Septic tank 100%
2nd Floor 100% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 100%
Plumbing 100% Plumbing 100%
Ground (Plumbing ang Fixtures) 100% Ground (Plumbing ang Fixtures) 100%
2nd Floor (Plumbing and Fixtures) 100% 2nd Floor (Plumbing and Fixtures) 100%
Plastering and Clearing 100% Plastering and Clearing 100%
Roof 100% Roof 100%
Roof Framing 100% Roof Framing 100%
Roofing 100% Roofing 100%

ARCHITECTURAL 0% ARCHITECTURAL 0%
Doors Doors
Windows Windows
Staircase (Contractor) Staircase (Contractor)
Tile Works (Contractor) Tile Works (Contractor)
Celing Celing
2nd Floor Partition 2nd Floor Partition
Terrace Terrace
Stone laying Stone laying
Painting Painting
ELECTRICAL 92% ELECTRICAL 92%
Wiring and Provision 100% Wiring and Provision 100%
Box setting and Piping 100% Box setting and Piping 100%
Fixtures (Outlet and Switch) 75% Fixtures (Outlet and Switch) 75%
LOT 67 58% LOT 68 58%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 96% STRUCTURAL 96%
Ground Floor 100% Ground Floor 100%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 100% Service Area and Comfort Room 100%
Carport and Septic tank 100% Carport and Septic tank 100%
2nd Floor 100% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 100%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 100% Ground (Plumbing ang Fixtures) 100%
2nd Floor (Plumbing and Fixtures) 50% 2nd Floor (Plumbing and Fixtures) 50%
Plastering and Clearing 100% Plastering and Clearing 100%
Roof 100% Roof 100%
Roof Framing 100% Roof Framing 100%
Roofing 100% Roofing 100%

ARCHITECTURAL 0% ARCHITECTURAL 0%
Doors Doors
Windows Windows
Staircase (Contractor) Staircase (Contractor)
Tile Works (Contractor) Tile Works (Contractor)
Celing Celing
2nd Floor Partition 2nd Floor Partition
Terrace Terrace
Stone laying Stone laying
Painting Painting

ELECTRICAL 77% ELECTRICAL 77%


Wiring and Provision 80% Wiring and Provision 80%
Box setting and Piping 100% Box setting and Piping 100%
Fixtures (Outlet and Switch) 50% Fixtures (Outlet and Switch) 50%
LOT 71 58% LOT 72 58%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 96% STRUCTURAL 96%
Ground Floor 100% Ground Floor 100%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 100% Service Area and Comfort Room 100%
Carport and Septic tank 100% Carport and Septic tank 100%
2nd Floor 100% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 100%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 100% Ground (Plumbing ang Fixtures) 100%
2nd Floor (Plumbing and Fixtures) 50% 2nd Floor (Plumbing and Fixtures) 50%
Plastering and Clearing 100% Plastering and Clearing 100%
Roof 100% Roof 100%
Roof Framing 100% Roof Framing 100%
Roofing 100% Roofing 100%

ARCHITECTURAL 0% ARCHITECTURAL 0%
Doors Doors
Windows Windows
Staircase (Contractor) Staircase (Contractor)
Tile Works (Contractor) Tile Works (Contractor)
Celing Celing
2nd Floor Partition 2nd Floor Partition
Terrace Terrace
Stone laying Stone laying
Painting Painting

ELECTRICAL 77% ELECTRICAL 77%


Wiring and Provision 80% Wiring and Provision 80%
Box setting and Piping 100% Box setting and Piping 100%
Fixtures (Outlet and Switch) 50% Fixtures (Outlet and Switch) 50%
LOT 75 32% LOT 76
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 96% STRUCTURAL 96%
Ground Floor 100% Ground Floor 100%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 100% Service Area and Comfort Room 100%
Carport and Septic tank 100% Carport and Septic tank 100%
2nd Floor 100% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 100%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 100% Ground (Plumbing ang Fixtures) 100%
2nd Floor (Plumbing and Fixtures) 50% 2nd Floor (Plumbing and Fixtures) 50%
Plastering and Clearing 100% Plastering and Clearing 100%
Roof 100% Roof 100%
Roof Framing 100% Roof Framing 100%
Roofing 100% Roofing 100%

ARCHITECTURAL 0% ARCHITECTURAL 0%
Doors Doors
Windows Windows
Staircase (Contractor) Staircase (Contractor)
Tile Works (Contractor) Tile Works (Contractor)
Celing Celing
2nd Floor Partition 2nd Floor Partition
Terrace Terrace
Stone laying Stone laying
Painting Painting

ELECTRICAL 0% ELECTRICAL 0%
Wiring and Provision Wiring and Provision
Box setting and Piping Box setting and Piping
Fixtures (Outlet and Switch) Fixtures (Outlet and Switch)
LOT 79 32% LOT 80 32%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 96% STRUCTURAL 96%
Ground Floor 100% Ground Floor 100%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 100% Service Area and Comfort Room 100%
Carport and Septic tank 100% Carport and Septic tank 100%
2nd Floor 100% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 100%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 100% Ground (Plumbing ang Fixtures) 100%
2nd Floor (Plumbing and Fixtures) 50% 2nd Floor (Plumbing and Fixtures) 50%
Plastering and Clearing 100% Plastering and Clearing 100%
Roof 100% Roof 100%
Roof Framing 100% Roof Framing 100%
Roofing 100% Roofing 100%

ARCHITECTURAL 0% ARCHITECTURAL 0%
Doors Doors
Windows Windows
Staircase (Contractor) Staircase (Contractor)
Tile Works (Contractor) Tile Works (Contractor)
Celing Celing
2nd Floor Partition 2nd Floor Partition
Terrace Terrace
Stone laying Stone laying
Painting Painting
ELECTRICAL 0% ELECTRICAL 0%
Wiring and Provision Wiring and Provision
Box setting and Piping Box setting and Piping
Fixtures (Outlet and Switch) Fixtures (Outlet and Switch)
LOT 83 32% LOT 84 32%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 96% STRUCTURAL 96%
Ground Floor 100% Ground Floor 100%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 100% Service Area and Comfort Room 100%
Carport and Septic tank 100% Carport and Septic tank 100%
2nd Floor 100% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 100%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 100% Ground (Plumbing ang Fixtures) 100%
2nd Floor (Plumbing and Fixtures) 50% 2nd Floor (Plumbing and Fixtures) 50%
Plastering and Clearing 100% Plastering and Clearing 100%
Roof 100% Roof 100%
Roof Framing 100% Roof Framing 100%
Roofing 100% Roofing 100%

ARCHITECTURAL 0% ARCHITECTURAL 0%
Doors Doors
Windows Windows
Staircase (Contractor) Staircase (Contractor)
Tile Works (Contractor) Tile Works (Contractor)
Celing Celing
2nd Floor Partition 2nd Floor Partition
Terrace Terrace
Stone laying Stone laying
Painting Painting
ELECTRICAL 0% ELECTRICAL 0%
Wiring and Provision Wiring and Provision
Box setting and Piping Box setting and Piping
Fixtures (Outlet and Switch) Fixtures (Outlet and Switch)
LOT 87 32% LOT 88 0%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 96% STRUCTURAL 0%
Ground Floor 100% Ground Floor 0%
Foundation 100% Foundation
Flooring 100% Flooring
Walling 100% Walling
Service Area and Comfort Room 100% Service Area and Comfort Room
Carport and Septic tank 100% Carport and Septic tank
2nd Floor 100% 2nd Floor 0%
Steel Deck 100% Steel Deck
Slab 100% Slab
Shear Wall 100% Shear Wall
Comfort Room 100% Comfort Room
Plumbing 75% Plumbing 0%
Ground (Plumbing ang Fixtures) 100% Ground (Plumbing ang Fixtures)
2nd Floor (Plumbing and Fixtures) 50% 2nd Floor (Plumbing and Fixtures)
Plastering and Clearing 100% Plastering and Clearing
Roof 100% Roof 0%
Roof Framing 100% Roof Framing
Roofing 100% Roofing

ARCHITECTURAL 0% ARCHITECTURAL 0%
Doors Doors
Windows Windows
Staircase (Contractor) Staircase (Contractor)
Tile Works (Contractor) Tile Works (Contractor)
Celing Celing
2nd Floor Partition 2nd Floor Partition
Terrace Terrace
Stone laying Stone laying
Painting Painting

ELECTRICAL 0% ELECTRICAL 0%
Wiring and Provision Wiring and Provision
Box setting and Piping Box setting and Piping
Fixtures (Outlet and Switch) Fixtures (Outlet and Switch)
LOT 69 58% LOT 70 58%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 96% STRUCTURAL 96%
Ground Floor 100% Ground Floor 100%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 100% Service Area and Comfort Room 100%
Carport and Septic tank 100% Carport and Septic tank 100%
2nd Floor 100% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 100%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 100% Ground (Plumbing ang Fixtures) 100%
2nd Floor (Plumbing and Fixtures) 50% 2nd Floor (Plumbing and Fixtures) 50%
Plastering and Clearing 100% Plastering and Clearing 100%
Roof 100% Roof 100%
Roof Framing 100% Roof Framing 100%
Roofing 100% Roofing 100%

ARCHITECTURAL 0% ARCHITECTURAL 0%
Doors Doors
Windows Windows
Staircase (Contractor) Staircase (Contractor)
Tile Works (Contractor) Tile Works (Contractor)
Celing Celing
2nd Floor Partition 2nd Floor Partition
Terrace Terrace
Stone laying Stone laying
Painting Painting 0%

ELECTRICAL 77% ELECTRICAL 77%


Wiring and Provision 80% Wiring and Provision 80%
Box setting and Piping 100% Box setting and Piping 100%
Fixtures (Outlet and Switch) 50% Fixtures (Outlet and Switch) 50%
LOT 73 32% LOT 74. 32%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 96% STRUCTURAL 96%
Ground Floor 100% Ground Floor 100%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 100% Service Area and Comfort Room 100%
Carport and Septic tank 100% Carport and Septic tank 100%
2nd Floor 100% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 100%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 100% Ground (Plumbing ang Fixtures) 100%
2nd Floor (Plumbing and Fixtures) 50% 2nd Floor (Plumbing and Fixtures) 50%
Plastering and Clearing 100% Plastering and Clearing 100%
Roof 100% Roof 100%
Roof Framing 100% Roof Framing 100%
Roofing 100% Roofing 100%

ARCHITECTURAL 0% ARCHITECTURAL 0%
Doors Doors
Windows Windows
Staircase (Contractor) Staircase (Contractor)
Tile Works (Contractor) Tile Works (Contractor)
Celing Celing
2nd Floor Partition 2nd Floor Partition
Terrace Terrace
Stone laying Stone laying
Painting Painting

ELECTRICAL 0% ELECTRICAL 0%
Wiring and Provision Wiring and Provision
Box setting and Piping Box setting and Piping
Fixtures (Outlet and Switch) Fixtures (Outlet and Switch)
LOT 77 32% LOT 78 32%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 96% STRUCTURAL 96%
Ground Floor 100% Ground Floor 100%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 100% Service Area and Comfort Room 100%
Carport and Septic tank 100% Carport and Septic tank 100%
2nd Floor 100% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 100%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 100% Ground (Plumbing ang Fixtures) 100%
2nd Floor (Plumbing and Fixtures) 50% 2nd Floor (Plumbing and Fixtures) 50%
Plastering and Clearing 100% Plastering and Clearing 100%
Roof 100% Roof 100%
Roof Framing 100% Roof Framing 100%
Roofing 100% Roofing 100%

ARCHITECTURAL 0% ARCHITECTURAL 0%
Doors Doors
Windows Windows
Staircase (Contractor) Staircase (Contractor)
Tile Works (Contractor) Tile Works (Contractor)
Celing Celing
2nd Floor Partition 2nd Floor Partition
Terrace Terrace
Stone laying Stone laying
Painting Painting

ELECTRICAL 0% ELECTRICAL 0%
Wiring and Provision Wiring and Provision
Box setting and Piping Box setting and Piping
Fixtures (Outlet and Switch) Fixtures (Outlet and Switch)
LOT 81 32% LOT 82 32%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 96% STRUCTURAL 96%
Ground Floor 100% Ground Floor 100%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 100% Service Area and Comfort Room 100%
Carport and Septic tank 100% Carport and Septic tank 100%
2nd Floor 100% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 100%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 100% Ground (Plumbing ang Fixtures) 100%
2nd Floor (Plumbing and Fixtures) 50% 2nd Floor (Plumbing and Fixtures) 50%
Plastering and Clearing 100% Plastering and Clearing 100%
Roof 100% Roof 100%
Roof Framing 100% Roof Framing 100%
Roofing 100% Roofing 100%

ARCHITECTURAL 0% ARCHITECTURAL 0%
Doors Doors
Windows Windows
Staircase (Contractor) Staircase (Contractor)
Tile Works (Contractor) Tile Works (Contractor)
Celing Celing
2nd Floor Partition 2nd Floor Partition
Terrace Terrace
Stone laying Stone laying
Painting Painting
ELECTRICAL 0% ELECTRICAL 0%
Wiring and Provision Wiring and Provision
Box setting and Piping Box setting and Piping
Fixtures (Outlet and Switch) Fixtures (Outlet and Switch)
LOT 85 32% LOT 86 32%
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 96% STRUCTURAL 96%
Ground Floor 100% Ground Floor 100%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 100% Service Area and Comfort Room 100%
Carport and Septic tank 100% Carport and Septic tank 100%
2nd Floor 100% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 100% Comfort Room 100%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 100% Ground (Plumbing ang Fixtures) 100%
2nd Floor (Plumbing and Fixtures) 50% 2nd Floor (Plumbing and Fixtures) 50%
Plastering and Clearing 100% Plastering and Clearing 100%
Roof 100% Roof 100%
Roof Framing 100% Roof Framing 100%
Roofing 100% Roofing 100%

ARCHITECTURAL 0% ARCHITECTURAL 0%
Doors Doors
Windows Windows
Staircase (Contractor) Staircase (Contractor)
Tile Works (Contractor) Tile Works (Contractor)
Celing Celing
2nd Floor Partition 2nd Floor Partition
Terrace Terrace
Stone laying Stone laying
Painting Painting
ELECTRICAL 0% ELECTRICAL 0%
Wiring and Provision Wiring and Provision
Box setting and Piping Box setting and Piping
Fixtures (Outlet and Switch) Fixtures (Outlet and Switch)

INDIVIDUAL PROGRESS OF BLOCK 3


BLOCK 4 LOT (67 - 88) As of: AUGUST 24 - SEPTEMBER 03, 2022
2 Storey Residential Row House
General Progress of the Project
BLOCK 4
Current Finish Work (December 13, 2022) Previous Finish Work (December 01, 2022) As of: December 13, 2022
Lot No. Structural Architectural Electrical Finish Work(%) Structural Architectural Electrical Finish Work(%) General Progress(+,-)
48 100.00% 0.00% 92.00% 64.00% 100% 0% 92% 64.00% 0.00%
49 100.00% 0.00% 92.00% 64.00% 100% 0% 92% 64.00% 0.00%
50 100.00% 0.00% 92.00% 64.00% 100% 0% 92% 64.00% 0.00%
51 100.00% 0.00% 92.00% 64.00% 100% 0% 92% 64.00% 0.00%
52 100.00% 0.00% 92.00% 64.00% 100% 0% 92% 64.00% 0.00%
53 100.00% 0.00% 92.00% 64.00% 100% 0% 92% 64.00% 0.00%
54 100.00% 0.00% 92.00% 64.00% 100% 0% 92% 64.00% 0.00%
55 100.00% 0.00% 92.00% 64.00% 100% 0% 92% 64.00% 0.00%
56 100.00% 0.00% 92.00% 64.00% 100% 0% 92% 64.00% 0.00%
57 100.00% 0.00% 92.00% 64.00% 100% 0% 92% 64.00% 0.00%
58 100.00% 0.00% 92.00% 64.00% 100% 0% 92% 64.00% 0.00%
59 100.00% 0.00% 92.00% 64.00% 100% 0% 92% 64.00% 0.00%
60 100.00% 0.00% 92.00% 64.00% 100% 0% 92% 64.00% 0.00%
61 100.00% 0.00% 92.00% 64.00% 100% 0% 92% 64.00% 0.00%
62 100.00% 0.00% 92.00% 64.00% 100% 0% 92% 64.00% 0.00%
63 100.00% 0.00% 92.00% 64.00% 100% 0% 92% 64.00% 0.00%
64 100.00% 0.00% 92.00% 64.00% 100% 0% 92% 64.00% 0.00%
65 100.00% 0.00% 92.00% 64.00% 100% 0% 92% 64.00% 0.00%

Note:
Projecting the general progress of the whole project. This
includes delays:
* Lack of Human power
* Weather Condition (Heavy Rainfall)

Green Represents (Finished Work)


Red Represents (Unfinished Work)
`
Current Finish Work (December 13, 2022) Previous Finish Work (December 01, 2022) As of: December 13, 2022

Lot No. Structural Architectural Electrical Finish Work(%) Structural Architectural Electrical Finish Work(%) General Progress(+,-)
67 96.00% 0.00% 77.00% 58.00% 90.00% 0.00% 0.00% 0.00% 58.00%
68 96.00% 0.00% 77.00% 58.00% 92.00% 0.00% 0.00% 0.00% 58.00%
69 96.00% 0.00% 77.00% 58.00% 90.00% 0.00% 0.00% 0.00% 58.00%
70 96.00% 0.00% 77.00% 58.00% 90.00% 0.00% 0.00% 0.00% 58.00%
71 96.00% 0.00% 77.00% 58.00% 90.00% 0.00% 0.00% 0.00% 58.00%
72 96.00% 0.00% 77.00% 58.00% 82.00% 0.00% 0.00% 0.00% 58.00%
73 96.00% 0.00% 0.00% 32.00% 78.00% 0.00% 0.00% 0.00% 32.00%
74 96.00% 0.00% 0.00% 32.00% 78.00% 0.00% 0.00% 0.00% 32.00%
75 96.00% 0.00% 0.00% 32.00% 78.00% 0.00% 0.00% 0.00% 32.00%
76 96.00% 0.00% 0.00% 32.00% 78.00% 0.00% 0.00% 0.00% 32.00%
77 96.00% 0.00% 0.00% 32.00% 77.00% 0.00% 0.00% 0.00% 32.00%
78 96.00% 0.00% 0.00% 32.00% 77.00% 0.00% 0.00% 0.00% 32.00%
79 96.00% 0.00% 0.00% 32.00% 78.00% 0.00% 0.00% 0.00% 32.00%
80 96.00% 0.00% 0.00% 32.00% 78.00% 0.00% 0.00% 0.00% 32.00%
81 96.00% 0.00% 0.00% 32.00% 78.00% 0.00% 0.00% 0.00% 32.00%
82 96.00% 0.00% 0.00% 32.00% 78.00% 0.00% 0.00% 0.00% 32.00%
83 96.00% 0.00% 0.00% 32.00% 78.00% 0.00% 0.00% 0.00% 32.00%
84 96.00% 0.00% 0.00% 32.00% 76.00% 0.00% 0.00% 0.00% 32.00%
85 96.00% 0.00% 0.00% 32.00% 76.00% 0.00% 0.00% 0.00% 32.00%
86 96.00% 0.00% 0.00% 32.00% 76.00% 0.00% 0.00% 0.00% 32.00%
87 96.00% 0.00% 0.00% 32.00% 65.00% 0.00% 0.00% 0.00% 32.00%
88 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

SECTOR PERCENTAGE OF THE PROJECT 2 Storey Residential Row House


BLOCK 3
Structural Architectural Electrical

95% 0% 53.00%
51% 49%

A 49%
B 51.00%
51% 49%

Individual Progress per Department (+,-) Individual Progress per Department (+,-)
Lot No. Structural Architectural Electrical Lot No. Structural Architectural Electrical
48 0.00% 0.00% 0.00% 67 6.00% 0.00% 77.00%
49 0.00% 0.00% 0.00% 68 4.00% 0.00% 77.00%
50 0.00% 0.00% 0.00% 69 6.00% 0.00% 77.00%
51 0.00% 0.00% 0.00% 70 6.00% 0.00% 77.00%
52 0.00% 0.00% 0.00% 71 6.00% 0.00% 77.00%
53 0.00% 0.00% 0.00% 72 14.00% 0.00% 77.00%
54 0.00% 0.00% 0.00% 73 18.00% 0.00% 0.00%
55 0.00% 0.00% 0.00% 74 18.00% 0.00% 0.00%
56 0.00% 0.00% 0.00% 75 18.00% 0.00% 0.00%
57 0.00% 0.00% 0.00% 76 18.00% 0.00% 0.00%
58 0.00% 0.00% 0.00% 77 19.00% 0.00% 0.00%
59 0.00% 0.00% 0.00% 78 19.00% 0.00% 0.00%
60 0.00% 0.00% 0.00% 79 18.00% 0.00% 0.00%
61 0.00% 0.00% 0.00% 80 18.00% 0.00% 0.00%
62 0.00% 0.00% 0.00% 81 18.00% 0.00% 0.00%
63 0.00% 0.00% 0.00% 82 18.00% 0.00% 0.00%
64 0.00% 0.00% 0.00% 83 18.00% 0.00% 0.00%
65 0.00% 0.00% 0.00% 84 20.00% 0.00% 0.00%
85 20.00% 0.00% 0.00%
86 20.00% 0.00% 0.00%
87 31.00% 0.00% 0.00%
This Space intended for the computation of percentage 88 0.00% 0.00% 0.00%
of structural, Architectural, and Electrical over the
whole project.

Note:
This individual progress focus more on structural
department. Architectural and Electrical has a
long time interval.
INDIVIDUAL PROGRESS OF BLOCK 4
BLOCK 4 LOT (48 - 65)
As of: DECEMBER 13, 2022
4
)