You are on page 1of 3

COMPANY : PT.

TIGA PILAR ENERGI


PROJECT : CENTRAL JAVA 2X1000MW SUPERCRITICAL COAL FIRED POWER PROJECT
CLIENT : PT. JURONG ENGINEERING LESTARI
(I) ERECTION OF BOILER PRESSURE & NON PRESSURE PARTS, PARTS, FIRING EQUIPMENT 12
AND SOOT BLOWING SYSTEM (FOR 2 UNITD) AND (II) ERECTION BOILER STEEL 12
SCOPE OF WORK :
STRUCTURE, BOILER ELEVATOR, CONVEYOR BRIDGE AND MISCELLANEOUS STRUCTURE
(FOR 2 UNITS)
9 3
Weather report : Weather report: F - Fine; R-Rain; W-Wind; C-Cloudy; D-Drizzling 9 3
F F F F
DAILY ACTIVITY REPORT ISSUED DATE/TIME
21-Nov-17 09.00 Hrs
Drz 6
6
8 2
Yesterday (20/11/2017) Today (21/11/2017)
Manpower -Normal Manpower - OT hrs - Manpower -Normal hrs Manpower - OT hrs -
Direct Manpower Total Usage Area for Equipment & Tools Total ( no's ) hrs ( 7am to 15pm ) (16pm to 18pm) Direct Manpower Total Usage Area for Equipment & Tools Total ( no's ) ( 7am to 15pm ) (16pm to 18pm)
8 8 1
Foreman Rigger 1 Pick Up 1 8 1 Foreman Rigger 1 Pick Up 1 8 1
Foreman Scaffolder 2 Drilling Machine 2 16 2 Foreman Scaffolder 2 Rol Painting 5 16 2
Foreman Structure 1 Grinding Machine 4" 2 8 1 Foreman Structure 1 Drilling Machine 2 8 1
Rigger 1 4 Nail Hammer 2 32 4 Rigger 1 4 Nailhammer 3 32 4
Rigger 2 4 Sledgehammers 1 32 4 Rigger 2 4 Grinding Machine 3 32 4
Boiler Fitter 3 Oxygen Tube 1 24 3 Boiler Fitter 3 Lamp 1 24 3
Fitter Structure 4 Measuring Tape 2 32 4 Fitter Structure 4 Cable 4 roll 32 4
Scaffolder 1 5 Hoe 2 40 5 Scaffolder 1 5 Saw 2 40 5
Scaffolder 2 5 LPG Tube 1 40 5 Scaffolder 2 5 Bucket 6 40 5
Skill Electician 2 Shovel 2 16 2 Skill Electician 2 Auto Level 1 16 2
Skill Surveyor 2 Cutting Wheel 2 16 2 Skill Surveyor 2 Theodolite 1 16 2
Plate Welder 7 Pliers 3 56 7 Plate Welder 7 56 7
Semi Skill Boiler Fitter 2 LAYDOWN 10 (SITE Screwdriver 3 16 2 Semi Skill Boiler Fitter 2 LAYDOWN 10 (SITE 16 2
OFFICE AND OFFICE AND WAREHOUSE
Semi Skill Surveyor 3 WAREHOUSE AREA) Travo Welding 1 24 3 Semi Skill Surveyor 3 AREA) 24 3
Helper Structure 2 Cable 4 (roll) 16 2 Helper Structure 2 16 2
Workers (Civil) 14 Rol Painting 4 112 14 Workers (Civil) 13 104 13
Paint Brush 4
Welding Machine 2
Cutting Torch 2

Sub-Total ( Direct Manpower ) 61 37 488 61 Sub-Total ( Direct Manpower ) 60 25 480 60

Indirect Manpower Indirect Manpower

Site Manager 1 Station 7 Seat 4 8 - Site Manager 1 Station 7 Seat 4 8 -


PPC Engineer 1 8 - PPC Engineer 1 8 -
Procurement Officer 1 8 - Procurement Officer 1 8 -
Finance Officer 1 8 - Finance Officer 1 8 -
HRD Officer 1 8 - HRD Officer 1 8 -
HRD Assistant Officer 1 8 HRD Assistant Officer 1 8 -
Civil Engineer 2 16 - Civil Engineer 2 16 -
QC Engineer 1 8 - QC Engineer 1 8 -
Structure Engineer 1 8 - Structure Engineer 1 8 -
Rigging Engineer 1 8 - Rigging Engineer 1 8 -
MC/WH Engineer - 0 - MC/WH Engineer 1 8 -
HSE 1 8 - HSE - 0 -
Electric Supervisor - 0 - Electric Supervisor 1 8 -
Structure Supervisor 1 8 - Structure Supervisor - 0 -
Boiler Supervisor 1 LAYDOWN 10 (SITE 8 Boiler Supervisor 1 LAYDOWN 10 (SITE 8 -
OFFICE AND OFFICE AND WAREHOUSE
Welder Supervisor 1 WAREHOUSE AREA) 8 - Welder Supervisor 1 AREA) 8 -
WH Supervisor - 0 - WH Supervisor 1 8 -
Material Control 1 8 - Material Control 1 8 -
Ducting Supervisor 1 8 - Ducting Supervisor 1 8 -
Surveyor Supervisor 1 8 - Surveyor Supervisor 1 8 -
Rigger Supervisor 2 16 - Rigger Supervisor 2 16 -
Scaffolder Supervisor 1 8 - Scaffolder Supervisor 1 8 -
Driver Station 7 Seat 4 32 4 Driver Station 7 Seat 4 32 4
Driver Pick up 1 8 1 Driver Pick up 1 8 1

Sub-Total ( Indirect Manpower ) 26 4 208 5 Sub-Total ( Indirect Manpower ) 27 4 216 5


Total ( Direct + Indirect) 87 4 696 66 Total ( Direct + Indirect) 87 4 696 65

Job Description Job Description

1 Temporary Facility 1 Temporary Facility

- Installation cable power 3 x 2.5m of 5 unit & Pulling cable of 50m (Continue) - Installation cable power 3 x 2.5m of 5 unit & Pulling cable of 50m (Complete)

- Painting wall (containers site office no.2 & no.3 complete and Container no.4 continue) - Painting wall (containers site office no.2 & no.3 complete and Container no.4 continue)

- Fabrication & Install for support AC Office of 4 unit (Continue) - Fabrication & Install for support AC Office of 4 unit (Continue)

- Fabrication & Install tools box of 2 unit (Complete) - Installation Pipe Septic tank & Ceramic installation

2 Construction 2 Construction

- Continue Handover foundation, dimension foundation & top of concrete elevation for coloumn G-H (Waiting for approval SC BTG JEL) - Handover foundation, dimension foundation & top of concrete elevation for coloumn G - H (Coloumn 12 & 11A Complete)

- Prepare chipping foundation (Marking coloumn packer plate) - Continue Handover foundation, dimension foundation & top of concrete elevation for coloumn K - P

- Making formwork for concrete block 9 sets complete & 8 sets complete - Chipping foundation for Coloumn G-H (12 & 11A)
- Fabrication Rebar for concrete block 9 sets complete & 3 sets complete - Preparation assembly starway structure at Laydown

- Check material coloumn at Laydown PT. JEL (Continue) - Preparation Nut (Top Plate/Wassher) & Cleaning for first coloumn - Boiler Unit 1

- Prepare Colour Code Material Scaffolding 1m of 450 lgh, 1.5m of 350 lgh, 2 m of 350 lgh & 4m of 50 lgh - Prepare or Check material Frame Starway, Check Grating Stair Tread and Check bolt nut stair

- Loading material scaffolding from PT. JEL - Prepare Colour Code Material Scaffolding 1m of 150 lgh, 1.5m of 50 lgh & 6m of 50 lgh

- Prepare Colour Code Clamp ( Fixed Clamp of 2000 each, Swifel Clamp of 1000 each, Beam Clamp of 400 each, Joint Clamp of 1000 each & Base Clamp of 500
- Fabrication Packer Plate (230 x 300 x 16t of 14 pcs), (130 x 200 x 16t of 56 pcs), (230 x 300 x 12t of 21 pcs) & Packer Plate (130 x 200 x 12t of 84 pcs) each)

- Preparation Nut (Top Plate/Wassher) & Cleaning for first coloumn - Boiler Unit 1 - Loading material scaffolding to Boiler Area

- Preparation assembly starway structure at Laydown - Fabrication Packer Plate (230 x 300 x 16t of 14 pcs), (130 x 200 x 16t of 56 pcs), (230 x 300 x 12t of 21 pcs) & Packer Plate (130 x 200 x 12t of 84 pcs)

- Making formwork for concrete block 24 sets complete & 6 sets on progress

- Fabrication Rebar for concrete block 30 sets (Complete)

- Pouring Concrete Block 17 sets Complete , 7 sets On Progress and 6 sets Continue

- Check material coloumn at Laydown PT. JEL (Continue)

Issues & Concern Issues & Concern

1 - 1

2 2

3 3

4 4

5 5

6 6

Manpower - Manpower - OT
Man-hour Normal hrs ( 7am hrs - (16pm to Total Hr
to 15pm ) 18pm)
Yesterday (20/11/2017)

696 66 762
Today (21/11/2017) 696 65 761
- Prepared by, Approved by,
- PT. Tiga Pilar Energi PT. Jurong Engineering Lestari
-
-
-
-
-
- Juli Suharni Sudhesh Rajamoorthy
-
Our Achievement 1,392 131 1,523
1 Welding Supervisor : Joner Manurung
Manpower
1 Afiq Putra P : Fitter 1 (Plate welder)
2 Jarot Sugiarto : Fitter 1 (Plate welder)
3 Abdul Hanif : Fitter 1 (Plate welder)
4 Dicky Noviansyah : Fitter 1 (Plate welder)
5 Faturohman : Fitter 1 (Plate welder)
6 Richo Knarta Asip : Fitter 1 (Plate welder)
7 Erick Nahason M : Fitter 1 (Plate welder)

2 Ducting Supervisor : Ramli D.S

3 Scaffolding Supervisor : Solehuddin


Manpower
1 M. Jalaluddin : L/H Scaffolder (Foreman)
2 Lutfi : L/H Scaffolder (Foreman)
3 Buten Toyoso : Skill 1 Scaffolder
4 Baisul Baori : Skill 1 Scaffolder
5 Misbah : Skill 1 Scaffolder
6 Moh Sulhan : Skill 1 Scaffolder
7 Agus Salim : Skill 1 Scaffolder
8 Salehuddin : Skill 2 Scaffolder
9 Edi Sudarsono : Skill 2 Scaffolder
10 Ryan Farisi : Skill 2 Scaffolder
11 Moh Sigit : Skill 2 Scaffolder
12 Fitriyarman : Skill 2 Scaffolder

4 Rigging Supervisor 1 : Suwardji


Manpower
1 Darmuji : Rigger 1
2 Juli Andrean : Rigger 1
3 Imam Safi'i : Rigger 2
4 Kasmuri : Rigger 2

5 Rigging Supervisor 2 : Heri


Manpower
1 Darmuji : Rigger 1
2 Juli Andrean : Rigger 1
3 :
4 :
5 :
:
:
:

You might also like