Daily Report Dated 20 - 21 November 2017
Daily Report Dated 20 - 21 November 2017
- Installation cable power 3 x 2.5m of 5 unit & Pulling cable of 50m (Continue) - Installation cable power 3 x 2.5m of 5 unit & Pulling cable of 50m (Complete)
- Painting wall (containers site office no.2 & no.3 complete and Container no.4 continue) - Painting wall (containers site office no.2 & no.3 complete and Container no.4 continue)
- Fabrication & Install for support AC Office of 4 unit (Continue) - Fabrication & Install for support AC Office of 4 unit (Continue)
- Fabrication & Install tools box of 2 unit (Complete) - Installation Pipe Septic tank & Ceramic installation
2 Construction 2 Construction
- Continue Handover foundation, dimension foundation & top of concrete elevation for coloumn G-H (Waiting for approval SC BTG JEL) - Handover foundation, dimension foundation & top of concrete elevation for coloumn G - H (Coloumn 12 & 11A Complete)
- Prepare chipping foundation (Marking coloumn packer plate) - Continue Handover foundation, dimension foundation & top of concrete elevation for coloumn K - P
- Making formwork for concrete block 9 sets complete & 8 sets complete - Chipping foundation for Coloumn G-H (12 & 11A)
- Fabrication Rebar for concrete block 9 sets complete & 3 sets complete - Preparation assembly starway structure at Laydown
- Check material coloumn at Laydown PT. JEL (Continue) - Preparation Nut (Top Plate/Wassher) & Cleaning for first coloumn - Boiler Unit 1
- Prepare Colour Code Material Scaffolding 1m of 450 lgh, 1.5m of 350 lgh, 2 m of 350 lgh & 4m of 50 lgh - Prepare or Check material Frame Starway, Check Grating Stair Tread and Check bolt nut stair
- Loading material scaffolding from PT. JEL - Prepare Colour Code Material Scaffolding 1m of 150 lgh, 1.5m of 50 lgh & 6m of 50 lgh
- Prepare Colour Code Clamp ( Fixed Clamp of 2000 each, Swifel Clamp of 1000 each, Beam Clamp of 400 each, Joint Clamp of 1000 each & Base Clamp of 500
- Fabrication Packer Plate (230 x 300 x 16t of 14 pcs), (130 x 200 x 16t of 56 pcs), (230 x 300 x 12t of 21 pcs) & Packer Plate (130 x 200 x 12t of 84 pcs) each)
- Preparation Nut (Top Plate/Wassher) & Cleaning for first coloumn - Boiler Unit 1 - Loading material scaffolding to Boiler Area
- Preparation assembly starway structure at Laydown - Fabrication Packer Plate (230 x 300 x 16t of 14 pcs), (130 x 200 x 16t of 56 pcs), (230 x 300 x 12t of 21 pcs) & Packer Plate (130 x 200 x 12t of 84 pcs)
- Making formwork for concrete block 24 sets complete & 6 sets on progress
- Pouring Concrete Block 17 sets Complete , 7 sets On Progress and 6 sets Continue
1 - 1
2 2
3 3
4 4
5 5
6 6
Manpower - Manpower - OT
Man-hour Normal hrs ( 7am hrs - (16pm to Total Hr
to 15pm ) 18pm)
Yesterday (20/11/2017)
696 66 762
Today (21/11/2017) 696 65 761
- Prepared by, Approved by,
- PT. Tiga Pilar Energi PT. Jurong Engineering Lestari
-
-
-
-
-
- Juli Suharni Sudhesh Rajamoorthy
-
Our Achievement 1,392 131 1,523
1 Welding Supervisor : Joner Manurung
Manpower
1 Afiq Putra P : Fitter 1 (Plate welder)
2 Jarot Sugiarto : Fitter 1 (Plate welder)
3 Abdul Hanif : Fitter 1 (Plate welder)
4 Dicky Noviansyah : Fitter 1 (Plate welder)
5 Faturohman : Fitter 1 (Plate welder)
6 Richo Knarta Asip : Fitter 1 (Plate welder)
7 Erick Nahason M : Fitter 1 (Plate welder)