Professional Documents
Culture Documents
Discharge Frame
Discharge Frame
TANJUNG JATI B UNIT 5&6 2X1000MW COAL FIRED POWER PLANT Sumitomo Corporation
Boiler Division
CLIENT : PT. BHUMI JATI POWER REPORT NO : TJB5&6-U5-VT-
Acceptance
PROJECT : TANJUNG JATI-B : AWS D1.1
Criteria
Remarks :
F Free O Overlap P Porosity UC Undercut
C Crack UF Under Fill R Reinforcement WS Weld Spatter
ACC ACCEPTABLE NA NOT ACCEPTABLE IP Incomplete Penetration FW Fillet Weld
PT. TPE PT. JEL SCBD EPC-IHE BJP-OE
Name : Name : Name : Name : Name :
FORM NO.:ITP-M-006-04
SCBD TANJUNG JATI B 5&6 2X1000MW COAL FIRED PROJECT
PT JEL
PT Jurong Engineering
Sumitomo Corporation Boiler
Division REQUEST FOR INSPECTION Lestari
INSPECTION POINT
ACTIVITY
SCBD EPC/IHE BJP/OE
Inspection Results
: The above works have been inspected and are in accordance with applicable specifications
standards and method statement and are acceptable.
: The above works are postponed for the following reasons. Re-inspection to be done on :
(where applicable)
Remark/Comments :
Name:
Signature:
Date:
FM-TJB-SCBD-QC-M-001-REV.1
SCBD
TANJUNG JATI B UNIT 5&6 2X1000MW COAL FIRED POWER PLANT Sumitomo Corporation
Boiler Division
CLIENT : PT. BHUMI JATI POWER REPORT NO : TJB5&6-U5-VT-
Acceptance
PROJECT : TANJUNG JATI-B : AWS D1.1
Criteria
Remarks :
F Free O Overlap P Porosity UC Undercut
C Crack UF Under Fill R Reinforcement WS Weld Spatter
ACC ACCEPTABLE NA NOT ACCEPTABLE IP Incomplete Penetration FW Fillet Weld
PT. TPE PT. JEL SCBD EPC-IHE BJP-OE
Name : Name : Name : Name : Name :
FORM NO.:ITP-M-006-04
SCBD
TANJUNG JATI B UNIT 5&6 2X1000MW COAL FIRED POWER PLANT Sumitomo Corporation
Boiler Division
CLIENT : PT. BHUMI JATI POWER REPORT NO : TJB5&6-U5-VT-
Acceptance
PROJECT : TANJUNG JATI-B : AWS D1.1
Criteria
Remarks :
F Free O Overlap P Porosity UC Undercut
C Crack UF Under Fill R Reinforcement WS Weld Spatter
ACC ACCEPTABLE NA NOT ACCEPTABLE IP Incomplete Penetration FW Fillet Weld
PT. TPE PT. JEL SCBD EPC-IHE BJP-OE
Name : Name : Name : Name : Name :
FORM NO.:ITP-M-006-04
SCBD
TANJUNG JATI B UNIT 5&6 2X1000MW COAL FIRED POWER PLANT Sumitomo Corporation
Boiler Division
CLIENT : PT. BHUMI JATI POWER REPORT NO : TJB5&6-U5-VT-
Acceptance
PROJECT : TANJUNG JATI-B : AWS D1.1
Criteria
Remarks :
F Free O Overlap P Porosity UC Undercut
C Crack UF Under Fill R Reinforcement WS Weld Spatter
ACC ACCEPTABLE NA NOT ACCEPTABLE IP Incomplete Penetration FW Fillet Weld
PT. TPE PT. JEL SCBD EPC-IHE BJP-OE
Name : Name : Name : Name : Name :
FORM NO.:ITP-M-006-04
SCBD
TANJUNG JATI B UNIT 5&6 2X1000MW COAL FIRED POWER PLANT Sumitomo Corporation
Boiler Division
CLIENT : PT. BHUMI JATI POWER REPORT NO : TJB5&6-U5-VT-
Acceptance
PROJECT : TANJUNG JATI-B : AWS D1.1
Criteria
Remarks :
F Free O Overlap P Porosity UC Undercut
C Crack UF Under Fill R Reinforcement WS Weld Spatter
ACC ACCEPTABLE NA NOT ACCEPTABLE IP Incomplete Penetration FW Fillet Weld
PT. TPE PT. JEL SCBD EPC-IHE BJP-OE
Name : Name : Name : Name : Name :
FORM NO.:ITP-M-006-04
SCBD TANJUNG JATI B 5&6 2X1000MW COAL FIRED PROJECT
PT JEL
PT Jurong Engineering
Sumitomo Corporation Boiler
Division REQUEST FOR INSPECTION Lestari
INSPECTION POINT
ACTIVITY
SCBD EPC/IHE BJP/OE
Inspection Results
: The above works have been inspected and are in accordance with applicable specifications
standards and method statement and are acceptable.
: The above works are postponed for the following reasons. Re-inspection to be done on :
(where applicable)
Remark/Comments :
Name:
Signature:
Date:
FM-TJB-SCBD-QC-M-001-REV.1