You are on page 1of 8

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/296217325

New tunnel boring machine accelerates tunnel construction in deep mining


operations

Article · July 2010

CITATION READS

1 595

2 authors, including:

Fred Christopher Delabbio


Strategy Focused Innovation
5 PUBLICATIONS 2 CITATIONS

SEE PROFILE

All content following this page was uploaded by Fred Christopher Delabbio on 18 June 2020.

The user has requested enhancement of the downloaded file.


UNDER ROUND M N N

G
I
I
G
New tunnel boring machine
accelerates tunnel construction
in deep mining operations
A
s openpit copper operations transition from surface Fig 1
mines to underground, the speed of underground Robbins MM130 (Willoughby, 1993).
infrastructure construction prior to production is
critical for maximizing the value of the project. Typically,
the preferred underground bulk mining method is block
caving.
In preparation for future underground projects, Rio
Tinto made the strategic decision to invest in a step-change
program that would develop system solutions to reduce the
construction time of block caves. The program focused on
improving safety and doubling or more the construction
speed of both vertical shafts and horizontal infrastructure
compared to existing drill-and-blast rates.
After an extensive selection process, Rio Tinto selected
the Atlas Copco mobile miner machine as one of the
concepts to proceed with for construction of horizontal
infrastructure for access and footprint. In addition to un-
derground drilling and hauling equipment, Atlas Copco’s Copco mobile miner machine technology.
Robbins mobile miner concept (a previous attempt at Tunnels have been excavated by drill-and-blast, tunnel
horizontal mechanical excavation) completed trials at boring machine (TBM) methods and, on rare occasions,
Mount Isa, Pasminco and Taisei. other mechanical methods. TBMs are considered advan-
Rio Tinto selected the new Atlas Copco mobile miner tageous for high speed tunneling. TBM’s provide a higher
machine concept for a number of reasons including the advance rate, a very smooth profile and a careful excavation,
use of proven technology from the three previous mobile reducing demands for rock support. The drawbacks for a
miner machines and other commercial products, as well as TBM include the cost of the machine, its limited ability to
the ability to install complete ground support typical with change profile as well as difficulties handling small curve
high rock stress conditions at approximately 1,500 to 2,000 radii. These are all aspects in which drill-and-blast has a
m (4,900 to 6,500 ft) depth. number of advantages. The TBM profile has strengths and
Atlas Copco, with support from Rowa, the Swiss weaknesses. The arched roof is a benefit, but the nonflat
company that specializes in back up systems for tunnel invert is not ideal for all applications. Cutting crosscuts and
boring machines (TBM), is advancing the detail design of branching is difficult with TBMs, and normally requires
the access version of a tunneling system on behalf of Rio extensive, extra measures. The choice between the two
Tinto. Because of the different requirements between an methods is, therefore, a complex exercise involving many
excavation system for access tunnels and that for tunnels different parameters and complex calculations.
on the footprint, two different versions of the mobile miner Based on performance estimates and observed real
machine technology were performance, a “brutal tool” is sometimes used for an initial
envisioned. The access and quick selection of the preferred tunneling method for a
the footprint versions of the normal tunnel with length L (m), diameter D (m) and rock
Sverker Hartwig and Atlas Copco mobile miner compressive strength UCS (Pa). It was found that when
Fred Delabbio machine share a major-
ity of key technologies and
using the simple formula: Q = L/ (D* 3√UCS), if the result
is a value larger than 1.5, then the TBM method has to be
Sverker Hartwig is vice president systems. Therefore, it was considered the prime candidate. If the result of the formula
Technology for Atlas Copco Construction possible to conduct a perfor- was below 1.5, then the drill-and-blast method would be
mance confirmation test us- better. The result, Q, is a sort of feasibility index, but this is
and Mining Technique, Fred Delabbio, ing a full-scale version of the just a first suggestion that must be verified through a more
member SME, is general manager access machine that would detailed analysis.
innovation - underground, Rio Tinto, also mitigate the technical Using this formula with all of its limitations, one can
Brisbane, Australia e-mail Fred. risks for the footprint ver-
sion. To alleviate confusion,
still find some conclusions. Obviously, tunnel length is
important. Capital cost is also important, as are startup
delabbio@riotinto.com, Sverker. this article focuses on the time and the first months of typical “running in” low per-
Hartwig@se.atlascopco.com. access version of the Atlas formance of a TBM tunnel. The negative influence of the

28 july 2010 Mining Engin ring


ee
MIN_028_043.indd 28 6/22/10 3:15 PM
UNDER ROUND M N N

G
I
I
G
diameter can be explained in different ways. One obvious Fig 2
way is that the cutterhead speed has to be reduced with Mini machine tunnel, circa 1970.
increasing diameters, leading to fewer meters per hour of
advance. The influence of the rock strength is remarkable.
In this formula, its weight has been reduced by the “cubic
root” function. In essence, this means that “rock hardness”
is not the “one and only” determination factor. It also points
to the fact that a hard rock TBM can cut almost any type
of hard rock, even rock as hard as 300 MPa. This is unlike
some other mechanical methods, like roadheaders, where
there is a clear limit, never to be exceeded. There may ex-
ist different opinions of exactly where the limit for road
headers is; 80,100 or 120 MPa.
july 2010_Layout 1 6/14/2010 12:47 PM Page 1
The length and diameter of the tunnel are also im-
portant. But would a number of shorter tunnels, more or
less at the same place, do the trick? Yes, but only with the
assumption that the TBM could move by itself to the next
section, in a matter of hours or days. A reasonable tunnel
size, less than 6 m (20 ft), would be ideal. Therefore, a mine
would be the perfect marketplace because there are many
tunnels, not too big, difficult rock and high stresses.
To accomplish this, a machine would have to be able to
change profile; make a flat invert; be able to back up after
ground support was installed and tunnel closure completed;
be able to make small radius curves; do cross cuts, travel by Start of the dream
itself; be easy to launch with shaft access; and also maintain The dream, as such, may very well have been around
a large part of TBM speed and gentleness to adjacent rock. for hundreds of years. In the dream, the hope for a continu-
In short, this is the basis for the “mobile miner dream.” ous mole, that is controlled remotely, with limited ventila-

STOUT
Offering a single-source supply
of all mine hoisting plant services
Locomotives
Rolling Stock
Scooptrams
Drill Jumbos
Mine Hoists
Stage Winches
Ventilation Equipment a division of Mining Equipment Ltd.

Phone: (705) 495-8587 | Fax: (705) 497-1016 | www.minehoist.com

Mining Engin ring july 2010 29


ee
MIN_028_043.indd 29 6/22/10 3:15 PM
Fig 3 “Wild ideas” like the mobile miner were not new to
Atlas Copco in any way.
A midi for White Pine and a Mini for Sidney Harbour, circa
1974.
Atlas Copco’s history in mechanical rock cutting
Even as a 130-year-old company, Atlas Copco remains
closely related to the Swedish method of tunneling. The
Swedish method is “the one man, one machine” rock drill
technique developed around the time of World War II.
These machines, having built-in rotation, tungsten carbide
bits and the pusher leg, revolutionized not only rock drill-
ing, but also Atlas Copco. However, after 10 to 15 years,
it became obvious that step-change development goes
on, and further innovations were needed. Since then, the
development has followed two directions. The first was
mechanization and later automation of the drill-and-blast
process including all unit operations, drilling, charging,
blasting, scaling, bolting and mucking.
Atlas Copco realized that there could be further tech-
nical developments that could differentiate it from other
competitors in the market. Could rock be drilled by means
other than rotary or percussive? Could these options
include microwaves, high-pressure water, thermal lances
and plasma burners? Then, the ultimate opportunity was
the possibility that the machines tried in the late 1800s, the
tunnel boring machines, would develop into something that
not only advanced drill-and-blast methods, but replaced it.
It should be noted that Atlas Copco had a research
institute in Switzerland, CERAC, that for many years
tried any possible (and some impossible) ways to make
a hole or a slot in rock. Techniques such as high-pressure
water and lasers were tried as well as rapid tunneling using
battle cruiser ship cannons. The latter works, but is rather
expensive and noisy. A couple of water jet drilling and or
slot-cutting machines were actually sold.
tion and other support and utilities, keeps on delivering a During the 1960s, Atlas Copco acquired the Swiss com-
precrushed, steady stream of high-grade ore at shaft. The pany Habegger, which became Atlas Copco TBM Machines
first ideas of how to make it true appeared in the 1970s. based in Thun, Switzerland. This company focused on use of
Primus motor here was Dick Robbins and The Robbins professor Wohlmeyer’s undercutting method that included
Company (Robbins). Robbins delivered many concepts large tungsten carbide cutting picks, running at very low
for shaft sinking, tunneling, box holing and raise boring. speed with high forces in a “get in under and rip out” type
An entirely new idea evolved using TBM-type disc cut- of operation. Many machines, some extremely successful,
ters arranged on a cutterhead enabling most of the dream were built of this type model, including the Mini and Midi,
functions. The machine type, best known throughout the as shown in Figs. 2 and 3.
world as the mobile miner (Fig. 1), has given its name to There was, however, certain rock types (particularly
any other attempt to realize something similar. Atlas Copco those with high ductility) where the machine type per-
and Robbins manufactured three machines of this type and formed poorly. Similar machines have been tried most
the latter two were still active or under manufacture when recently in the platinum industry.
Atlas Copco acquired Robbins Co. in 1993. Atlas Copco needed a machine whose performance was

Fig 4 Fig 5
The Atlas Copco shaft borer MBM, circa 1987. Robbins MM 120, circa 1992.

30 july 2010 Mining Engin ring


ee
MIN_028_043.indd 30 6/22/10 3:15 PM
more predictable and acceptable in hard rock. Table 1
So it was decided that Atlas Copco should get
involved with more classical TBM machines. Data on MM120 and MM 130 machines.
It acquired Jarva in Solon, OH. This company Mt. Isa Pasminco Taisei


had a range of successful Jarva MK x TBMs, MM 120 MM 130 MM 130


which today are difficult to beat in competent (ranging)


hard ground. Jarva further developed shield Tunnel height (m) 3.7 fixed 4.1 fixed 6.1-8.1
machines, raise boring machines (RBM) and Tunnel width (m) 4.9-7 5.5-7.9 9.0-12
some special shaft machines. An interesting Cutterhead diameter (m) 3.7 4.1 4.1
machine started to be developed in Solon, Cutterhead power (kW) 300 500 500
but finished after Atlas Copco moved this Cutterhead speed (RPM) 12.7 15 15
business to Stockholm, the mobile boring ma- Number of cutters 20 18 18
chine (MBM). Notice the similarity between Load per cutter 35 23 23
the Atlas Copco MBM from 1986 with later Stroke length (m) 0.75 0.75 0.75
developments in the business (Fig. 4). Best consistent
In parallel, with these TBM activities, performance 0.15 m/h 83 m/ month 0.5 m/h
Atlas Copco joined forces with Gbr Eickhoff
in Germany for the development of heavy
roadheading machines, which had applications in civil en- And there was the exceptionally hard rock, with a UCS
gineering projects. Not hiding the fact that a roadheader that approached 300 MPa (45 kips) in many places. The
can do remarkable jobs in softer ground, again Atlas Copco cutters became a long Golgotha walk for the machine and
entered into a situation in which it was clear that these types everything known was tried to improve the situation. Actual
of machines could not be used as a universal mining tool boring time reached an average 23 percent of total time
like drill-and-blast. with cutter changes and related issues accounting for 17
After the move of Jarva to Sweden, Atlas Copco flour- percent of total time. Adding the above three percentages
ished for 10 years in this business, developing a number 47, 23 and 17 (87 percent), it was realized that little time
of hard rock TBMs, new cutters, the variable speed drive was lost for other reasons. But, of course, being a prototype,
(VSD) technique and many more features. To further en- several small and a few large breakdowns were reported.
hance this business, Atlas Copco acquired Robbins in 1993. Also, other operational problems occurred, such as the
Atlas Copco decided to sell off the TBM part of the business machine not being able to clean the invert perfectly, so it
in 1998 and keep RBM’s and the other mining machines started to climb itself on the muck left behind.
portion. Atlas Copco has since been involved in a number There was one fundamental problem with the machine.
of more or less detailed developments of special mining A good stable classical TBM maintains the kerfs for the
machines, for shafts, narrow vein excavation and more. cutters in neat rings on the face. Simplified, all of the energy
Atlas Copco has worked actively with novel rock exca- applied to the machine goes into making fine powder of the
vation techniques since the late 1950s with noticeable and rock in these kerfs. But all the rock in between the cutter
sometimes very successful efforts. kerfs falls out free of charge. A narrow cutter and a large
spacing will, before other factors are taken into account,
Robbins/Atlas Copco mobile miners give an improved result. The mobile miner does not follow
Three machines of this type were built in the late 1980s in its own kerfs. In essence, it mills the whole face into fine
and early 1990s. They all worked with a vertical narrow dust and gets nothing for free because of its sweeping mode
cutterhead that was sumped into the rock and then in a of operation. This observation is supported by a very high
sweeping movement under rotation was swung +/- 45°. The reported specific power consumption reported in kWh/
last machine could also lift the cutter head in a “ranging” m3 for this machine compared to a TBM in similar rock.
type mode. Different configurations were tested to hold Obviously, this will influence cutter wear as well. Here, it is
the machine stationary in the drift while cutting and also clear that cutter consumption was many times higher per
to propel them forward. m3 of rock than for a conventional TBM. Add to this the
The first was a machine tried at Mt. Isa Mines, applied power to each cutter was on average almost three
Queensland, Australia, the MM 120 (Fig. 5).
This machine was followed by the MM 130 Pasminco, Fig 6
Broken Hill machine (Fig. 1). Drift cut by MM130 at Pasminco Mine, circa 1993.
The Pasminco machine made several projects and a clas-
sical picture is, of course, this beautiful drift. The last of the
three mobile miners was the Taisei MM130R. Some sum-
mary data on these three machines is outlined in Table 1.

Some observations from these machines


Given the conditions, the Pasminco machine was very
successful. Performance measured in meters/month was
handicapped by basically two circumstances. First, was an
experimental machine, it was the one that always had to
stand back when there was risk of interference with im-
portant mining operations. Therefore, average standstill
delays accounted for 47 percent of total available time.

Mining Engin ring july 2010 31


ee
MIN_028_043.indd 31 6/22/10 3:15 PM
Fig 7 construction safer and also reduce the time for construction
Robbins MM130 destined for Taisei, circa 1993. Several companies were invited to bring ideas and to
work with Rio Tinto during a concept development stage.
After a comprehensive analysis and selection process, two
tunneling concepts and one shaft-sinking concept were
selected for further detail engineering. One of the selected
tunneling machines was the Atlas Copco modular mobile
mining (MMM) machine. The MMM machine is based on
all Atlas Copco’s previous experience with the MMM.
To comply with Rio Tinto’s demands, some compro-
mises were needed from the true versatility of the original
MM concept. The new machine is much bigger and more
times higher than on a TBM, due to the fact that very few powerful than the mobile miner. On the other hand, it is
cutters at any given moment were in contact with the rock. not so flexible in changing tunnel widths or negotiating
It was clear that the cutters would become a problem. narrow turns. Instead, the machine is based on modules so
that, even if not used during one tunnel, components can be
Rio Tinto´s requirements added, or changed, to adapt the vehicle to new challenges
Rio Tinto, facing the challenge of going underground in the same mine or another mine entirely.
with block caves (less than 100 kt/d or 110,000 stpd), is fo-
cused on advancing tunnel construction systems for safety What properties is Rio Tinto looking for to be
and development rate. Due to the massive developments mastered by the Atlas Copco mobile miner
needed for starting up a block caving operation, the old machine?
expression “need for speed” is particularly well placed. For Two versions of the Atlas Copco mobile miner machine
the latter reason, Rio Tinto and Atlas Copco have several technology were envisioned. The access and the footprint
ongoing discussions and projects to speed up tunneling in versions of the Atlas Copco MMM machine share a ma-
traditional drill-and-blast operations. jority of key technologies and systems. Therefore, it was
Additionally, Rio Tinto decided to seriously develop possible to conduct a performance confirmation test using a
a step-change program in rapid mine construction that full-scale version of the access machine that would mitigate
would look at technologies, concepts and systems that the technical risks for the footprint version. In terms of
could double or more tunneling and shaft sinking speeds the access tunnels, it is ideal to have a flat invert, straight
in Rio Tinto mining operations of the future. This included or slightly curved sidewalls and a “Roman” arched roof.
a fresh look at mechanical excavation since the conditions The dimensions can vary, larger and smaller, than the base
and requirements for underground copper operations are machine that would be 5.5-m- (18-ft-) wide with a height
different to those that previous machines, such as the mobile (center) of 5.5 m (18 ft). Curve radius is less than 90 m (295
miner, had been designed for. Having a continuous excava- ft) preferably down to 30 m (98 ft). Slope should be +/- 15°.
tion process that can eliminate explosives, blast gases and Rock conditions are expected to range from 40 MPa up to
scaling of loose ground should increase worker safety by 150 MPa (in different mines). Fault and other difficult zones
eliminating risks with a process change. The other positive expected from 0-5 percent of the overall length.
aspect is the dramatic increase in development rate that The machine must have the means to handle extraor-
is possible versus drill-and-blast. The key reason behind dinarily bad rock by installing rock support at face, and
this advantage is that ground support can be installed in for all other types of rock continuous systematic bolting
parallel with rock excavation. The net result of these two and shotcrete (two layers), most of which is to be applied
factors is that Rio Tinto will have the ability to make mine between 1 and 10 m (3.3 and 33 ft) from the face. The
Fig 8 Fig 9
Cutting profile using three bottom cuts, plus five top cuts. Cutting profile using three bottom cuts and three top, out of
which two have revolving heads.

32 july 2010 Mining Engin ring


ee
MIN_028_043.indd 32 6/22/10 3:15 PM
Fig 10 need to be done to complete the face. If 3.5 cuts are needed
Cross section of cutter head. to make full width, it means four cuts. Iterating this a few
times the basic cutterhead size, power, speed and number
were established. The machine will, in normal operation,
cut the lower cuts at full depth and width. Then the whole
center part of the machine will be lifted (still horizontal,
not tilted) and three or five top cuts will be done, each with
much less cut volume than the bottom three. Actually two of
them are more “polishing” type cuts to generate the desired
arch. Examples of profiles are illustrated in Fig. 8 and 9.
This type of cutterhead has pros and cons versus a TBM.
A weakness is that only maximum half of the cutters are
active at the same time and, in the top cuts, much less. But
there are some strong points as well. All these cutters travel
with the same speed, not like a TBM where the center cut-
ters run slow and vice versa. Another strong point is that
on this drum, there is room for two cutters per kerf. On a
TBM, this is not true for the positions near the center and
that will define the rate of penetration (ROP) per revolu-
tion for the whole machine. In all, 56 cutters (two cutters
mounted in 26 positions) are installed, placed in classical
machine will be self-propelled and self-supporting with
TBM manner with angled gage cutters and “center” but
everything onboard except muck trucking from the rear
with a slight difference in the meaning of center. The cut-
of the machine. Under these conditions the machine will
terhead will have a diameter of 4.5 m (15 ft) and a cutting
perform on average 8 to 12 m/d (26 to 39 ft/d) of advance.
width of 1.8 m (6 ft). Having such a wide head provided
High in situ stresses as well as high rock temperatures are
the opportunity to mount all needed motors and gearboxes
expected in some applications.
inside the head, which avoided the complex angled drive
The Atlas Copco mobile miner machine line of the mobile miner. At the same time, power has now
The approach for the Atlas Copco proposal was to reuse been increased from the old machines 300 to 500 kW (403
the working principles of the previous mobile miners as to 670 hp) to 1,260 kW (1,690 hp). The drive system is based
much as possible. It was clear from the beginning that the on VSD technique and the speed can be altered from 0-15
machine must operate in a mode where the cutters follow rpm in both directions.
their own tracks (significant difference to mobile miners). Atlas Copco is using a fairly advanced statistical model
So, instead of swinging the cutterhead sideways when work- of the cutter loads. The model is based on extensive mea-
ing the cutterhead, it must be advanced straight or almost surements determined from individual cutter positions
straight forward. This is a partial face machine (only a por- on TBMs. In the model, each cutter presents a load as
tion of face is excavated at one time). This means that the function of time (reference to pink noise). This is math-
head has to be retracted out of the rock and then moved ematically explained with the help of rain flow statistics
sideways or vertical in the air and then sumped forward transformed into a total cutter head load in all directions
again to cover the entire drift face. In order to reduce the (time and frequency). The design criteria used thereafter
lost time for this necessary repositioning, the machine is based on an average plus a suitable number of added σ
(variance). Using this method, safety factors can be kept
should have a longer stroke than the mobile miner.
at a low number. This does not lead to a lighter machine,
The second issue that needed to be addressed was muck
but instead a heavier one.
collection in front of the machine. Roadheader aprons with
The basic concept can now be described by Fig. 10.
collector wheels/arm and chain conveyors are not free from
To the left, the cutterhead is mounted in a fork. This
problems, but were regarded as the more suitable answer
than the previous mobile miner solution. Fig 11
The third issue was related to the extensive rock rein-
forcements called for in the Rio Tinto requirements. The 3D functional view of Atlas Copco mobile miner machine.
machine had to be stretched length-wise in order to provide
enough room for rock bolting and shotcrete equipment.
The rock support must be installed simultaneously with the
rock boring. Finally, the expected performance is to reach
an average advanced rate of 240 to 360 m/month (790 to
1,200 ft/m) versus the MM130 Pasminco machine’s best
month of 83 m (272 ft). For these reasons, more power,
more cutters and a much heavier machine for stability
reasons was needed.
It can be said that the design of a machine of this na-
ture always starts with the cutters and cutterhead. Using
proven cutter technology, the size and numbers needed
will be determined rather quickly. That, in turn, leads to
a cutterhead size. Tunnel shape and cutterhead width and
diameter will define how many of these repeated part cuts

Mining Engin ring july 2010 33


ee
MIN_028_043.indd 33 6/22/10 3:15 PM
is provided all the way from the rear
Summary data - access version of Atlas Copco MMM to the final destination. Due to the
(all numbers are preliminary) expected hot ambient temperatures
Atlas Copco MMM Access Version that will be encountered, the backup
paratmeter Atlas Copco MMM Comments has extensive built in heat exchang-
mining tunneling machine ers for water, lube oil and hydraulic
Tunnel width (m) 5.3-6.3 Without change of oil. In the rear end, there exist drums
modules. for trailing cable, water hose and
Tunnel height (m) 5,25-6.1 Can be increased further ventilation duct storage.
by spacers. Apart from the normally re-
Horizontal curve radius (m) 70 /30 30 with increased tracted “emergency” bolting and
tunnel width. shotcrete boom in front of cutter
Slope (degrees) +/-15 wheel, the first set of bolts and
Cutterhead size (m) 4.5x 1.8 (Diameter x width) shotcrete is applied as soon as pos-
Cutters number and size (in) 2 x 28 x 17” sible after first gripper system (Fig.
Installed power (kVA) 2500 (6/10/16 kV) 11). The machine has two remote
Cutterhead power (kW) 1,260 at 12 RPM controlled bolt feeds. In a third ad-
Cutterhead speed (RPM) 0-15 , both directions ditional bolting station, application
Forward thrust static (kN/lbf) 3,500 / 780 000 of shotcrete and wire mesh can be
Load per cutter (kN) 183 -270 completed. Each of these stations is
Machine weight (ton) 350 separated from the other with a dust
Complete machine wall. The machine includes the latest
with backup (ton) 675 technology for emergency refuge
chamber and dust filtration system.

Performance
fork can be moved along the curved front plate +/-15°. This Rio Tinto and Atlas Copco estimate the average perfor-
movement is normally done under no load and then the mance of this technology will be between 10 to 16 m/d (33
fork is locked in position, for the left, right or center cut. The to 52 ft/d). This is based on a combination of conventional
whole yellow part, the main body with internal torque tube cutter performance from RBM’s and TBM’s combined
can within the gray gripper frames is lifted horizontally 1.5 with the results of a detailed discrete event simulation.
m (5 ft) for the upper cuts. The advance for each part cut is The simulation individual process steps of this machine,
a stroke of 1.75 m (5.75 ft) achieved by cylinders inside the along with supporting equipment, includes allowances for
yellow square tube forcing the bent front plate forward. In probe hole drilling, extending services, truck and transmixer
the side cuts, the cutterhead will, thus, advance with a small movements and all ground support activities. As rock cut-
skewed angle, but always in line with the tunnel. After all ting rates change with different rock conditions, the critical
of the six or eight cuts, the whole machine with a trailing path (rate limiting activity) will change in the process. As
backup system will move forward for next set of strokes. an example, a typical cycle in 150 MPa rock for a full ad-
The machine is modular and, as such, can use spacers vance of 1.75 m (5.7 ft), inclusive of rock support, will take
beneath the grippers to handle larger tunnels. Also, the 2 hours 45 minutes. This corresponds to 0.64 m/h (2.1 ft/
front plate can be adopted for different maxi or mini tunnel hour) instantaneous rate of penetration. When considering
widths. In any case, this machine cannot cut a lower profile factors that delay cutting and ground support activities, such
then 4.5 m (15 ft) since that is the size of the head. However, as planned and unplanned downtime, maintenance, services
larger and smaller machines can be designed using similar and trucking delays, an advance rate of 12 m/d (39 ft/d)
components. Other modules that can be added are a cut- is predicted. It is important to note that, in weaker rock,
terhead revolving unit that can tilt the head sideways +/- 30° the advance rate speed will be increase significantly. Since
and also an articulation that can be fitted between the front rock support is installed concurrently with rock excavation,
and rear grippers. These aspects enable this technology to reaching advance rates of around 16 m/day (52 ft/d) will be
ideally cover all present and future requirements of access possible, with the time required for rock support being the
and footprint excavation of horizontal infrastructure. process limiting task (critical path). n
Backup system Acknowledgments
The backup system was developed with close coopera-
This project has only been possible due to the support
tion between Rowa, Rio Tinto and Atlas Copco. It should
and vision of Rio Tinto and Atlas Copco executive and
be regarded as a full TBM backup with all such facilities. It
management teams. The technical work presented here is
is crawler based, with individually steerable crawlers mak-
the result of a large collaborative global team that consists
ing it possible to negotiate narrow curves when boring and
of members from Atlas Copco, Rio Tinto Innovation, Rio
when backing out for repositioning to a new face. Muck
Tinto Copper Projects and external consultants. The effort
is collected in front of the machine and transported to the
of many is greatly appreciated.
rear of the backup with several conveyors. The muck can
then be delivered to mine trucks or possibly into extendable
conveyor systems. The backup hosts a 2,500 kVA system for
References
Sales material and internal documentation from TRC and Atlas Copco
the MMM’s VSD and hydraulic systems, shotcrete pumps, 1960 -1999.
compressors, ventilation fans and dust suction fans. Mate- Principal Arrangement of Access Version of Atlas Copco MMM Machine
rial transportation of bolts, wire mesh, spares and cutters and Back-up System.

34 july 2010 Mining Engineering

MIN_028_043.indd
View publication stats 34 6/22/10 3:15 PM

You might also like