Provision & Hose Handling Crane 2009-07-09
OPERATING PROCEDURE
※ Trained staff must inspect all parts of the crane and required / necessary cleaning is to be
carried out before the crane is put into operation.
● Check the oil level gauge of hoisting and slewing reducer gears and the oil tank of hydraulic unit.
● Apply to grease at necessary points.
● Switch "ON" on the remote push button switch and "MCB" of main starter panel.
● Release locking devices for hook.
● Raise jib without load.
● Ensure that each limit valve is property operating without load.
● Ensure that there is nothing wrong with each motor, brake and hyd. cylinder.
※ The crane can be operated by means of the main control valves on operation platform.
All motions have step-less speed control from 0 to maximum.
Two(2) motions can be operated at the same time with maximum load, but with reduced speed.
MAINTENANCE PROGRAM
1. Introduction
The maintenance program has been developed by DMC in accordance to our supplier's own maintenance
program for each component. Conforming to this maintenance program will ensure long-time, trouble-free
- Overhaul - Replace
Lubrication : Lub.
Lubrication is identified with following :
Inspection : Insp.
Inspection is identified with the following :
Overhaul : Ovhl.
Overhaul is identified with the following :
▲ Remove the component from the unit.
▲ Disassemble the component and inspection each part.
▲ Repair if necessay :
- Bearings
Replace : R
Replace is identified with the following :
3. Maintenance Program.
Futher information
Contact : Customer service department
Tel : +82-(0)55-720-3095
Fax : +82-(0)55-720-3099
E-mail : cs@dongnam-crane.co.kr
1. General information
Following this instruction, slewing bearing rocking test should be done periodically for recording the
While operating crane continually, periodic checkup of wear of slewing bearing will prevent
2. Measurement of wear
There are two check points including the inside and outside of pedestal, but we'd like to recommend
To reduce wear of the inside of slewing bearing ball and race, it should be charged with gear oil
recommended periodically.
The max. allowable deviation(Table.1) are ones for single row ball type slewing bearing.
3. Interval of measurement
After delivery of ship, wear of slewing bearing should be checked in the basic three(3) months, and
4. Check procedure
1. When rocking testing, a checkpoint on the pedestal part should be chosen at the place to
interference, revolving sideshell or crane.
2. Measurement position should be chosen at four(4) directions by equivalent degree on the
fixed post(pedestal) parts.
3. If there is restriction of revolving area when the crane revolves, make sure to divide all angles
able to revolve into four(4) equal parts.
4. Extra red paint should be marked on the bolt checked on the fixed post(pedestal).
5. Record on the check sheet after checking regularly at the same point and direction as equipvalent
degree marked on the status of no-load and max. working radius of the crane.
6. The tool(depth gauge) which is used to check can measure like photo of Fig.1.
7. The result of periodic measurement record should be compared with the max. allowable deviation
provided by the manufacturer.
8. If new check dimension is larger than the prior record of wear, the gear oil charging cycle should
be short.
9. Please contact to customer service department of DMC if it is measured over the max. allowable
deviation of Table.1.
WARNING !
Be cautious not to operate crane as checking dimension during rocking test.