The document lists several changes between a new and old design, including:
1) The elevated floor is now visible from the sides, requiring a suspended slab foundation.
2) The entrance hall design changed from 4 piles with inclined members to an unspecified new design.
3) A basement was added.
4) A cantilevered platform slab now projects from the basement wall at ground level.
5) A circular display wall with direct foundation support replaced a slab.
The document lists several changes between a new and old design, including:
1) The elevated floor is now visible from the sides, requiring a suspended slab foundation.
2) The entrance hall design changed from 4 piles with inclined members to an unspecified new design.
3) A basement was added.
4) A cantilevered platform slab now projects from the basement wall at ground level.
5) A circular display wall with direct foundation support replaced a slab.
The document lists several changes between a new and old design, including:
1) The elevated floor is now visible from the sides, requiring a suspended slab foundation.
2) The entrance hall design changed from 4 piles with inclined members to an unspecified new design.
3) A basement was added.
4) A cantilevered platform slab now projects from the basement wall at ground level.
5) A circular display wall with direct foundation support replaced a slab.
level became visible from the sides, resulting the slab on grade will be designed as suspended slab, increasing in structural members and foundation.
2) Entrance hall is supported on 4 piles
with inclined members, please clarify? As it is a complete change from the current design.
3) Basement has been added.
4) Cantilever platform slab projected
from basement wall at the ground level.
5) Circular display wall added
supported directly to foundation due to removal slab at the circular wall.
6) Roof slopes of central building have
been refined.
7) Slopped suspended ramp with voids
at the sides instead of flat slab on grade.
Clarify the slopped platform material
proposed and the new added stub circular columns. 8) Central hallway pass extended, span increased. Additional queries 1) the cladding at the ramp areas is not continuous to the ground and the orange column will be visible, the orange columns of the ramp are not aligned below cladding, additional column will be added to be aligned below the cladding.
2) Entrance hall columns and foundation will be at the
corners inclined braces and piles not preferred.
3) Column bracing at the top of the column to be extended to the
end as shown in magenta.
4) Please confirm the basement depth 1.5m or 2.5 or 3 m from the
Ground level. 5) Please confirm ceiling required at entrance hall, exit hall and center hallway.