Duration
Project ID Task ID Name Dependencies Best
A Planning
A.100 Construction Plan 15
A.200 Hiring Plan 15
A.300 Plan Review A.100, A.200 10
B Construction
B.100 Construction: Task 1 A.300 60
B.200 Construction: Task 2 A.300 60
B.300 Construction: Task 3 A.300 30
C Review
C.100 Construction Review B.100,B.200,B.300 15
C.200 Internal Review A.300 15
C.300 Compliance Review C.100, A.300 15
C.400 Compliance / Completion C.200, C.300 15
C.500 Project Review C.200, C.400 10
Completion Date
Best Case Expected
Expected Worst Sample Start End Start
5/26/2016 146
Worst Case MC Simulation
End Start End Start End
16 44 30.0 5% 6 21%
16 44 30.0 3% 8 16%
10 28 16.7 4% 7 21%
Internal Review
100%
80%
60%
40%
20%
0%
0 7 4 1 8 5 2 9 6 3 0 7 4 1 8 5 2 9 6 3
21 21 22 23 23 24 25 25 26 27 28 28 29 30 30 31 32 32 33 34
Construc-
tion: Task
1; 6% Construction: Task 2; 11%
Construc-
tion Plan;
5%
Plan Re-
view; 4%
Project
Review; Construction Review; 21%
1%
Hiring Plan; 3%
Construc-
tion: Task
3; 0%
Internal
Review;
0%
Compliance / Completion; 25%
on Review; 21%
Review; 22%
Histogram Data Sorted R2 Values
Completion Time Probability Cumulative Index Row
210 0% 0% 11 12
217 0% 0% 10 8
224 0% 0% 9 15
231 2% 1% 8 2
238 5% 3% 7 3
245 8% 8% 6 1
252 9% 15% 5 6
259 15% 25% 4 7
266 15% 39% 3 11
273 12% 54% 2 13
280 12% 67% 1 14
287 9% 79%
294 7% 88%
301 3% 94%
308 2% 97%
315 1% 99%
322 0% 99%
329 0% 100%
336 0% 100%
343 0% 100%
Label Value
Internal Review 0%
Construction: Task 3 0%
Project Review 1%
Hiring Plan 3%
Plan Review 4%
Construction Plan 5%
Construction: Task 1 6%
Construction: Task 2 11%
Construction Review 21%
Compliance Review 22%
Compliance / Completion 25%