You are on page 1of 5

NS2PC - DVN Nghi Son 2 BOT Thermal Power Plant

FOR APPROVAL

C 07/May/2019 V.Q.TRU N.Q.HUY Y.H.KANG REVISED FOLLOWING THE OWNER’S COMMENTS

B 15/Mar/2019 V.Q.TRU N.Q.HUY Y.H.KANG REVISED FOLLOWING THE OWNER’S COMMENTS

A 18/Feb/2019 V.Q.TRU N.Q.HUY Y.H.KANG FOR APPROVAL


Rev Date Prepared Checked Approved Details of Revision
Owner

Owner’s Engineer

Contractor

DOOSAN HEAVY INDUSTRIES VIETNAM

Sub-Supplier

Project

NGHI SON 2 BOT THERMAL POWER PLANT PROJECT


(2 X 600 MW)

Title
INSPECTION AND TEST PLAN FOR
CABLETRAY INSTALLATION

Document No. Rev. Page-No.

NS2-DH01-P0ZEN-140004 C 4 pages
NS2PC - DVN Nghi Son 2 BOT Thermal Power Plant

CONTENTS

1. Inspection and Test Plans for Cable Tray Installation


2. Inspection Report for Cable Tray Installation
3. Reference Documents

Detailed Legend

S: Surveillance Point : A point where Contractor and others may carry out surveillance of
work in progress and documentation associated on an unscheduled basis, with no
notification required by any party and without amendment to the scheduled program

R : The documents are to be submitted to the appropriate inspectorate for review by Owner. Note
that work shall not proceed until Owner approval has been received.

W : That is designated to be witnessed by a specified party. The specified party must be given
reasonable advance notification prior to performing the designated operation. If the specified
party is unable to be contacted or fails to be present, the operation may be performed without
being witnessed

H : A designated stopping place during or following a specified activity at which inspection or


examination is required before further work can be performed without the approval of
designated organization or authorized personnel

NS2-DH01-P0ZEN-140004 Rev C Page 1 of 4


NS2PC - DVN Nghi Son 2 BOT Thermal Power Plant

1. Inspection and Test Plan

ID No. NS2-DH01-P0ZEN-14004

NGHI SON 2 THERMAL POWER PLANT PROJECT Rev B

Date 15/Mar/2019

TITLE: INSPECTION AND TEST PLAN FOR CABLE TRAY INSTALLATION

Inspection & Test Activities


Description of Inspection/ Test Applicable Code & Standard Reporting
No. Remarks
Process Documentation format Sub Main Owner/
Contractor Contractor Engineer
Verify material type, size, quantity and
1 Drawing/Method Statement NS2-DH01-P0ZEN-14000-4
physical damage
1.1 Verify material type, size, quantity Drawing/Method Statement NS2-DH01-P0ZEN-14000-4 H W W

1.2 Physical damage Drawing/Method Statement NS2-DH01-P0ZEN-14000-4 H W S

2 Cable Tray Installation Drawing/Method Statement NS2-DH01-P0ZEN-14000-4

2.1 Cable Tray Support Installation Drawing/Method Statement NS2-DH01-P0ZEN-14000-4 H W S

2.2 Cable Tray Installation Drawing/Method Statement NS2-DH01-P0ZEN-14000-4 H W W

2.3 Bonding & Connection Drawing/Method Statement NS2-DH01-P0ZEN-14000-4 H W S

2.4 Touch-up Painting Drawing/Method Statement NS2-DH01-P0ZEN-14000-4 H W S

Abbreviation : S: Surveillance R: Report Review W: Witness Inspection H: Hold Inspection

NS2-DH01-P0ZEN-140004 Rev C Page 2 of 4


NS2PC - DVN Nghi Son 2 BOT Thermal Power Plant

2. Inspection Report for Cable Tray Installation

OWNER INSPECTION REPORT IR No.

FOR
CONTRACTOR CABLE TRAY INSTALLATION DATE

SUBCONTRACTOR LILAMA PAGE of

PROJECT NAME Nghi Son 2 BOT Thermal Power Plant Project UNIT NO.

INFORMATION DATA

Construction PKG No. Const. PKG Name

System/Component Sys./Component ID

Drawing No./Rev. No. Drawing Title

Referent Document No. Location/Building

Verification & Approval


No CHECK ITEM Remark
Yes No N/A
1 Check that material for cable tray and support are of approved type.

2 Check for physical condition of the cable tray support and trays at receipt

3 Check that the cable tray support are install properly as per approved construction drawing

4 Check that the cable tray are install properly as per approved construction drawing

5 Check that all the bolts tightened properly and cleaning cable trays/ladders/surrounding area

6 Check that expansion joint and connection points is properly

7 Check leveling, alignment and distance between each layer of cable trays

Check that no sharp edge and check the touch-up painting on the repaired points/ cut ends of cable tray
8
( Using cold galvanizing paint )

9 Check for cable tray identification and cable tray cover installation ( if required )

12 Check interference with other assets

13 Check correct fitting used

Comments:

Sub-Contractor Contractor Owner/Owner Engineer

Full Name

Signature

Date

NS2-DH01-P0ZEN-140004 Rev C Page 3 of 4


NS2PC - DVN Nghi Son 2 BOT Thermal Power Plant

3. Reference Documents.

a. Method Statement for Cable Tray Installation, NS2-DD09-P0ZEN-140004

b. Site Quality Control Procedure, NS2-CH04-P0ZEN-040001

NS2-DH01-P0ZEN-140004 Rev C Page 4 of 4

You might also like