Ns2-Dh01-P0zen-140004 - Itp For Cable Tray Installation - Rev.c
Ns2-Dh01-P0zen-140004 - Itp For Cable Tray Installation - Rev.c
FOR APPROVAL
Owner’s Engineer
Contractor
Sub-Supplier
Project
Title
INSPECTION AND TEST PLAN FOR
CABLETRAY INSTALLATION
NS2-DH01-P0ZEN-140004 C 4 pages
NS2PC - DVN Nghi Son 2 BOT Thermal Power Plant
CONTENTS
Detailed Legend
S: Surveillance Point : A point where Contractor and others may carry out surveillance of
work in progress and documentation associated on an unscheduled basis, with no
notification required by any party and without amendment to the scheduled program
R : The documents are to be submitted to the appropriate inspectorate for review by Owner. Note
that work shall not proceed until Owner approval has been received.
W : That is designated to be witnessed by a specified party. The specified party must be given
reasonable advance notification prior to performing the designated operation. If the specified
party is unable to be contacted or fails to be present, the operation may be performed without
being witnessed
ID No. NS2-DH01-P0ZEN-14004
Date 15/Mar/2019
FOR
CONTRACTOR CABLE TRAY INSTALLATION DATE
PROJECT NAME Nghi Son 2 BOT Thermal Power Plant Project UNIT NO.
INFORMATION DATA
System/Component Sys./Component ID
2 Check for physical condition of the cable tray support and trays at receipt
3 Check that the cable tray support are install properly as per approved construction drawing
4 Check that the cable tray are install properly as per approved construction drawing
5 Check that all the bolts tightened properly and cleaning cable trays/ladders/surrounding area
7 Check leveling, alignment and distance between each layer of cable trays
Check that no sharp edge and check the touch-up painting on the repaired points/ cut ends of cable tray
8
( Using cold galvanizing paint )
9 Check for cable tray identification and cable tray cover installation ( if required )
Comments:
Full Name
Signature
Date
3. Reference Documents.