QUALITY CONTROL
Quality Control will be exercised by the representative members of the Professional Team.
The Project Managers will ensure that defects lists are drawn up by the individual members of the Design
Team at the appropriate times during construction and that the necessary rectification by the Contractor is
carried out as expeditiously as possible.
Quality Inspections
Although it is clearly the contractor’s responsibility to produce a building that complies with specification, it is
in the interest of the project as a whole that the various consultants, on a fortnightly basis, review the product
being produced by the contractor and comment on the quality aspects thereof. (To be carried out by each
Consultant in his/her own time during the 2 weeks between Main Contractor Site Meetings).
Each Consultant will be required to review those aspects of the contract works which fall under their
jurisdiction in terms of quality and provide a regular formal report (The Quality Control Report) which is to be
tabled to the contractor at the Site Meeting for action. Progress of remedial work can thereafter be monitored
by the Project Manager to ensure that any quality problems that have been raised are timeously addressed by
the contractor.
Site Inspection Meetings (To be held every other week in-between the Main Contractor Site Meetings). This
meeting will start with a short sit down meeting to confirm which issues are required to be looked at (based on
Quality Logs issued by Consultant) and then followed by a formal minuted walk through with all consultants
(Client is invited to join once per month, see Client Site Inspection Meeting below), to review those identified
items and other areas of concern or relevant progress.
Site Inspections will be held on a fortnightly basis and will be conducted and minuted by the Project
manager. These inspections will require contractor and all relevant consultants to attend (relative to the
stage of construction). The purpose of the site inspections will be to review site progress relative to
problems being experienced by the contractor as well as to review quality problems.
The Main Contractor Site Meeting – Held fortnightly to discuss formal Main Contractor contractual and
progress issues. All quality inspections are to be conducted between the fortnightly Main Contractor Site
Meeting and addressed with the contractor by the Monday preceding the meeting to ensure that all quality
issues are understood and being resolved.
The intention is that no quality issues are raised at the Site meeting, other than those that cannot be resolved
in the Monday meeting directly with the contractor. Alternatively these items will be discussed at the Site
Inspection meeting. All Consultants are required to table a Quality Control Report with associated Quality Log
at this meeting.
1|P a g e
Minimum proforma breakdown of information required in the Quality Reports expected from Consultants
every 2 weeks.
1.2. Mockups
• Required – full list of all mockups required for the next 6 months
• Approved / rejected / comments / requirements
1.3. Shopdrawings
• List of all elements requiring shopdrawing drafting and approval
• List of shopdrawings received with comments and showing approval status
2|P a g e
• Any major items on the quality log you wish to discuss in the meeting.
• Slabs finish
• zone / level inspected in the last 2 weeks
• Items requiring attention noted in Quality log on OnSiteIMS
• Any major items on the quality log you wish to discuss in the meeting.
• Columns
• Etc
• Paving
• Facebrick
• Marmoran
• Plaster (Internal / external)
• Stone packing
• Shopfronts
• Steel paint colours
• Sunscreens
• Tiling
• Waterproofing
• etc
All professionals are to ensure that they comply with the agreed quality assurance procedures and submit
their reports timeously as agreed.
3|P a g e