Professional Documents
Culture Documents
COMMENTS
Fabricator ON PRODUCTION
and Contractor Comments P
IMPROVEMENTS TO Drawings
on Engineering ENGINEERING
(DESIGN/DRAWINGS)
Prepared and Recorded for the Structural
Engineers Association of Utah
GOAL ELEVATED BC
SOG REPAIR
GOAL
Provide structural
engineers with
feedback on typical
drawing practices and
interpretation regarding
post tension fabrication
and field installation in
order to optimize
project pricing,
scheduling, and
construction efficiency.
Pricing
• Clarity
• Limited estimating resources
• Completeness
• Assumptions are conservative
• Hard Bid vs Change Orders
Costs
• Commitment
• Project management time
• Estimated Project Cycle
(Construction Team)
Project Scheduling
• Preconstruction
• Minimize Drafting Time
• Submittals and Approval
• Minimize RFI Submissions/Responses
• Forecast Production Efforts
• More flexibility inside fabrication
window
• Exposure to Price Escalations
• 2018 – Steel Tariffs
• 2020 – Antidumping Investigation
• 2021 – Antidumping duties & global
COVID recovery
Construction Efficiencies
• Forming Delays/Changes
• Inspection Delays
• Fabrication Delays
• Out of state shipping
considerations
• “Losing a day for the crew may
mean losing the crew for two
weeks.”
All while asking engineers to design
during construction.
“This is the conversation we
never get to have in the middle
of a project.”
UNBONDED
MONOSTRAND
POST TENSION
SYSTEMS
REFRESHER
Unbonded
Reinforcing strand travels freely in plastic
sleeve. Stressed and anchored once
concrete has cured to strength.
• Minimal maintenance
• ICC
• ACI
• Local codes
• PT Tendon
• Definition: a complete
assembly of a prestressing
element consisting of
anchorages and couplers,
prestressing steel, and
sheathing or duct with PT
coating for unbonded
applications.
• PT coating
lubricant/”grease”
Prestressing Steel (Strand)
• Extruded HDPE
• Watertight
• Same wedges
Hardware Systems
• Bursting bar
• Pre-slab Install
• Pre-Slab Inspection
• Concrete placement
• Tendon Stressing
• Pre-slab Install
• Slab on ground – may be installed by PT
supplier; 3rd party installation company; or
concrete contractor
• Elevated decks – typically installed by rebar
placing crews
• More complex reinforcing system; must
install with rebar
• Pre-Slab Inspection
• Verify material properties (paperwork)
• PT layout
• Tendon count
• Sheathing condition
• Tendon profiles
• Concrete placement
• Protect tendons during pour
Tendon Stressing
• PT Design
Parameters
• Translating PT
designs from
Construction
Documents
PT Slab Systems
• One-Way System
• If pre-compression &
curvature tests pass
for 2 directions, the
floor is a two-way
system, otherwise it is
a one way
PT Slab Systems
Types of Two-Way
Systems
2) Tendon Profile
PT Design Parameters
Forces in PT Tendons
• Jacking Force
• 80% of Minimum Ultimate Tensile Strength (MUTS)
• Fpu = 216 ksi
• Seating & Friction Loss
• 70% of MUTS
• Fpu = 189 ksi
• Long Term Losses
• Due to creep and shrinkage of concrete (assumed)
• Fpu = 175 ksi
PT Design Parameters
Disadvantages
LDP Specifies
• Number of Tendons
• Material Properties
• Size (Diameter) of
Tendons Required
• Minimum FEF per
Tendon for Basis of
Assumptions
PT Design Parameters
Specify Number of Tendons
and
Minimum FEF per Tendon
• If PTMS cannot
satisfy minimum FEF
requirements, what
then?
PT Design Parameters
Advantages Disadvantages
• No responsibility for
calculating losses
PT Design Parameters
Advantages Disadvantages
• PTMS can efficiently estimate and • Single set of loss properties must be
interpret construction documents assumed which allows for less
flexibility in tendon types and sizes
• Easier correlation between
construction documents and PTMS • Changes in pour break locations will
shop drawings require LDP to issue redesigned
construction documents
• Avoid rounding disputes
Translating PT Designs from
Construction Documents
• Challenges
• Missing / Vague Information
• Congestion
• Temperature Cables
• Podium Slabs
• Short Tendon Lengths
• Solutions
• RFIs
• BIM
Translating PT Designs from Construction
Documents
FROM…
Translating PT Designs from Construction Documents
TO…
TO….
Translating PT Designs from Construction
Documents
Challenges
• Summation Errors
Missing FEF
information
missing or unclear
Distributed force limits
2'-5 1/2" 1'-8 1/8" 3'-9" 7'-7 3/8"
C PRE-FAB CANOPY BY
OTHERS (TYPICAL)
4-#5 CONTINUOUS REF 16/S6.02
0 6 / S 3 .0 2
F= 5 6 3 K
PERIMETER BARS SEE C
1 1 3 /8 "
6 .0 0 "
F= 6 9 7 K
F= 5 3 6 K
F= 5 3 6 K
F= 6 9 7 K
1 '- 1 1 7 / 8 "
03/S3.01
6 .0 0 "
4 .5 0 "
4 .5 0 "
4 .5 0 "
3 '- 1 3 / 8 "
3 1/2"
4 '- 3 7 / 8 "
2 '- 4 "
3 1 /2 "
3 1 /2 "
SR-C1
SR-E3
4 .5 0 "
4 .5 0 "
6 .0 0 "
6 .0 0 "
4 .5 0 "
F=30.4 K/FT
4.50" 11.00" 11.00" 11.00" 6.00"
0 6 / S 3 .0 2
13/S3.0 2
3 .0 0 "
6 .0 0 "
6 .0 0 "
4 .0 0 "
4 .0 0 "
6F .=0 0 1" 3 4 1K 3 '- 1 7 / 8 "
3 1 /2 "
Challenges
Documents
7'-7 1/8"
1 1 .0 0 "
1 1 .0 0 "
1 1 .0 0 "
1 1 .0 0 "
1 1 .0 0 "
F=27.8 K/FT
6.00" 11.00" 11.00" 11.00" 11.00"
6.00" 1.00" 4.00" 4.00" 2.00" 4.00"
0 2 / S 3 .0 3
5 .0 0 "
5 .0 0 "
5 .0 0 "
6 .0 0 "
6 .0 0 "
HAIRPINS PER
09/S3.01 (TYP.)
4-#5 CONTINUOUS
PERIMETER BARS SEE
03/S3.0 1
T-9 -5
4'-2" 5'-1"
1 1 .0 0 "
1 1 .0 0 "
1 1 .0 0 "
Summation Errors
Translating PT Designs from Construction
Documents
Challenges
H
S3.02
t op cover t o CGS = 6 t op cover t o CGS = 6 t op cover t o CGS = 6
G
S3.02
t op cover t o CGS = 2.13 t op cover t o CGS = 2.13 t op cover t o CGS = 2.13 t op cover t o CGS = 2.13
information vague
bot t om cover t o CGS = 1 bot t om cover t o CGS = 1 bot t om cover t o CGS = 1
=1
CGS
er t o
m cov
bot t o
1 A
Congestion
• Slab
B C
6 "
Congestion
• Slab Edge
1 0 "(+ )
1 3 S P A @
5
9.88
Challenges
Documents
8.5
t op c
1.25
Fe = 125 KIPS/ft
1.25
12'-0" NOTE 7
Translating PT Designs from Construction
t op cover t o CGS = 3
9
21
CC
1
2 C
Translating PT Designs from Construction
Documents
Challenges
Congestion
• Beams
Translating PT Designs from
Construction Documents
Challenges
Temperature PT Cables
• PT Details
Translating PT Designs
from
Construction Documents
Challenges
Podium Slabs
• Depressed areas and steps in slab soffits
• Conflicts between the profile and where the
steps occur
• Can lead to…
• Blowouts in the concrete
• Cracks due to unintended reverse
parabolas
• Important to be clear on construction
documents and show exactly where the slab
steps for PTMS
• The more details, the better!
Translating PT Designs from Construction
Documents
Challenges
Podium
Slabs
Translating PT Designs from Construction
Documents
Challenges
Podium
Slabs
Translating PT Designs from Construction
Documents
Challenges
H
6 S3.0 2
16
6
.=
6
.=
.=
.=
.=
.=
T.C
T.C
T.C
T.C
T.C
T.C
t op cover t o CGS = 6 t op cover t o CGS = 6 t op cover t o CGS = 6 t op cover t o CGS = 6
40 0 KIPS
200 KIPS
G
4 E NOTE 9
S3.0 2
5
1.2
bot t om cover t o CGS = 1.25
.=
B.C
bot t om cover t o CGS = 1.25
.9
.9
.9
9 .8
5
13
13
15
1.2
.=
.=
.=
.=
6 0 0 Kips
.=
T.C
T.C
T.C
T.C
B.C
bot t om cover t o CGS = 1.25 t op cover t o CGS = 2.13 t op cover t o CGS = 2.13 t op cover t o CGS = 2.13 t op cover t o CGS = 2.13
t op cover t o CGS = 2.13
8
9 .8
9 .8
5 E 5 E
.=
.=
T.C
T.C
t op cover t o CGS = 2.13 5 D
bot t om cover t o CGS = 1.25
.9
5
5
C1
1.2
1.2
1.2
27
.=
.=
.=
.=
B.C
B.C
B.C
T.C
t op cover t o CGS = 3.75 bot t om cover t o CGS = 1.25 bot t om cover t o CGS = 1.25 bot t om cover t o CGS = 1.25
.25
S=1
t o CG
cove r
bot t om cover t o CGS = 1 bot t om
4 E NOTE 9 1.25
bot t om cover t o CGS 1.25cover t o CGS =
bot=t om
bot t om cover t o CGS = 1.25
.3
1 A
519
B.C
t op cover t o CGS = 2.13
.=
.=
T.C
1.2
140 0 KIPS
5
Podium
S3.0 2
.9
C8
.9
.9
24
25
10
13
13
.=
.=
.=
.=
.=
.C
T.C
T.C
T.C
T.C
t opTcover t o CGS = 5.5 t op cover t o CGS = 2.13 t op cover t o CGS = 2.13 t op cover t o CGS = 2.13
t op cover t o CGS = 2.13
= 2.13 J
.9
t o CGS
t op cover
13
.=
S3.0 2
T.C
C1 t op cover t o CGS = 2.13
TYP
5
5 E 5 E
1.2
.=
4 E NOTE 9
B.C
Slabs
5 E
5
5
5
1.2
1.2
1.2
.=
.=
.=
B.C
B.C
B.C
12
5
bot t om cover t o CGS = 1.25 bot t om cover t o CGS = 1.25 bot t om cover t o CGS = 1.25
1.2
.=
t o CGS = 1.25
T.C
.=
CGScover
bot t om coverbott ot om = 1.25
bot t om cover
B.C
bot t om cover t o CGS = 1.25
16 00 Kips
1500 Kips
16 75 Kips
70 0 Kips
5
1.2
4 E NOTE 9
.=
B.C
.9
.9
.9
21
12
13
15
.=
.=
.=
.=
T.C
T.C
T.C
T.C
12
t op cover t o CGS = 12 t op cover t o CGS = 2.13 t op cover t o CGS = 2.13 t op cover t o CGS = 2.13
.=
T.C
G 5 E
4 D
4 E S3.0 2
NOTE 9
5
5
5 1.2
1.2
1.2
1.2
5
5
1.2
.=
.=
.=
1.2
.=
B.C
B.C
B.C
.=
B.C
.=
G P 6
6 P
S3.0 3
8
8
S3.0 2
8
9 .8
9 .8
9 .8
9 .8
8
8
9 .8
S3.0 3
9 .8
.=
.=
.=
.=
T.C
T.C
T.C
T.C
.=
.=
T.C
t op cover t o CGS = 6 t op cover t o CGS = 6 t op cover t o CGS = 2.13 t op cover t o CGS = 2.13
6 6
6
6
.= .=
.=
.=
.=
t opT.Ccover t o CGS = 6 T.C
T.C
T.C
T.C
t op cover t o CGS = 6 t op cover t o CGS = 6 t op cover t o CGS = 6
CMU
V 6 V 6 V 6
S3.0 3 S3.0 3 S3.0 3
Translating PT Designs from Construction
Documents
Challenges
Podium
Slabs
Translating PT Designs from Construction
Documents
Challenges
South R1 South R2 South R3 South R4 South R5 South R6 South R7 South R8 South R9 South R10 South R11 South R12 South R13 South R14 South R15
Podium NO R15 NO R14 NO R13 NO R12 NO R11 NO R10 NORTH R9 NORTH R8 NORTH R7 NORTH R6 NORTH R5 NORTH R4 NORTH R3 NORTH R2 NORTH R1
Slabs
SOUTH P1 SOUTH P2 SOUTH P3 SOUTH P4 SOUTH P5 SOUTH P6 SOUTH P7 SOUTH P8 SOUTH P9 SO P10 SO P11 SO P12 SO P13
NO P13 NO P12 NO P11 NO P10 NORTH P9 NORTH P8 NORTH P7 NORTH P6 NORTH P5 NORTH P4 NORTH P3 NORTH P2 NORTH P1
Translating PT Designs from
Construction Documents
Challenges
Podium Slabs
• Pour Breaks
FEF due to seating loss TENDON NO. JACKING LIFT OFF 3 7/8 END1 END2 TOTAL % % VARIANCE
• Why? 1
2
5350
5350
0
0
3 7/8
3 7/8
4
4
4
4
103.23%
103.23%
3.23%
3.23%
• Shorter Tendon Length = 3 5350 0 3 7/8 4 4 103.23% 3.23%
Shorter Tendon Elongation 4
5
5350
5350
0
0
3 7/8
3 7/8
4 1/2
4
4 1/2
4
116.13%
103.23%
16.13%
3.23%
• Elongation Reports 6
7
5350
5350
0
0
3 7/8
3 7/8
4
4
4
4
103.23%
103.23%
3.23%
3.23%
• Short tendons elongations 8 5350 0 3 7/8 4 4 103.23% 3.23%
9 5350 0 3 7/8 4 4 103.23% 3.23%
usually outside the design 10 5350 0 3 7/8 4 4 103.23% 3.23%
tolerance 11 5350 0 3 7/8 4 4 103.23% 3.23%
12 5350 0 3 7/8 4 4 103.23% 3.23%
• Verify gauge pressure at 13 5350 0 3 7/8 4 1/4 4 1/4 109.68% 9.68%
time of stressing over 14 5350 0 3 7/8 4 4 103.23% 3.23%
elongation
• Investigate mild reinforcing
design alternatives
Translating PT Designs from Construction
Documents Solutions
SUPERIOR POST TENSION, LLC RFI #:
1179 CENTER POINT DRIVE
HENDERSON, NV 89074 RFI DATE:
Office (702) 565-7866 Fax (702) 565-1886
NV License #75576 AZ License #269973 JOB #:
REFERENCE:
SCOPE:
• What is BIM?
using Tekla
Translating PT Designs from Construction
Documents Solutions
• Preconstruction
Planning
• Post Tension
Installation & Inspection
• Typical
Challenges/Solutions
Tendon Information - Bidding
• Tendon Count
• Tendon Length
• Hardware System
(Bare/Encapsulated)
• Spacing
• Elongation
PTI ELONGATION
TABLE
Installation
• Place tendons and hardware
• Sweep tendons as needed
Inspection
• Verify material properties
• Hardware system
• Sheathing condition
• Spacing & Clearance
Stressing
• Provide current calibration
sheets
• Visually inspect for
honeycombs or uncured areas
• Mark tendons for elongation
measurements
• Place wedges for stressing
• Stress tendons to gauge
pressure
• Cut and cap tails & patch
grommet hole
Inspection
• Witness gauge reading
• Complete stressing &
elongation form
• Measure elongations
MOST COMMON OBSTACLES
GENERAL
PLANS INSPECTORS LIFT OFFS
CONTRACTORS
Plans
• Self-perform Concrete
Lift Offs
• Performed to verify the force on the stressed
tendon
• Components
• Types of Systems
• Design
Considerations
• Strand
Components • Anchorages
• Cast in Place Inserts
Strand
Typically
• ½” Diameter
• 250 ksi
• Barrel Anchors
• Grabb-It Anchors
Cast In Place • Pocket Former with PVC
Inserts • Grabb-It Rail
• Surface Mount System
Types of Systems • Interior System Through Columns
Design
Considerations
• Designed to resist a single
point load of 6,000 lbs
applied horizontally in any
direction to system
• Load area of 1 square foot
applied at 18” and 27”
above surface of floor
• Horizontal deflection
typically should not exceed
18”
• Why?
• Anchorages must be
capable of transmitting the
loads from vehicle impact
to the structure
Design
Considerations
How does a vehicular barrier cable
system fail?
• Anchorage System
• Cable Deflection
• Cable Failure
• Stub Columns on PS
Roofs
• Examples
Causes
• Pre-pour
• Short Strand (coupler)
• Anchor Damage
• Sheathing Damage
• Kinked Strand
• Rebar Congestion (to prevent blow out)
• Post-Pour
• Concrete failure
• Blowouts, honeycombing, voids,
consolidation
• Broken tendon
Site Conditions
• Pre-pour
• Open Slab
• Continuous Tendon (Intermediate
Anchorage)
• Post-pour
• Concrete Conditions
• Accommodate Repair Hardware
• Interior Aesthetics
• Access/Schedule
Solutions
• Pre-pour
• Short strand
• Splice additional tendon length
• Necessary if in second pour
• Replace tendon
• Anchor damage
• Remove and field-affix
• 18” – 24” tail will provide adequate
length
• Sheathing Damage
• Restore coating
• Waterproof tape for minor damage
• Waterproof Tape + Split Tubing for major
• All sheathing must be continuous for
encapsulated systems
• Kinked strand
• Replace -- splice unto existing strand if
appropriate
Sheathing
Repair
Solutions
• Post-Pour
• Concrete failure
• Blowouts, honeycombing, voids, inadequate consolidation
• Broken tendon
• Penetrations, corrosion, etc
• Abandon Tendon
• Remove and rethread new tendon
• 0.5” or 7/16” strand for repair
• Endspan Repair
• Midspan Repair
• Remove and rethread new tendon
• 0.5” or 7/16” strand for repair
• End Span Repair
• Anchor replacement
• Midspan Repair
• Splice Chuck
• Dog Bone
• Consider hardware dimensions
• Congestion
Summary
• Continuing Education
• PTI resources
REFERENCES
• Aalami, Bijan O. “One-Way and Two-Way Post-Tensioned
Floor Systems.” PTI Technical Note Issue 3, October 1993.