You are on page 1of 2

1.

Define the difference between Construction Management and Project Management

Construction Management

1- Construction Management mainly focuses on managing construction work.

2- Construction managers have less responsibility than project managers

3- Construction managers only look after the construction work within the organization.

Project Management

1- Project management mainly focuses on managing project work.

2- Project management has more responsibilities than construction managers.

3- Project managers must also pay attention to the food chain in the organization.

Cost Codes are defined as:

The cost code identifies a specific task within a job. The cost type identifies specific costs within the
activity, such as labour or materials and equipment. Cost codes are numerical labels placed on all the
tasks and items related to a project & allowing you to understand where money is being allocated
quickly.

Cost coding systems vary widely in structure and complexity based on the needs of the organization
and the specific requirements of the job at hand.

4. Identify the Five Schedule Levels

Schedules are typically developed from the top to down and maintained from Level-4 up. Level 5
schedules are temporary documents based on the Look-ahead schedule and used to coordinate work
in an area.

Level 1 Schedule: Executive Summary

Level 2 Schedule: Management Summary

Level 3 Schedule: Project Coordination Schedule (integrated rollup of level 4)

Level 4 Schedule: Execution Schedule (Project Working Level Schedule)

Level 5 Schedule: Detail Schedule (breakdown of activities)


What are Schedule Types?

The schedule develops as the project moves from its early conceptual phase into the execution
phase.

Conceptual

When the scope of the project is being determined, a simple schedule that shows the major tasks
and approximate start and end dates is developed to allow senior management to make decisions
about the scope of the project. Detail is not required at this stage because entire tasks might be
dropped from the scope, or the whole project might not be approved.

Master

If the project is chosen, a master schedule is created. It has major events and dates such as the
starting date and the completion date. The master schedule is often part of a contract. Changes to
the master schedule must be approved using a documented change process with approval by the
project sponsor and client.

Detail

To execute the master schedule, the major activities are broken down into smaller activities and
resources are assigned to those activities. The most detailed versions or portions of the schedule
may be developed a few weeks prior to the execution of those activities and are called two-week
plans. Portions of the master schedule that affect particular vendors might be sent to them so they
can provide detailed activities that they would perform.

You might also like