RAB Pekerjaan Area MEM PTVI

Pek. Bongkar dan Pasang Rangka, Atap Area OIL Trap QTY Remark
1 Pasang Scaffolding & Life Line 12 Bay lief Rp - By VALE
2 Pembongkaran Atap Lama Rp 88,409 144 m2 Rp 12,730,919 By Contractor
3 Fabrikasi (Brash, Welding) Rp 22,500 1700 Kg Rp 38,250,000 By Contractor
4 Bongkar Rangka Atap, Gording, Kaso (Oxy, Acyteline) Rp 99,960 144 m2 Rp 14,394,286 By Contractor
5 Painting Rp 6,750 1700 Kg Rp 11,475,000 By Contractor
6 Erection Rp 11,250 1700 Kg Rp 19,125,000 By Contractor
7 Pasang Atap dan Rangka Rp 285,601 168 m2 Rp 55,540,953 By Contractor
8 Pembersihan Area Rp 14,280 168 m2 Rp 2,399,048 By Contractor
9 Mob demobilisasi Material Rp 880,000 30 Hour Rp 26,400,000 By Contractor
Rp 180,315,206
Pekerjaan Atap Bocor Area Kantor
1 Pemasangan Scaffolding & Life Line Bay lief Rp - By VALE
3 Pembongkaran Atap Lama Rp 88,409 60 m2 Rp 5,304,550 By Contractor
4 Erection Rp 44,132 60 m2 Rp 2,647,932 By Contractor
5 Pemasangan Atap Rp 200,601 60 m2 Rp 12,036,055 By Contractor
7 House Keeping Area Rp 20,060 60 m2 Rp 1,203,605 By Contractor
8 Mob demobilisasi Material Rp 880,000 16 hour Rp 14,080,000 By Contractor
Rp 35,272,142
Pek Penggantian Atap Area Kolam Remark
1 Pasang Scaffolding & Life Line Rp - 8 Bay Lief Rp - By VALE
2 Bongkar Atap Lama Rp 88,409 156 m2 Rp 13,791,829 By Contractor
3 Fabrikasi Rp 22,500 820 Kg Rp 18,450,000 By Contractor
4 Erection Rp 11,250 820 Kg Rp 9,225,000 By Contractor
5 Pemasangan Atap Rp 200,601 156 m2 Rp 31,293,742 By Contractor
6 Pembersihan Area Rp 10,030 156 m2 Rp 1,564,687 By Contractor
7 Mob demobilisasi Material Rp 880,000 16 Hour Rp 14,080,000 By Contractor
Rp 88,405,259