განმარტებითი ბარათი A4

სასტუმრო "ტრაიბი" გვერდი - 1


თარიღი 2023
შ.პ.ს
მისამართი: ქ.თბილისი , ქეთევან დედოფლის წამებულის გამზირი #46ბ, #48,#50
„UGT“
ინჟინერი: ერეკლე ესტვირიშვილი ხელმოწერა

wyalmomaragebis sistemebis

proeqtirebisaTvis gankuTvnili ganmartebiTi baraTi.

PLUMBING SYSTEM

DESIGN REPORT & SPECIFICATIONS

გამოყერნებული სტანდარტები და ნორმები:


CODES AND STANDARDS OF WORKS
 saqarTveloSi momqmedi saproeqto normebis.
 arqiteqturul-teqnologiuri naxazebis monacemTa bazebis mixedviT
 According to Terms of Reference assigned by the Client
 According to georgian local regulation
 Climatic conditions of Georgia
 According to the databases of architectural technological drawings
 Technical Requirements - Tribe Hotel Accor
 ASHRAE:American society of heating, refrigerating & air conditioning Engineers, USA
 ASME: American society of Mechanical engineers, USA
 AMCA: Air movement and control association, USA
 ASTM: American society of testing materials, USA
 AWS: American welding society, USA
 HI: Hydraulic Institute, USA
 ANSI: American National standards Institute, USA
 CIBSE:Chartered Institute of Building services Engineers, UK
 BS 6700 Design, installation, testing and maintenance of services supplying water for domestic use
within buildings and their Cartilages
 BS EN-806 Specifications for installations inside buildings conveying water for human consumption
 Plumbing Engineering Services Design Guide. International Plumbing Code
განმარტებითი ბარათი A4
სასტუმრო "ტრაიბი" გვერდი - 2
თარიღი 2023
შ.პ.ს
მისამართი: ქ.თბილისი , ქეთევან დედოფლის წამებულის გამზირი #46ბ, #48,#50
„UGT“
ინჟინერი: ერეკლე ესტვირიშვილი ხელმოწერა

ცივი და ცხელი წყლის დგარები მოთავსდება სპეციალურად მოწყობილ შახტებში, საიდანაც წყალი მიეწოდება
შიდა ქსელს. შემყვანზე ტექნიკურ ოთახში გათვალისწინებულია წყალმზომის კვანძი. შენობაში არსებული სან-
კვანძებისათვის გამოყენებულია ცივი წყლის პლასტმასის d 20-63მმ მილები და ფასონური ნაწილები. შენობის
ცხელი წყლით მომარაგება ხორციელდება სახურავზე განთავსებული საქვაბის სისტემიდან სადა განთავსებული
წყალტევადობითი გამაცხელებლები. ცხელი წყლის სისტემაში გამოყენებულია ცხელი წყლის პლასტმასის d 20-
63მმ მილები და ფასონური ნაწილები.. ცხელი წყლის მილები მოეწყობა ცივი წყლის პარალელურად. შენობაში
წყალმომარაგება ხორციელდება სარდაფის ნიშნულზე განთავსებული წყალმომარაგების სატუმბო სადგურის
სისტემებიდან. უწყვეტი წყლის ზრუნველყოფისთვის სარდაფის დონეზე არის 40 ტ მოცულობის
წყალმომარაგების უჟანგავი ლითონის ფურცლებისგან შემდგარი მოდულური ანაკრები ავზი. შენობაში
წყალმომარაგება ხდება საფეხურებრივი სატუმბი სადგურით ან/და ბაიპასით (შემოვლით) პირდაპირ
წყალმომარაგების ქსელზე მიერთებით იმ შემთხვევებში როდესაც ქალაქის წყალმომარაგების ქსელში წყლის
წნევა არანაკლებ 4 ატმ არის. ცივწყალმომარაგების მილად გათვალისინებული არის გათვალისწინებული არის
PP (პოლიეთილენის მილები) PEX-a ტექნიკური მახასიათებლებით. დასაშვებია ასევე PPR (პოლიპროპილენის
მილები) PEX-B ტიპის . მილის ნომინალური წნევა არ უნდა იყოს 16 ატმ ნაკლები წნევის მედეგობის
რეკომენდირებული არის PN20 წნევის ნომინალის მილები. არმირება ცივწყალმომარაგების მილებისთვის
აუცილებელი არ არის ხოლო ცხელწყალმომარაგების მილები აუცილებლად უნდა იყოს არმირებული.
წყალგამყვანი მილების სისტემა დათბუნებული არის ნიტრილის რეზინის 20 მმ სისქის EN 14706, EN 14707 და
EN 14304 სტანდარტების შესაბამისად თბოგამტარობა λ 0º = 0.033 = W/(m · K) თბოიზოლაციით. ცივი წყლის
მილი ადის სახურავზე არსებულ ცხელწყალმომარაგების ავზებში რომელებიც აღჭურვილის მილღრუიანი
თბომცვლელებით. ერთი მაღალპოტენციური ენერგიის ხოლო მეორე დაბალპოტენციური ენერგიის მისაღებად.
ცივი წყალი გაივლის ჩქაროსნულ ბოილერს და გაცხელებული შედის პარალელურად სამივე წყალტევადობით
ცხელწყალმომარაგების ავზში. საიდანაც მიედინება შენობის ცხელწყალმომარაგების ქსელში. ცხელი წყლის
ონკანში სწრაფად მისაღებად გამოყენებულია ცხელწყალმომარაგების რეცირკულაციის კონტურები რომელიც
პარალელურად უერთდება სამივე ცხელწყალმომარაგების წყალტევადობით ბოილერს. ბოილერები
აღშურვილია ელ ტენის ჩაყენების შესაძლებლობით. რეცირკულაციის ტუმბო აღჭურვილია მშრალი სვლის
დაცვის კონრაქტორით.
ცხელი წყლის დარეზერვება ხორციელდება 60°-70°C, შენობაში ცხელი წყლის ტემპერატურა მაქს 40-50°C,
ცხელი,ცივი და ცირკულაციის წყლის მილგაყვანილობა შეფუთულია, ცხელწყალმომარაგების აცირკულაციო
სისტემისთვის დაპროექტებულია საბალანსო ვენტილები . წყალმომარაგების სისტემის ხარჯია:
ცივი წყალი: (+10% პერსპექტივის გათვალისწინებით) V=5,1 L/s - ∅90 პლასტმასის მილი PN16
წყალმომარაგერბის სისტემებში გათვალისიწნებულია შემდეგი რისკები:
 არ ხდება ლეგიონების ან მიკრობების გაჩენის საშიშროება
 არ მოხდება დაბინძურებული წყლის მოხვედრა წყალმომარაგების სისტემებში
 წყალმომარაგების მილგაყვანილობა არ უნდა იყოს ელექტრო მაომარაგების ქსელთან ერთად
 ცივი და ცხელი წყლით უწყვეტ რეჟიმში მომარაგება ხორციელდება მთელს შენობაში

წყლის ხარჯები
განზ. რ- ხელს დღე-ღამეში საათში ხელსაწყო,
მომხმარებელი ხელსაწყო, q0
ერთეული ბა . ლ/დღ.ღ. , qu ლ/სთ qhr, u q0, hr
tot c h tot c h tot c h tot c h
საცხოვრებელი მაცხოვრებელ 0, 18 18
350 540 200 100 100 22,4 12 10,4 0,3 0,2 250
კორპუსი ი 2 0 0
განმარტებითი ბარათი A4
სასტუმრო "ტრაიბი" გვერდი - 3
თარიღი 2023
შ.პ.ს
მისამართი: ქ.თბილისი , ქეთევან დედოფლის წამებულის გამზირი #46ბ, #48,#50
„UGT“
ინჟინერი: ერეკლე ესტვირიშვილი ხელმოწერა

q, q hr, q d,
q m, q qh
P a ლ/ წ Р hr a hr მ3/ს მ3/დღ. Q hr Qm Qs
მ3/სთ cir cir
მ თ ღ
0.01 4.9 0.05 12.2
საერთო 3.294 9.797 2.917 70.000
3 41 8 46
0.01 2.8 0.04 6.98 2.5 290.3 67.66 431.57
ც.წყლ 2.837 7.763 1.458 35.000
1 37 3 7 77 02 7 7
ცხ.წყლ(ზაფხ 0.01 2.5 0.05 6.25 2.5 362.8 84.58 539.47
2.577 6.952 1.458 35.000
ული) 4 77 5 7 77 77 3 2
ცხ.წყლ(ზამთ 0.01 2.5 0.05 6.25
2.577 6.952 1.458 35.000
არი) 4 77 5 7
წყალარინება( 5.2 12.2
2.917 70.000
Стоки) 41 46

შენიშვნა:
წყალმომარაგების ჭის ადგილდებარეობა შეთანხმებული უნდა იყოს „საქართველოს გაერთიანებული
წყალმომარაგების კომპანია“- სთან.
წყალმომარაგების მილგაყვანილობის მონტაჟის შემგომ აუცილებელია, სამონტაჟო კომპანიის მიერ
განხორციელდეს მისლადანების სიმტკიცისა და ჰერმეტულობისთვის გამოიცადოს ჰიდრავლიკური ხერხით,
(ან პნევამტიკური ხერხით) სამეურნეო-სასმელი წყალმომარაგების მილსადენები და ნაგებობები,
ექსპლუატაციაში მიღების წინ ექვემდებარება გარეცხვას (გასუფთავებას) და დეზინფექციას ქლორირებით,
შემდგომი გარეცხვით, წყლის დამაკმაყოფილებელი სამეურნეო-სასმელი წყალმომარაგების მილსადენების და
ნაგებობების გარეცხვა და დეზინფექცია უნდა მოხდეს სამშენებლო-სამონტაჟო ორგანიზაციის მიერ, რომელიც
ასრულებს მილსადენების და ნაგებობების გაყვანისა და მონტაჟის.სამეურნეო – სასმელი წყალმომარაგების
მილსადენებსა და ნაგებობებზე ჩატარებული გარეცხვისა და დეზინფექციის შედეგებზე უნდა შედგეს სათანადო
აქტი.

PLUMBING SYSTEM

Domestic Cold Water Production & Distribution


The building will get domestic and firefighting water need from city network.
The incoming city main water :

Cold Water Capacity Total: V=5.6L/s - ∅90 PP PN16

Water Tank Capacity Calculation


Daily Domestic Cold Water Consumption (according to Feurich/DIN)

Domestic water storage is calculated for 1,0 day. According to the calculation minimum storage
Water Tank Capacity: 2 x V=20m3

For cold water design flow rates, flow pressures and fixture units (FU), following table
(from EN 806-3 used.
განმარტებითი ბარათი A4
სასტუმრო "ტრაიბი" გვერდი - 4
თარიღი 2023
შ.პ.ს
მისამართი: ქ.თბილისი , ქეთევან დედოფლის წამებულის გამზირი #46ბ, #48,#50
„UGT“
ინჟინერი: ერეკლე ესტვირიშვილი ხელმოწერა

Hotel Room areas’ domestic hot water will be produced by DHW tank in necessary fixtures.

Hot Water Capacity Total: V=3.2L/s

Calorifier Coil Heat Capacity;


Q= V x c x ρ x (tç-tg) (kW)
V : Hot Water Demand (l/s)
c : Specific Heat of Water (kj/kg ͦ C)
ρ : Density of Water (kg/l)
tç : Water Outlet Temperature ( 55 ͦ C )
tg : Water Inlet Temperature ( 10 ͦ C ) Q= 500 (kW)
Water Supply
The design of the water pipes shall be based on the diversified load for fixtures used intermittently on
the system. Pipe size shall be determined by the loading unit method.
Design Goals
The water supply system shall be designed to:
• Conserve domestic water.
• Reduce energy for heating water.
• Provide complete water supply service and usage.
The goals are achieved through plumbing fixtures designed for low water consumption, automatic
faucets and dual flushing devices and other methods

• The required daily rate of consumption for the restaurant meals shall comply with the requirements of
the BS 6700-Design, installation, testing and maintenance of services supplying water for domestic use
within buildings and their Cartilages (ie: 8 liters/meal).
• Pipe sizing and flow rate calculations shall comply with BS EN 806-3.
Domestic water system minimum water pressures shall be 2.5 to 3.5 bar at point of usage and min 3.5
bar at kitchen.

Piping Insulation
Domestic water piping insulation shall be be in accordance with the following table :
Insulation Insulation
Service Pipe Size
Material Thickness
Elastomeric
Domestic Cold Water 15-32 mm 9 mm
Rubber
40-150 mm 13 mm
Domestic Hot Water 15-100 mm Glass Fibre 25 mm

All pipe work, fittings and accessories shall be installed strictly in accordance with the manufacturer's
recommendations and due allowance made for thermal movement.

All pipe work, fittings and accessories shall be obtained from one manufacturer only, who shall be nominated by the
contractor in writing and approved by the Consultant prior to ordering any materials. Materials from different
განმარტებითი ბარათი A4
სასტუმრო "ტრაიბი" გვერდი - 5
თარიღი 2023
შ.პ.ს
მისამართი: ქ.თბილისი , ქეთევან დედოფლის წამებულის გამზირი #46ბ, #48,#50
„UGT“
ინჟინერი: ერეკლე ესტვირიშვილი ხელმოწერა

manufacturers shall not be incorporated into the system. All pipe work, fittings and accessories shall be stored in
properly ventilated well-supported racked storage sheds.

All pipe work shall be erected to present a neat and orderly appearance arranged to or at right-angles to the structural
member of the building, giving maximum headroom and not obstructing window or doorways. Pipes shall bend round
piers, projections and into recesses forming part of the structural works whether so indicated on the drawings or not.
Pipe work shall be erected such that there is a minimum of 50 mm clear below to the finished floor level and at least
25 mm clear to the finished wall face.

The pipe works, which are to be insulated, contractor shall allow space for each pipe around its whole circumference.
Adequate clearance shall be provided between insulated pipe work running together and adjacent to walls and floors.
Clearances between insulation and floor and insulation and wall shall be as for bare pipe work.

No joints shall be formed in the thickness of walls, floor slabs or roof slabs. No pipe work shall be chased into floor
slabs, roof slabs or walls. During the installation period open ends of pipe work shall be capped off using purpose-
made plugs or blank counter-flanges. Pipe work shall be kept free of dirt and other foreign debris at all times.

All pipe work fittings, valves and other components forming the piping installation shall be erected such that they can
be dismantled and are accessible for repair and replacement. Where valves and equipment are fitted, unions and
flanges shall be provided as appropriate for the diameter pipe work in order to allow valves and equipment removal.

All pipe work shall be erected such that it may be vented and drained satisfactorily. All low points in the system shall
have drain cocks fitted and high points shall have air bottles or automatic air vents.

Cold Water Storage


The water supply to the project shall be obtained from the existing water wells and stored in modular water storage
tanks at the lower level plantroom. Accordingly, the water storage will be split into:
• Domestic water tank
• Filtered water tank
The filtration of the domestic water will consist of filter units, filtration pumps (duty/standby) and
controls. The raw water shall be taken from the raw water tank, filtered and pumped for storage inside

Cold Water Distribution


The cold water shall be distributed via boosted water supply from the filtered tank to cold water risers.
Water distribution shall be regulated and maintained throughout the project to meet acceptable levels
The design for cold water pipes shall be based on the diversified load for fixtures used intermittently on the system
known as the loading unit method.
All cold water distribution pipe work and fittings will be installed using PP pipe and manufactured to the requirements
of BS EN 15874.

Cold Water Booster Pumps


A set of booster pumps will be provided for the building at lower level plant room. The booster pump set
shall be a factory manufactured works tested set.
Water booster will include a minimum of 3 duty pumps each rated 50% od max. demand.
Pumps shall be complete with cast iron casing, bronze/stainless steel impeller, stainless steel shaft and
mechanical seals. The control panel shall be complete with VFD starters, door interlocked isolator,
indicator lights, fuses, main isolator, duty select switch, test pushbutton, anti-condensation heater and
cable numbering. All in steel enclosure IP65. The diaphragm pressure vessel shall be constructed of a
steel shell with polypropylene lining on internal wetted areas and a butyl rubber diaphragm. All
interconnecting pipe work shall be copper to BS 2871 Table X with a gate valve on the suction and
discharge of each pump and a silent check valve on the discharge branches of each pump. A pressure
switch for each of the pumps and a system pressure gauge shall be mounted on a common aluminium
pressure manifold to eliminate using small bore fittings, to ensure easy replacement of pressure switch
or gauge, and to ensure that the pump set arrangement is compact and has only one common pressure
signal source.
განმარტებითი ბარათი A4
სასტუმრო "ტრაიბი" გვერდი - 6
თარიღი 2023
შ.პ.ს
მისამართი: ქ.თბილისი , ქეთევან დედოფლის წამებულის გამზირი #46ბ, #48,#50
„UGT“
ინჟინერი: ერეკლე ესტვირიშვილი ხელმოწერა

Potable Water Maximum Demand Calculation


The flow rate of each booster pump set shall be based on the projected peak probable simultaneous
water demand and shall be calculated using the total number of water fixture units.

Hot Water Supply


Domestic hot water generation will be provided to hotel and existing buildings via use of plate heat
exchangers located in mechanical plant rooms. Pre-heat heat exchangers will be fed from the heat
recovery of the chillers. Final heating of the domestic hot water will be provided via use of plate heat
exchangers fed from hot water boilers. Kitchens will be served by a separate heat exchanger and
domestic hot water system in order to provide different hot water supply temperature for kitchen usage.
Hot water distribution around the buildings will be on a pumped return basis with appropriate thermal
balancing valves provided on each return branch connection to ensure satisfactory circulation
throughout the building.
All domestic hot water supplies will be controlled to a maximum temperature by the use of appropriate
approved thermostatic controls either as inline valves or integral to the outlet.
All hot water distribution pipe work and fittings will be installed using PP pipe and manufactured to the
requirements of BS EN 15874.
Between
boilers and calorifiers circuit design temperatures will be 80/60°C. Hot water at 55°C will be supplied to necessary
fixtures
calorifiers heating coils. Hot Water temperatures for will be able to reach 70 C for hygiene purpose.
Hot water system installations should comply with European Legionella Standards considering
maximum length for dead leg (3 mt)

Water Consumption Metering


The water supply bulk meter and the primary backflow preventer will be located on the building water
connection. Restaurant kitchens, laundry facilities and retail areas will be provided with sub meters
connected to the BMS.

PIPE AND FITTINGS


A. Domestic Cold Water Piping:
PPR pipe shall be used for domestic cold water piping in risers, main lines and in wet
area. Domestic cold water pipes shall be insulated with elastomeric rubber foam.
B. Domestic Hot Water:
PPR pipe shall be used for domestic hot water piping in risers, main lines and in wet
area Domestic hot water pipes shall be insulated with elastomeric rubber foam.
C. PPR Pipe
1. Pipe: PPR pipes shall be SDR 9 pressure class.
2. Pipes shall be complying with standard (ASTM F 2389, CSA B137.11, NSF 14)
3. PPR pipes shall be resistance to 90 degrees, transmission coefficient 0,15 W/mK
and elongation coefficient 0,035 mm/mK

VALVES
A. General:
1. Provide valve on each branch serving a toilet room.
2. Provide interior shut-off and drain valve on each branch to hose bib in exterior
locations.
3. Provide valves as indicated and where required to adequately service all parts of
systems and equipment.
4. Valves 2½ inch (60 mm) and smaller shall be bronze with screwed or flanged
ends as required by the piping system in which they are installed.
5. Valves 3 inch (75 mm) and larger shall have cast iron bodies with bronze
mountings, shall be provided with screwed or flanged ends as required by the piping
system in which they are installed.
6. Submit a schedule of all major control valves complete with all pertinent data,
განმარტებითი ბარათი A4
სასტუმრო "ტრაიბი" გვერდი - 7
თარიღი 2023
შ.პ.ს
მისამართი: ქ.თბილისი , ქეთევან დედოფლის წამებულის გამზირი #46ბ, #48,#50
„UGT“
ინჟინერი: ერეკლე ესტვირიშვილი ხელმოწერა

such as manufacturer, catalogue number, pressure, etc. for approval.


7. A valve shall be installed at the foot of each water supply riser - Supply lines to
and from tanks shall be supplied with valves the tank within the pump room.
- The cold water branch to each water heater shall be provided with a value located
near the equipment.
- All water supply control valves shall be placed so as to be readily accessible for
service and maintenance
- Control valves on all water lines shall, when fully opened, have a cross- sectional
area of at least 85% of the cross-sectional area of the line in which they are installed.
B. Gate Valves:
1. 2" (50 mm) and smaller- inside screw, nonresing stem, solid wedge, shaped disc,
bronze steam nut, rubber seat, epoxy coating all interior iron surfaces including
surfaces of disc.
2. 2½ " (60 mm) and smaller solder/screwed: Solder ends for copper tubing inside
screw non rising stem, solid wedge, for self soldering to K, L and copper tubing
carrying hot or cold water, bronze material.
3. 3" (75 mm) and larger flanged-outside screw Yoke rising stem gates bronze trime,
solid wedge- iron body, renewable bronze seat rings. In sizes to 3" wedge in solid
bronze, in larger sizes, it is iron with rolled-in bronze face rings, precisely machined.
Stem threads are out of line of flow and accessible for cleaning and lubricating.
4. 200 psi maximum working pressure, hydrostatically tested at 400 psi
5. Valves shall have a clear water way equal to the full nominal diameter of the
valve.
C. Check Valves:
1. 2" (50 mm) and smaller solder/screwed- regrinding swing checks, bronze disc, for
the prevention of backflow of water, where flow velocity is low-not for lines where
flow pulsates violently- for horizontal lines only where flow is upward, under the disc,
125 PSI pressure, bronze material.
2. 2½ (60 mm) and smaller sold- regrinding swing check, solder ends for K,L, and M
copper tubing, for non-return control service on hot or cold water lines or low
pressure where a copper tubing system is used to assure smooth, unobstructed flow,
300 PSI pressure, IBBM materials.
3. 3" (70 mm) larger flanged regrind-review swing check, bronze seat ring and disc
bolted cover. For the non return control of water 500 PSI pressure, IBBM.
D. Reduced pressure backflow preventer check valves, test cocks and relief valve,
all assembled as an integral unit.
1. Install on domestic water line as required by Code.
2. Threaded ends in sizes thru 50 mm (2 In): flanged for 50 mm and larger.
3. Pressure loss thru backflow preventer not exceeding 65 mm at design flow.
4. Pressure reducing valves:
a. Pressure reducing valves shall be provided and installed in branch water
connections to groups of fixtures or equipment at pressure or as indicated on the
drawing.
b. Valves shall be single sealed, tight closing, interval spring loaded, with spring
suitable for the proper pressure differential.
c. Valves ends shall be threaded and the body and trim shall be made of bronze, the
stem of stainless steel, disc and diaphragm of synthetic rubber. Adjusting screw shall
be protected with a temper proof cap. All internal parts shall be replaceable and
adjustable without removing the valve body from the line. Bronze inner valve shall be
suitably guided, synthetic rubber.
d. Valves shall be capable of reducing the pressure from the calculated pressure at
the given floor to a maximum outlet pressure of 70 PSIG or as indicated on drawing
and B.O.Q
e. A strainer shall be installed immediately upstream from a reducing valve. The
blow-off from each strainer shall be equipped with a valve and a drain line extended
to drain.
f. Pressure gauges shall be provided on each side of pressure reducing valves.
განმარტებითი ბარათი A4
სასტუმრო "ტრაიბი" გვერდი - 8
თარიღი 2023
შ.პ.ს
მისამართი: ქ.თბილისი , ქეთევან დედოფლის წამებულის გამზირი #46ბ, #48,#50
„UGT“
ინჟინერი: ერეკლე ესტვირიშვილი ხელმოწერა

SPECIALTIES
A. Gauges:
1. Pressure gauges shall have 110 mm diameter dial. White coated with black
figures and graduations. Shut off cock shall be provided between gauge and piping
or permit gauge removal while system is under pressure.
2. Location will be at domestic cold water inlets, pump suctions, where pressure
ranges 0-100 PSI (0-7 kg per sq.cm) and at fire pump discharge where pressure
ranges 300 PSI (0-21 kg per sq.cm).
B. Strainers
1. Provide strainers in inlet line to all pressure regulating, automatic modulating or
open and shut control valves.
2. Strainers shall be "Y" type, full pipe size and fitted with blow-off gate valves.
3. Unless otherwise called for, basket screens shall be brass with perforation
suitable for the service intended.
4. Strainers body material shall be as called for under the valve sections for the
system in which it is installed.

METERS
Water meter:
A. Use threaded fittings on meters 50 mm (2 IN) and less in size.
B. Use flanged connections on meters 65 mm (2-1/2 IN) and larger.
C. Provide valve before and after the meter.
D. Provide full sized bypass line around meter with sealed valve if approved by local
utility.
E. Water meter boxes: water meter boxes and covers shall be manufactured from
cast iron to conform to ASTM A48 and shall be coated by epoxy coating to a
minimum dry film thickness of 100 microns. The cover shall be inscribed with the
words "Potable Water Meter" in Arabic and English. The fabricated box and covers
shall comply with BS497

INSTALLATION OF PIPING
A. Install piping as indicated and as required to provide suitable supply connection to
each fixture and item of equipment requiring water supply.
B. Install plumbing without any crossings interconnections between potable and
nonpotable lines.
C. Run all piping concealed wherever possible.
D. Under no circumstances reduce pipe size indicated without written consent of
Owner size supply branches to individual fixtures as indicated.
E. Adequately support pipelines with pipe hangers as indicated or as required.
F. Install valves as indicated in Section 03.
G. Where uncovered and covered exposed pipes 150 mm in size and smaller pass
through floors, finishes walls, or finished ceilings provide nickel or chrome plated
plates large enough to completely close hole around pipes completely. Secure plate
to pipe by set screw in an approved manner.
H. Provide approved type vacuum breaker at plumbing fixtures and equipment as
indicated or as required by code.
I. Piping: installed to drain to low points and provide for air elimination at high points.
J. Mains, risers and branch connections: installed to permit expansion and
contraction without strain by means of elbow swings and/or expansion joints.
K. Riser control valves: provided on each water riser. Provide a drain valve on each
riser located upstream of riser control valve.
L. Provide a control valve in suction and discharge connections to each piece of
equipment
M. Valves, check valves, reducing valves, shock absorbers, tempering valves, etc.
easily accessible for maintenance and/or removal.
N. Screwed joints shall be made with best quality pure red lead or approved pipe
განმარტებითი ბარათი A4
სასტუმრო "ტრაიბი" გვერდი - 9
თარიღი 2023
შ.პ.ს
მისამართი: ქ.თბილისი , ქეთევან დედოფლის წამებულის გამზირი #46ბ, #48,#50
„UGT“
ინჟინერი: ერეკლე ესტვირიშვილი ხელმოწერა

compound, carefully placed on male threads only and not on the fittings.
O. Cut and threaded pipe shall have the cutting burrs and sharp edges reamed cut.
P. In erecting pipe, friction wrenches and risers shall be used exclusively and any
pipe, cut dented or otherwise damaged shall be replaced.
Q. Ferrous to non-ferrous pipe connections shall be made with EPCO Sales Inc. Or
other accepted dielectric pipe or flange union isolating joints to prevent any
electrolytic action between dissimilar metals.
R. Copper tubing shall be cut square and reamed to remove all burrs. Outside and
inside of the fittings and outside of the tubing at each end shall be well cleaned with
steel wool before soldering to remove all traces of oxidation regardless of how clean
the surfaces of the pipe and fittings may appear.
S. Provide unions at connections to each piece of equipment for easy dismantling
and at such other points to facilitate installation. Unions shall be of same strength
and manufacture used in the respective piping systems and of ground joint type.
T. Nipples: any piece of pipe 8" (200 mm) in length and less shall be considered a
nipple. All nipples with unthreaded portion 1½" (42 mm), and less shall be extra
heavy. All other nipples shall be of weight corresponding to fitting connected. Only
shoulder nipples shall be used, closed nipples will not be acceptable.
U. Fittings, unions and connections at pumps, tanks or other major equipment 3" (75
mm) and over in size shall be assembled with flanged joints and approved gaskets.
V. Float valve, non modulating type clayton 2124 angle valve or approved equal.
Brass housing and linkage with stainless steel, and monel working parts. Sections of
brass pipe with, spud end coupling.

PIPE SUPPORTS, BRACKETS AND HANGERS

All pipe work shall be adequately supported in such a manner as to permit free movement due to expansion,
contractions, vibration or other changes in the system. Supports shall be arranged as near as possible to joints and
changes of direction. Spacing of supports shall comply with Table 13 contained in British Standard BS 5572: 1978.
Vertical rising pipes particularly in shafts shall be adequately supported at the base to withstand the total weight of the
riser. Under no circumstances shall branches from vertical rising pipes be the means of support for the vertical pipe
work.

Pipe work up to and including 65 mm diameter shall be supported clear of the structure with cast brass
brackets. Where exposed to view, bright finish brass hospital brackets shall be used with rawl plugs and brass screws.

All multi runs of pipe work within false ceilings or service shafts shall be supported on purpose designed
proprietary brackets suitable for carrying more than one pipe run, and shall be secured using expanding plugs or other
purpose designed fixing devices. Softwood plugs shall not be allowed. All purpose designed proprietary brackets shall
be submitted to the Consultant for approval prior to ordering.

All G.I hangers and supporting brackets shall be painted with one coat of red oxide and one coat of Galvanizing paint.
The spacing of supports where not specified must not exceed the spacing given in the following schedules. Where
one-support carries more than one pipe diameter the spacing shall be that specified for the smallest diameter.

All supports and hangers for GI piping shall be ferrous. Supports for copper pipes shall be non ferrous and chromium
plated, wherever specified. Brackets or supports shall be set out so that they do not obstruct the access to valves,
flanges or other fittings requiring maintenance.

All pipe work shall be supported by means of approved clips or hangers at centres as detailed. In the event of two or
more pipes being carried by a single support, the spacing shall be of a shorter interval.
All vertical drops shall be supported so as to prevent sagging or swinging. Unless otherwise indicated, pipe hangers
shall be spaced as follows.
განმარტებითი ბარათი A4
სასტუმრო "ტრაიბი" გვერდი - 10
თარიღი 2023
შ.პ.ს
მისამართი: ქ.თბილისი , ქეთევან დედოფლის წამებულის გამზირი #46ბ, #48,#50
„UGT“
ინჟინერი: ერეკლე ესტვირიშვილი ხელმოწერა

 20 to 32mm Not over 2.4m apart - 10mm rods


 40 to 100mm Not over 3.0m apart - 15mm rods
 Over 100mm Not over 3.6m apart - 22mm rods

Horizontal steel pipes on the roof shall be supported to prevent sagging or swinging. The pipes supports spacing shall
be as follows.

 20 to 32mm - 2.4m
 40 to 65 mm - 3.0m
 80 to 100mm - 3.6m
 125 to 250mm - 4.5m

Piping of all equipment and control valves shall be supported to prevent strains or distortions in the connected
equipment, valves and control valves. Piping shall be supported to allow for removal of equipment, valves and
accessories with a minimum of dismantling and without requiring additional supports after these items are removed.

All channels, angles, plates, clamps etc. necessary for fastening of hangers shall be furnished by the Contractor. All
hangers shall be properly sized for the pipe to be supported. Oversized hangers shall be permitted. Details of hangers
and supports to be used by the Contractor shall be submitted to the Engineer for approval before fitting. All hangers
shall be provided with lock-nuts and have provision for vertical adjustment of pipes.

Parallel groups of pipes shall be supported by trapeze type hangers of G.I construction. Individual horizontal piping
shall be supported by the hangers consisting of malleable split rings with malleable iron sockets or steel clevis type
hangers or roller hangers where specified. Pipe standard with base flange and adjustable type yokes shall be used
for pipes supported form the floor. Vertical piping shall have heavy wrought iron or steel clamps securely bolted on
the piping with the end extension bearings on the building construction.

Piping shall be anchored where required to localize expansion or to prevent undue strain on piping and branches.
Anchors shall be entirely separate from hangers and shall be heavy forged or welded construction of approved design.

Hangers and supports for cold piping shall have tongue and groove design rubber support inserts of approved make
or high density insulation capable of withstanding the compression and allowing the hanger to support the pipe without
any metal to metal contact.

All internal pipe supports, hangers and anchors etc. are to be painted with two coats of an approved rust preventive
paint, preferably zinc rich primer and two coats of enamel paint of grey colour or as approved by the Engineer.

All external pipes supports shall be finally painted with two coats of enamel paint of grey colour or as approved by the
Engineer.

INCOMING WATER SUPPLY AND METER

Building will supply water up to the water meter. The plumbing contractor shall take connections from there to the
contractor supplied water meter. The water meter and cabinets shall be supplied and installed by the contractor and
all meters and cabinets to be as per local authority requirements.

STERILIZATION OF DOMESTIC WATER SYSTEM


A. Sterilize system as indicated, or according to AWWA Codes.
B. Thoroughly flush potable water systems.
C. After flushing, introduce chloring or chlorine solution into system with dosage
sufficient to give an initial residua chlorine content of 50 Mgr/L
D. Collect samples from various taps and fixtures throughout buildings during
introduction of chlorine to assure uniform distribution. Open and close valves several
times.
E. After a 24-hours contact period, flush all traces of heavily chlorinated.
განმარტებითი ბარათი A4
სასტუმრო "ტრაიბი" გვერდი - 11
თარიღი 2023
შ.პ.ს
მისამართი: ქ.თბილისი , ქეთევან დედოფლის წამებულის გამზირი #46ბ, #48,#50
„UGT“
ინჟინერი: ერეკლე ესტვირიშვილი ხელმოწერა

water from system.


F. After flushing is complete, submit evidence of effectiveness of sterilization.
1. Laboratory reports of bacteriological tests on samples take from system.
2. Number and locations of taking samples as specified by construction manager.
G. If unsatisfactory results are obtained, repeat sterilization process until satisfactory.
H. Do not put system into service until tests are approved by Engineer

D. Collect samples from various taps and fixtures throughout buildings during
introduction of chlorine to assure uniform distribution. Open and close valves several
times.
E. After a 24-hours contact period, flush all traces of heavily chlorinated.
water from system.
F. After flushing is complete, submit evidence of effectiveness of sterilization.
1. Laboratory reports of bacteriological tests on samples take from system.
2. Number and locations of taking samples as specified by construction manager.
G. If unsatisfactory results are obtained, repeat sterilization process until satisfactory.
H. Do not put system into service until tests are approved by Engineer
განმარტებითი ბარათი A4
სასტუმრო "ტრაიბი" გვერდი - 12
თარიღი 2023
შ.პ.ს
მისამართი: ქ.თბილისი , ქეთევან დედოფლის წამებულის გამზირი #46ბ, #48,#50
„UGT“
ინჟინერი: ერეკლე ესტვირიშვილი ხელმოწერა

TESTING AND COMMISSIONING

General Setting Out of Work and Commissioning

After having ensured that water, electricity and other necessary supplies are available, the Contractor shall set
to work the completed works or part thereof, at the instruction of the Consultant and make the necessary adjustments
to ensure correct functioning.

After the installation or part thereof has been set to work and adjusted, the contractor shall demonstrate its
operation, at a time selected by and to the satisfaction of the Consultant. Test shall be in accordance with British
Standard Code of Practice CP 310: 1965.

The test shall demonstrate: -

a. That equipment provided complies with the specification in all particulars and is of adequate capacity for its full
rates of duty.

b. That all equipment operates sufficiently quietly to meet the specified requirements.

c. That all instruments, protection and control devices, etc., are correctly calibrated and accurate.

d. That all water systems are properly balanced, vented, and operates satisfactorily under test pressure.

The details of method of carrying out the recording of tests shall be agreed with the Consultant. The Client's
representative and the consultant shall be at liberty to be present at test and to participate in the tests. This shall not
relieve the contractor of his responsibilities for carrying out the tests satisfactorily.

The contractor shall make all the records during the tests and on completion thereof, shall provide the
Consultant with a test report and record both in triplicate.

The contractor shall also provide all test instruments, together with skilled supervision and adequate labour for carrying
out the tests.

Pipe-work Pressure Testing

All pipe-work services shall be subjected to a test of 500 kN/m2 or one and half times working pressure
whichever is the greater, for not less than 24 hours.

Where pipe-work is tested in sections, all valves shall be blanked off temporarily using plugs or blank flanges.
The valve wedge shall not be used to retain the water. The pipe-work services shall be charged with water allowing
all air to escape and avoiding shock or water hammer. The test pressure gauge shall be mounted within the pipe-work
system with a loop and cock and shall be calibrated such that the test pressure falls above its mid-range.

The contractor shall carry out his own test first to ensure there are no leaks prior to requesting the Consultant
to witness the test. The witnessed test shall be maintained for a minimum of 4 hour without measurable loss and
without further pumping.

Pipe-work main laid in ground shall be tested for 24 hours and leakage shall be measured by the quantity of
water pumped into the main under test. Leakage shall not exceed five litres per 25 mm of pipe diameter per 1750
meter length of pipe for 33 meters head pressure in a period of 24 hours.

The Consultant shall witness all pipe-work tests. The contractor shall give the Consultant a minimum of 24 hours
notice of all tests. The contractor shall also provide test sheets set out in an agreed manner of each pipe-work section
to be tested.

PRE-COMMISSIONING WORKS
განმარტებითი ბარათი A4
სასტუმრო "ტრაიბი" გვერდი - 13
თარიღი 2023
შ.პ.ს
მისამართი: ქ.თბილისი , ქეთევან დედოფლის წამებულის გამზირი #46ბ, #48,#50
„UGT“
ინჟინერი: ერეკლე ესტვირიშვილი ხელმოწერა

Tubes and all items of equipment shall be delivered stored and maintained in storage with their open ends effectively
plugged, capped or sealed. All fittings, valves and sundry items shall be stored in clean bins or bagged and stored in
suitable racks. All such stored items shall be maintained under weather proofed cover to be supplied by the contractor
until they are ready for incorporation in the works. Particular care shall be taken to ensure that electrical equipment
and components are kept clean and dry.

Before installations are handed over or subjected to the inspection and tests the entire installation shall be thoroughly
cleaned, both internally and externally.

All fire protection installations shall be flushed out with clean water. During the flushing out provision shall be made to
exclude any item of the system, which could be damaged by the cleaning operation. The entire operation shall be
carried out to the satisfaction of the consultant.
LABELS & IDENTIFICATION

All items of Water Supply Services shall be labeled and identified as required, and as per the requirements of the
Engineer.

EXTERNAL PIPE WORKS

The U/G main water services, if any, shall be PPR tube to relevant British Standards. The pipe work shall be installed
in ground minimum 600 deep to the satisfaction of the Engineer. All joints shall be wrap with denso tape after testing.
Concrete thrust blocks, size 300 x 300 x300 shall be provided at every junction and change in direction for pipe not
within the trench.

PRESSURE REDUCING VALVE

Wherever is required even not shown on the tender drawing, it is the contractor’s responsibility to provide the system
- a pressure reducing valve(s) if the distribution system available pressure is above in relation to the fixture pressure
requirement being offered.

This is to prevent damaged and leaks that may cause and fault that may arise due to over pressure since note that
location of fixtures are installed in different levels throughout the building.

WARRANTY

A. Provide warranty for one year and accordance with contract conditions.

Storage and Handling


Storing and handling including taking delivery, loading and unloading all fixtures and , fittings and other
equipment shall be carried out by the Contractor in such a manner as to avoid breakage, distortion, denting or other
damage. Stacking of materials shall be done in such a manner as to prevent to the pipe or coatings to the satisfaction
of the Engineer.
Plastic fittings shall be stored under cover and out of direct sunlight at all times. Pipes shall be supported
throughout their entire length and free flow of air around them maintained. Generally, all pipes shall be handled using
canvas slings not less than 250mm wide. The use of chains or wire slings will not be permitted.
All valves and fittings shall be stored under cover on hard standing until required for fixing. Uncreated valves
and fittings shall not be stacked.
Pipes and fittings damaged during handling or storage shall be set aside and the Engineer informed. If in the
Engineer’s opinion the damage is such that the pipe or fitting has been permanently impaired it shall be removed from
site.
No repairs shall be started without the approval of the Engineer.
Transport and Handling on Site
განმარტებითი ბარათი A4
სასტუმრო "ტრაიბი" გვერდი - 14
თარიღი 2023
შ.პ.ს
მისამართი: ქ.თბილისი , ქეთევან დედოფლის წამებულის გამზირი #46ბ, #48,#50
„UGT“
ინჟინერი: ერეკლე ესტვირიშვილი ხელმოწერა

Fixtures shall not be allowed to drop or strike objects, which may damage the pipe, but shall be lifted or lowered by
suitable approved equipment. Hoister and buildings of approved type shall be used on all vehicles used for the
transport of pipe.
The Contractor shall take every care to ensure that no damage whatsoever results to the fixture from transport and
stacking. All trucks, wagons, stacking methods and devices shall have the approval of the Engineer but his approval
shall in no way relieve the Contractor of his responsibilities under the Contract.
All fixtures shall be properly protected in factory assembled timbers with bedding of straw bags or similar approved by
the Engineer.
The Contractor shall ensure that all fixtures with special fittings are packed separately, as they should not be stacked.
Fixtures shall be laid on flat level ground and in such a manner as to prevent damage to other when handled period
of three hours.
GENERAL

All units and assemblies of sanitary ware shall be as shown on the Mechanical and Architectural drawings,
listed in schedules and as listed below.

Unless approved or stated otherwise all sanitary fixtures shall be from one manufacturer.

Each plumbing fixture shall be supplied and installed complete with all necessary fittings for operational and
maintenance requirements. All fittings exposed to view (i.e. not concealed in chase, void, duct or buried in building
structure) shall be heavily chrome plated unless otherwise indicated in the specification schedules or on the drawings.

WATER CLOSET (Floor Mounted)

Arrangement: Floor mounted pan with totally concealed low level cistern and plumbing.

Pan: constructed from vitreous china to BS 3402, 360mm high pan x 540mm projection with box flushing (two
stage ) and horizontal outlet, wash-down action.
Seat: heavy duty seat and universal cover, top fixed easy release plastics hinges and removable covers.
Color: white
Pan connector:
Cistern: Flushing cistern for WC for concealed installation. Dual flush discharge valve
Interruptible, pneumatic low noise, connection from top or back, insulated against condensation. 6L/4.5L,
410*120*430mm.angle stop valve ½’’, fixing bracket, flush pipe, 45 mm. Protecting block. Grohe 37766 or equivalent.

Wall plate: For two volume flushing cistern.156*197 mm. Push button and matt chrome Eco-knob Grohe 37376 P.
Palm operated with low level cistern adapter.

Fixing method: plugged and screw fixed to duct wall.

Other accessories: Factory built-in spray unit from the same producer.

Hand spray with flexible connection and angle valve and all other accessories and support system

WC bowl S-trap

Exact dimensions be coordinated with the loaded drawings and site requirement and engineering approval

WASH BASIN
განმარტებითი ბარათი A4
სასტუმრო "ტრაიბი" გვერდი - 15
თარიღი 2023
შ.პ.ს
მისამართი: ქ.თბილისი , ქეთევან დედოფლის წამებულის გამზირი #46ბ, #48,#50
„UGT“
ინჟინერი: ერეკლე ესტვირიშვილი ხელმოწერა

Wall hung type or pedestal type


Vitreous china to BS 3402, pedestal model Twyford WB 5751, counter-top model Twyford ENVY NV4511 Dimension
600*510 or equivalent, but not limited to:
A. Single mixer with ceramic cartridge, electronic sensor type with saving water Accessories and fittings shall be
similar to Grohe Euro plus with optic sensor. Fully recessed automatic "Sloane" electrical contractor is to provide a
240V 15 amp current and a 220/24V-30VA transformer.
B. Pop-up waste fitting
C. Chrome plated trap 32mmdia.
D. Two angle valves with escutcheon and copper tube flexible connections.
E. Wall brackets or support system as approved.
F. Exact dimensions to be coordinated with the loaded drawings and site requirement and engineering approval.
SINK
Single/ Double Drainer Sink
304 Stainless steel,1.6 mm thickness kitchen and of overall dimensions as shown on Architectural drawings. The sink
shall be complete with the following trim and accessories (but not limited to):
Single lever sink mixer 45mmdia deck mounted with ceramic cartridge, swivelling tubular spout, mousseur, with
adjustable volume and with saving water accessories and fittings similar to Grohe Euro plus ref.33 932.
White ploy propylene bottle traps with multi-fit outlet and 40mm seal. Each trap shall be supplied with a white flange
for plastic waste pipe and all other accessories.
Two angle valves with escutcheon and copper tube flexible connections.
Unit to be fixed at 900mm above finished floor level to top front edge and to be supported as site approval (as shown
on Arch. Drawings).
Exact dimensions of the sink shall be coordinated with the loaded drawings and site requirement and engineering
approval.
SANITARY ACCESSORIES
All Sanitary accessories shall be as shown on the Architectural drawings and engineer approval.
Accessories for Disabled Toilet
Liquid Soap Dispenser
Recessed wall mounted with lock. Model BRADLEY 644 .Shall be fabricated of type 304 (18-8), heavy gage stainless
steel with exposed surfaces satin finish Capacity 40oz Liquid soap.
Soap Dish and Holder
Recessed type, heavy gage stainless steel satin finish, removable soap tray. Model BRADLEY 9363.

Towel Bar
Surface mounted towel bar shall have chrome plated cast brass support posts with satin finish. Towel Bar shall be 1’’
Diameter, 18 gage seamless construction with satin finish. Model BRADLEY 908.
Toilet Paper Holder
Recessed single roll toilet tissue dispenser with hinged hood shall be chrome plated brass. Model BRADLEY 5103.
განმარტებითი ბარათი A4
სასტუმრო "ტრაიბი" გვერდი - 16
თარიღი 2023
შ.პ.ს
მისამართი: ქ.თბილისი , ქეთევან დედოფლის წამებულის გამზირი #46ბ, #48,#50
„UGT“
ინჟინერი: ერეკლე ესტვირიშვილი ხელმოწერა

Hand Dryer
Surface mounted hand dryer shall be fabricated from porcelain enamelled grey cast iron fitted with fixed nozzle and
infrared electronic control. Universal type motor, fuse protected, automatic circuit breaker protecting heating element.
Wiring single phase .Dryer shall deliver 130CFM air at 140 degrees F .Entire unit U.L. Listed.
Paper Towel Dispenser and Waste Receptacle
The waste receptacle shall be fabricated of type 304 (18-8), 22 gage stainless steel with exposed surfaces in satin
finish. Reusable heavy duty vinyl liner holds 16.5 gal.
Clear Glass Facial Mirror
Plate glass one piece mirror ¼’’float glass, triple silver plated with electro-copper plated layer and thermosetting
infrared cured paint backing. Guarantee 15 years against silver spoilage. Secure mirror to wall with screws then fasten
rosettes to mirror.