Professional Documents
Culture Documents
TABLE OF CONTENTS
Unless otherwise specified, the areas designated for clearing and grubbing shall
be cleared of all trees, stumps, bushes, roots, rubbish, debris, and other
objectionable matters.
Before removal of any trees or shrubs the Contractor shall obtain written RTA
Horticultural Section unless otherwise instructed by RTA at least two weeks in
advance of the planned removal. The Engineer's approval of any removal of trees
and undergrowth must be obtained before commence-ment of work.
Trees and plants designated for preservation shall be protected from injury or
damage which could result from the Contractor's operations including dewatering.
The form of protection for vegetation within the site shall be of a type and
standard approved by the Dubai Municipality Horticultural Section.
For the full width to be cleared, all objectionable materials and any other
obstructions shall be grubbed from areas to be excavated, to the satisfaction of
the Engineer.
Cavities left below subgrade elevation by the removal of stumps or roots shall be
carefully backfilled and the backfill material compacted to the Engineer's
satisfaction.
All tree trunks, stumps, bush, limbs, roots, vegetation, and other debris removed
in clearing and grubbing shall be either burned or removed to approved location
outside the right-of-way or otherwise disposed of so as to leave the roadway and
adjacent areas free from unsightly debris. Burning shall be done at such time and
in such manner as to prevent any damage to areas adjoining the right-of-way.
2/2.1 GENERAL
Prior to starting the removal of structures and obstructions, the Contractor shall
carry out a thorough survey of structures, fences, trees, etc., that are to be
removed. The Engineer shall be fully informed of the results of this survey and
the amount and extent of the planned removal and the plan shall then be agreed
by the Engineer.
The Contractor shall raze, remove and dispose of all structures and obstructions
as required including, but not limited to, the following: buildings, sheds, walls,
slabs, foundations, inlets, catch basins, culverts, headwalls, trash racks, irrigation
structures, standpipes, manholes, valves, ditch lining, pipelines, tanks, pool lining,
posts, poles, columns, signs, fences, gates, planters, curbs, gutters, sidewalks,
driveways, trees, stumps, shrubs and plants.
Where required, the Contractor shall be responsible, prior to removal of pipes, for
the disconnection of all services and clearance from the Dubai Municipality and all
Service Authorities.
All pipes to be removed and either salvaged or relaid shall be carefully removed
and every precaution taken to avoid breaking or damaging the pipe. The pipes
shall be stored when necessary so that there will be no loss or damage before
relaying. The Contractor will be required to replace sections lost from storage or
damage by negligence or by the use of improper methods in their removal.
2/3.1 GENERAL
Structural excavation shall consist of the excavation and removal of all materials
necessary for the construction of structures, pipelines and cables/ducts, including
foundations and substructures, in accordance with the details shown on the
Drawings and these Specifications and/or as directed.
The Contractor shall notify the Engineer a sufficient time in advance of the
beginning of excavation to allow pre-construction measurements and records to
be made of the undisturbed ground (refer to Clause 2/3.2). The required
excavation shall then be performed in reasonably close conformity to the lines,
grades and cross sections established or shown on the Drawings.
The Engineer may direct the Contractor to protect his excavation with timbering
where, in his opinion, such timbering is necessary to ensure the safety of the
workmen, adjoining structures and work generally. Any action taken by the
Engineer in this regard will in no way relieve the Contractor of any responsibility or
liability under the Contract.
Where a firm bearing material is not encountered at the elevation established for
bearing, due to soft, spongy or otherwise unstable soil, all such unsuitable
material shall be removed to the extent directed (see Clause 2/3.15).
No back throwing shall be allowed and all materials must be brought to the
surface and placed clear of the trench side.
The Contractor shall keep the trench excavation free from water at all times.
The Engineer reserves the right to direct the Contractor as to the lengths of
trench or portions of bulk excavations which shall remain open at any one time.
The use of explosives for any purpose whatsoever during the Contract is
prohibited.
(1) Ground levels shall be agreed at suitable intervals with the Engineer's
Representative.
(2) Surface materials and conditions will be recorded in collaboration with the
Engineer's Representative and where appropriate the owners or occupiers of
the land.
This information shall be neatly presented in bound volumes and submitted to the
Engineer. To this shall be added details of any existing natural or piped subsoil
drainage or other underground features as work proceeds.
Before any structural excavation is commenced the Contractor shall define the
centre line or other agreed reference line of the Works and erect the necessary
profiles throughout their full length if so required by the Engineer. The Contractor
shall be responsible for obtaining all verifications from the Dubai Municipality
Survey Section and the Contractor shall bear all associated costs.
Where pipelines are to be laid in agricultural land the surface and subsoil
drainage shall be maintained whether natural or artificial. Before commencing
work the Contractor shall ascertain from the owner or occupier of the land the
location of any existing land drains or mole drains.
Where instructed or necessary for reasons of limited access or any other reason,
excavation shall be carried out by hand at no additional cost.
The sides and/or the bottom of excavations in excess of 1.2 metres shall be
adequately supported.
The Contractor shall provide the necessary support for excavations and shall
submit to the Engineer his proposals for the supporting of excavations by trench
sheeting or other approved means at least seven days prior to the
commencement of any excavation works. His proposals shall take into account
the nature of the ground to be excavated, the level of the water table at the site
and the proximity of buildings and roads.
If in the opinion of the Engineer the support proposed for the excavations by the
Contractor is insufficient then the Engineer will order the provision of stronger
support than that provided by the Contractor and in this event the Contractor shall
adopt the methods so ordered by the Engineer and shall have no claim against
the Employer for any costs incurred in adopting the additional measures.
The Contractor shall not remove temporary works supporting the excavations until
in the opinion of the Engineer the permanent work is sufficiently advanced to
permit such removal which shall be executed under the personal supervision of a
competent foreman.
All temporary works supporting the excavation shall be removed during backfilling
unless previous approval has been obtained from the Engineer. Where
temporary supports have been used in the excavation any such supports left in
because it is impracticable to remove them shall be left in at the expense of the
Contractor.
Should temporary supports need to be left in any excavation carried out in open
cut owing to the Engineer deciding that their permanent installation is necessary
for the stability of an adjacent structure or service the Contractor shall be
reimbursed in accordance with the provisions of the Contract.
Timbering steel sheeting strutting and sheet piling for the support of excavations
where provided shall be fixed in accordance with BS 6031:1981, AMD 4251:83
Battered sides to trenches or other excavations will only be permitted if they can
be constructed within the limits of the site, without damage or interference to
existing services, properties or structures, without undue interference with
pedestrians and traffic and to slopes which are sufficiently flat to ensure stability
of the ground.
2/3.8 DEWATERING
A high water table is expected and the Contractor must do all necessary
measures to ensure proper dry conditions are maintained at all times during
construction. The Contractor shall provide and maintain ample means and
devices (including spare units kept ready for immediate use in case of
breakdowns) with which to intercept and/or remove promptly and dispose properly
of all water entering trenches and other excavations. Such excavations shall be
kept dry until the structures, pipes, and appurtenances to be built therein have
been completed. In addition precautions shall be taken to prevent floatation of
partially built structures, completed structures to be filled on commissioning of the
Works and pipelines awaiting backfilling.
All necessary precautions shall be taken to prevent any adjacent ground from
being adversely affected by loss of fines through any dewatering process.
Method statements shall include proposals for disposal of the water arising from
dewatering systems.
All water pumped or drained from the work shall be disposed of in a suitable
manner without undue interference with other work, damage to pavements, other
surfaces, or property. Suitable temporary pipes, flumes, or channels shall be
provided for water that may flow along or across the site of the work. No such
If permission is given to use new or existing pipes or culverts which are not part of
the live sewerage system, they shall be thoroughly cleaned of all silt and any
resulting damage made good after use.
During use the Contractor shall be responsible for the condition of the pipeline,
duct, etc., and any defect or failure shall be made good at the Contractor's
expense. Any delay to the Contractor's works caused by such defect or failure
shall be deemed as the Contractor's responsibility.
After use by the Contractor such pipeline, duct, etc., shall be handed back to the
Municipality in a condition not less than that at the commencement of use. Any
repairs or replacement required shall be at the Contractor's expense.
It cannot be guaranteed that permission will be given to use existing ducts and
pipelines.
All temporary works for control of water shall be sited clear of the Works, except
where temporary sub-drains under the Works are approved in which case the
pipes shall be laid with a 75 mm surround of gravel, and the top surface of the
surround shall be covered with tarred felt cloth or other approved material.
Unless otherwise directed all temporary drains and sub-drains shall be finally
sealed with concrete at approved intervals and all temporary ditches, sumps,
wells, etc., shall be refilled and reinstated as specified elsewhere.
In the exceptional event that lagoons for the storage of groundwater are
permitted, they must be suitably protected with fencing and attended by day and
night to prevent access by the general public and will not be sited adjacent to
buildings. Approved means of preventing the formation of mosquito larvae on the
surface of the lagoons will be employed.
A. Temporary Underdrains
Where the nature of the Works necessitates, the Contractor shall dewater the
excavations by means of an efficient wellpoint drainage system which will
drain the soil and prevent saturated soil from flowing into the excavation. The
wellpoints shall be designed especially for this type of service. The pumping
unit shall be designed for use with the wellpoints, and shall be capable of
maintaining a high vacuum and of handling large volumes of air and water at
the same time.
2/3.9 FORMATION
The formation of excavations for pipelines shall be dry, even and free of stones
and other protrusions.
A. Safety
B. Description
In no case, except with the approval of the Engineer, shall the earth be
plowed, scraped, or dug by machinery so near to the finished subgrade as
to result in the disturbance of material below said subgrade, the last of the
material to be excavated shall be removed by hand immediately before the
placing of the pipe, masonry, or other structure.
The extent of open excavation at any one time will be controlled by the
conditions, but shall always be confined to the limits prescribed by the
Engineer.
From areas within which excavations are to be made, loam and topsoil shall
be carefully removed and separately stored to be used again as directed, or
if the Contractor prefers not to separate surface materials, he shall furnish,
as directed, loam and topsoil at least equal in quantity and quality to that
excavated at no cost to the Works.
endanger adjacent road and structures. If the Engineer is of the opinion that
at any point sufficient proper supports have not been provided, he may
order additional supports placed at the Contractor's expense.
F. Bridging Trenches
The Contractor shall, at his own expense, provide suitable and safe bridges
and other crossings where required for the accommodation of travel, and to
provide access to private property during construction, and shall remove
said structures thereafter.
G. Road Signs
All existing road signs, street name plates and the like affected by the
Works are to be carefully taken down and stored. Signs to be re-erected
shall be cleaned, provided with new fixings where necessary and the posts
re-painted as required. Redundant signs shall be transported to the stores
or depots of relevant Authorities. Any sign, street name plate or the like
damaged by the Contractor during his operation shall be repaired or
replaced at the Contractor's cost.
Should the Contractor excavate to a depth greater than that required for the
construction of the foundations or pile caps, such excavation shall be filled with
Class C concrete at his own expense. Should the material forming the bottom of
any excavation, while acceptable at the time of excavation, become puddled soft
or loose during the progress of the Works, the Contractor shall at his own
expense, remove all such softened or loosened material and replace with Class C
concrete as directed by the Engineer's Representative.
Where such unyielding material is encountered in excavation other than for box
culverts or where an entire excavation for a box culvert bears on such materials,
the rock or other unyielding material shall be cleared of all loose fragments and
cut to a firm surface as directed.
Trenches for pipes shall be excavated to a sufficient depth and width to enable
the pipe and any specified or agreed joint, bedding, hauncing and surrounding to
be accommodated. Trenches shall be of width as specified and as shown on the
drawing.
The Contractor in carrying out excavation for cables/ducts shall, where required,
erect and maintain an approved type of temporary yellow plastic safety fencing
(refer to Clause 2/3.10) around any work and shall provide fenced access ways
across the trenches.
The bottom of the trench shall be accurately graded. Care shall be taken not to
excavate below the depths indicated. Where rock is encountered, the rock shall
be excavated to the required depth. Uneven surfaces of the bottom of trench shall
be excavated 150 mm deeper. Such depth in rock shall be backfilled with
approved fill material and compacted as specified and/or as directed by the
Engineer.
The width and depth of the trenches for electrical and telephone cables/ducts
shall be as specified in the relative drawings or as ordered by the Engineer.
Banks may be sloped or widened to facilitate placement of cables, but not the
extent that will cause interference with other utilities and structures. No battering
of trenches shall be allowed under existing carriageways, unless otherwise
agreed by the Engineer.
All excavated material will remain the property of the Employer unless designated
as surplus to the Contract requirements in which case it will be removed from site
immediately. The Contractor shall dispose of such surplus material as per Clause
2/3.16.
All excavated material shall be deposited so that it will cause as little damage and
inconvenience as possible.
The excavated material, if found unsuitable as backfill, shall be removed from site
and shall be replaced with suitable imported backfill to the approval of the
Engineer.
All surplus and unsuitable excavated material and rubble shall be transported to
the approved tip.
The Contractor shall seek approval for all the proposed disposal sites from the
Dubai Municipality before work commences and disposal at such sites shall be at
no extra cost to the Employer.
- Certain separate areas will be designated for the disposal of hard debris such
as building rubble, broken concrete, kerbing, road pavement and the like.
The Contractor shall use only these designated areas and shall keep these
disposal areas neat and tidy at all times.
2/3.17 COFFERDAMS
The Contractor shall, on request, submit detailed drawings for approval showing
his proposed method of cofferdam construction and other pertinent features not
shown in detail on the Drawings. No construction shall be started until such
Drawings are approved, however, such approval shall not relieve the Contractor
of any responsibility for the successful completion of the construction.
No timber or bracing which will extend into the concrete shall be left in cofferdams
or cribs.
Any pumping from the interior of any foundation enclosure shall be done in such a
manner as to preclude the possibility of any portion of the concrete material being
carried away. No pumping will be permitted during the placing of concrete or for a
period of at least 12 hours thereafter, unless it is done from a suitable sump
separated from the concrete work by a watertight wall. Pumping to remove water
from a sealed cofferdam shall not begin until the seal has set sufficiently to
withstand the hydrostatic pressure.
When no longer required, all cofferdam material down to the natural bed of the
waterway shall be removed. Cofferdam material outside the waterway to a
minimum of 0.5 m below the surface of the finished ground shall also be
removed.
2/4.1 GENERAL
Backfilling around structures and in pipe trenches shall be carried out as detailed
below except where otherwise designated/directed.
Backfilling of trenches other than in roads and paved/ tiled areas shall normally be
carried out using selected excavated materials similar to the in-situ materials in
which the trench or structure is being constructed.
Special backfill shall be used for backfilling trenches in roads, paved/tiled areas,
and where designated or directed.
Material for backfilling may be selected from any part of the site and methods of
selection may include sieving to remove large particles or methods of hand or
machine sorting together with soil classification and soil property testing.
A. Cohesive Soils
Cohesive soils shall be placed in layers not greater than 150 mm thick
(compacted thickness) and compacted such that throughout each layer placed
the dry density is not less than 95% of the MDD of the soil or the air voids content
(volume of air divided by total volume of soil) is not greater than 10% which ever
gives the higher state of compaction.
If site trials show that the specified compaction can be achieved with layers
greater than 150 mm compacted thickness approval may be given to backfill in
layers of greater thickness, but not exceeding 200 mm, providing the plant utilised
is that used for the trials.
The placement moisture of the soil shall be within the range +/-2% of O.M.C of
the soil before excavation.
B. Granular Soils
Granular soils shall be placed in layers not greater than 150 mm thick (compacted
thickness) and compacted such that throughout each layer placed the dry density
is not less than 95% of the maximum dry density as determined by BS 1377 on
the same soil at the same moisture content.
If site trials show that the specified compaction can be achieved with layers
greater than 150 mm compacted thickness approval may be given to backfill in
layers of greater thickness, but not exceeding 200 mm, providing the plant utilised
is that used for the trials.
For free draining granular soils that have no clearly defined optimum moisture
content, compaction shall be carried out to achieve a relative density of not less
than 95%. During compaction the soil shall be made as wet as practicable.
C. Testing of Backfill
Tests to determine the optimum dry density of the backfill material shall be carried
out as directed, the frequency depending on consistency of material and test
results.
Unless directed otherwise on site testing for density and moisture content of
in-situ soils shall be at the minimum rate of: -
(2) One test per backfill layer for every 30 linear metres of pipeline trench backfill
laid in one operation.
Where a land drain passes through an excavation the backfill shall first be taken
up to form a bed for replacement pipes. The severed drains shall then be
exposed at each side of the trench to allow for connection and laying of a new
drain across the excavation. This new drain shall be of similar pipes of the same
diameter as those in the existing drain. Before any further backfilling is done the
Contractor shall notify the owner or occupier to enable him to inspect the
reinstated land drain. The replacement drain shall be surrounded with pipe
bedding to a minimum thickness 150 mm before further backfilling.
The material used for special backfill shall be obtained from designated and
approved sources.
The materials shall be placed in layers of not more than 20cm in depth before
compaction, and each layer shall be compacted by means of mechanical or
pneumatic tamping devices or other suitable equipment to density of at least 95
percent of the maximum dry density as determined in accordance with the latest
BS 1377: Part 4: 1990 (Method 3.5 or 3.6, AMD 8259: 1995 & AMD 13925: 2002)
and the correction shall be made according to BS 1377.
The layers of material placed around structures shall be placed on opposite sides
to approximately the same elevation at the same time.
Special care shall be taken in placing and compacting material under haunches of
all pipe to prevent moving or raising the pipe from its bedding.
Material shall not be placed against any concrete abutment, wing wall, retaining
wall, box culvert or similar structure until the concrete has been in place at least
14 days, unless otherwise authorised.
A. Structural Filling
Structural filling shall be carried out using approved well graded natural sands
and gravel or special backfill in accordance with Clause 2/4.3.
B. Non-Structural Filling
The material and the procedure for Non-Structural filling shall be same as
outlined in Clause 2/4.2.
After the cables/ducts have been laid, the trench refilling shall commence with
approved fill in compacted layers not exceeding 200 mm thick, each layer being
well compacted by hand with iron rammers weighing not less than 5 kg, until the
trench has been filled to a height of 300 mm above the top of the cable/duct.
The remainder of the trench shall then be refilled in compacted layers not exceed
150mm in thickness, each layer being well compacted with power rammers,
vibrating plate compactors or other mechanical means of a type to be approved
until the ground is thoroughly consolidated up to the required level for surface
reinstatement. Each layer shall be compacted to 95% of its maximum dry density.
Should the quantity of the excavated materials be not sufficient, due to
unsuitability or otherwise, for the process of backfill and fill, the Contractor shall
obtain the quantity required of such backfill and fill from approved borrow pits and
transport same to the site of work at his own expense.
Trenches shall not be backfilled until all required tests are performed and until the
Engineer has verified that the cables, etc., have been installed in accordance with
the Specifications and Drawings.
Lumps and clods shall be broken up before use. Materials shall not be dropped
from a height and where directed water shall be added to assist in adequate
consolidation.
Where cover to cables/ducts is less than 400 mm, or where ordered by the
Engineer, protection in the form of concrete encasing shall be provided according
to an approved drawing or as ordered by the Engineer.
2.5.1 GENERAL
Where new pipes, mains, cables/ducts, etc., are to be laid alongside, over or
under the existing, the Contractor shall take care to interfere as little as possible
with the existing services and connections thereto and any damage shall be
repaired by the Contractor to the approval of the appropriate Authority or by
appropriate Authority at the cost of the Contractor.
The Contractor shall make all arrangements for protecting existing services and
for temporarily diverting them to maintain the services without interruption.
Existing services, pipes, mains, ducts, etc., exposed in trenches for new work
shall be protected in accordance with the requirements of the relevant Authority
before trenches are refilled.
The Contractor shall lay cables, fittings, specials, etc., under hedges, fences,
walls, etc., as necessary.
Where hedges are damaged or destroyed the whole shall be restored and
reinstated with shrubs of the same kind as the hedge, planted in due season in an
approved manner and fenced on each side with post and rail stock proof fences
finished on top with one strand of galvanised barbed wire, or otherwise protected
as required by the owners or occupiers and the Engineer.
Where fences or walls are damaged or destroyed the whole shall be restored and
reinstated with like materials to the satisfaction of the owners or occupiers and
the Engineer.
The Contractor shall ensure that no trees are damaged or permanently removed
in carrying out the Contract except where directed due to the presence of
permanent works.
In general the reinstatement of stripped areas of unpaved land shall restore the
ground to a condition not inferior to that which existed before the site was
occupied.
The compacted backfill shall be taken up to a level which allows for settlement. In
arable, grassed and similar areas the surface to be topsoiled shall then be
loosened to a depth of 200 mm and topsoil replaced on it to the specified depth
without compaction using approved topsoil of comparable quality to make up any
deficiency.
Areas where grass is to be sown shall be worked to a fine tilth, levelled, graded
and rolled with a light roller. The seed shall be sown evenly at the specified rate
of application in the proper season and in suitable weather conditions, and the
areas again rolled. Restoration and re-seeding of any areas where the new grass
is inadequate shall be carried out as instructed.
The grass shall be well watered four times a day and the Contractor will be
required to keep the grass cut short until the Defects Liability Certificate has been
issued.
Trenches and other excavations within road corridors may be opened in four
types of ground:-
(4) in unmade ground which does not fall into any of the above three categories.
All reinstatement works falling into the above categories/classes shall be carried
out either in compliance with the current Local Order and any subsequent revision
thereof issued by Dubai Municipality or in compliance with the details shown on
the Contract Drawings, whichever is the greater in either construction depth or
asphalt thickness.
Surfaced areas not in road corridors shall be reinstated using materials similar to
and not inferior to those existing prior to commencement of the Works.
The Dubai Municipality Horticulture Section will remove any trees, bushes and
plants from developed reservations that they wish to preserve prior to the
commencement of work by the Contractor. The Contractor must allow in his rates
for the removal and disposal of any remaining trees, bushes and plants necessary
for the execution of the Works and to keep sweet soil separate in accordance
with the current Local Order.