PROJECT PROPOSED 2-STOREY WITH ROOF DECK

OWNER ENGR. JEREMY SERQUIÑA


LOCATION LOT 7 BLOCK 65, BEAUMONT ST., RIO DE ORO, GENERAL TRIAS, CAVITE
SUBJECT BILL OF QUANTITIES
DATE October 11, 2023

UNIT PRICE
NO. DESCRIPTIONS QTY UNIT AMOUNT
MATERIALS LABOR AMOUNT
1.0 Site Development
1.1 Site Preparation
1.1.1 Site Clearing 144.0 SQM 65.00 41.00 106.00 15,264.00
1.1.2 Surveying, Gridline, Structural & Masonry Layout 1.0 LOT 12,156.55 19,450.48 31,607.03 31,607.03
1.1.3 Slope & Elevation Correction 144.0 SQM 31.00 285.00 316.00 45,504.00
1.1.4 Soil Poisoning & Termites Treatment 208.8 SQM 285.00 85.50 370.50 77,360.40
1.1.5 Earth Hauling 88.2 CU.M 850.00 340.00 1,190.00 105,002.63
Sub-Total For Site Development 274,738.06
2.0 Main Structure
2.1 Structural Works
2.1.1 Earth Works
2.1.1.1 Excavation 52.6 CU.M - 650.00 650.00 34,183.50
2.1.1.2 Backfill and Compaction 117.1 SQM - 450.00 450.00 52,704.00
2.1.1.3 Gravel Bedding 28.7 CU.M 930.00 279.00 1,209.00 34,674.63
2.1.2 Reinforcement -
2.1.2.1 Footing 467.9 KGS 71.00 23.00 94.00 43,984.20
2.1.2.2 Footing Tie beam 1,482.2 KGS 71.00 23.00 94.00 139,328.34
2.1.2.3 Column 913.7 KGS 71.00 23.00 94.00 85,884.81
2.1.2.4 Beam 3,643.2 KGS 71.00 23.00 94.00 342,462.22
2.1.2.5 Slab 1,536.8 KGS 71.00 23.00 94.00 144,462.58
2.1.2.6 Stairs 491.0 KGS 71.00 23.00 94.00 46,152.31
2.1.3 Formworks -
2.1.3.1 Footing 9.00 SQM 585.00 350.00 935.00 8,415.00
2.1.3.2 Footing Tie beam 75.10 SQM 585.00 350.00 935.00 70,218.50
2.1.3.3 Column 84.94 SQM 585.00 350.00 935.00 79,418.90
2.1.3.4 Beam 217.81 SQM 585.00 350.00 935.00 203,655.16
2.1.3.5 Slab 40.42 SQM 585.00 350.00 935.00 37,792.26
2.1.3.6 Stairs 48.28 SQM 585.00 350.00 935.00 45,138.18
2.1.4 Concreting -
2.1.4.1 Footing 7.12 CU.M 6,283.00 2,150.00 8,433.00 60,076.69
2.1.4.2 Footing Tie beam 6.01 CU.M 6,283.00 2,150.00 8,433.00 50,665.46
2.1.4.3 Column 9.05 CU.M 6,283.00 2,150.00 8,433.00 76,310.22
2.1.4.4 Beam 17.16 CU.M 6,283.00 2,150.00 8,433.00 144,751.60
2.1.4.5 Slab 48.59 CU.M 6,283.00 2,150.00 8,433.00 409,793.20
2.1.4.6 Stairs 9.84 CU.M 6,283.00 2,150.00 8,433.00 82,994.27
2.1.5 Vapor Barrier Installation 144.00 SQM 102.00 31.00 133.00 19,152.00
2.1.6 Steel Framing -
2.1.6.1 Roof Framing 1,635.25 KGS 95.00 28.50 123.50 201,953.21
2.1.6.2 Painting 38.14 SQM 175.00 300.00 475.00 18,118.40
Sub-Total for Main Structure 2,432,289.63

SUMMARY: Sub-Total for Site Development 274,738.06


Sub-Total for Main Structure 2,432,289.63
Over-all Estimated Direct Project Cost 2,707,027.69