You are on page 1of 2

BILL OF QUANTITIES BILL NO.

JUMEIRAH BEACH RESIDENCE (JBR)


EMPOWER
DISTRICT COOLING PLANT CONTAINMENT PROJECT
CONCRETE WORK 4
UNIT TOTAL PRICE
ITEM ITEM DESCRIPTION QTY UNIT
RATE AED

CONCRETE WORK

SUBSTRUCTURE

Poured Concrete

Blinding concrete, minimum characteristic strength 20 N/mm²


with moderate sulphate resistant cement as specified

A In blinding, 100 mm average thick 640 m² 10

Durable Concrete using GGBS 50-60 % or fly ash 30-40 % to


be added, with a cement content of 460 kg/m³ and fcu at 28
days should be not less than 50 N/mm2 and 80% of that
strength should be provided after 7 days, with a slump not
less than 200 mm using Super Plasticisers Rehobuild 805
from basf construction chemicals, al gurg fosroc or equally
approved a transit time of 45 minutes have been allowed from
mixing of concrete to placing of concrete W/C ratio not less
than 0.36.

B In isolated footings, 600mm thick 33 m³ 35

Concrete with minimum characteristic strength Grade of fcu.


50 N/mm² with a cement content not less than 420 kg/m³,
placing temperature shall not be more than be 30 degree
Celsius, water absorption shall be below 1.5% - when tested
as per bs 1881 part 122, water penetration shall be below
10mm -when tested as per din 1048, concrete chloride
permeability to be below 1500 coulombs - when tested as per
aashto T277, water binder ratio shall not be more than 0.36
and air content shall not be more than 2%.

C In pile caps; 800mm thick 300 m³ 30


D In tie beams 5 m³ 35
E In S.O.G; 200mm 780 m³ 35
F In column necks 20 m³ 35

To Collection

TR-361 - JBR DCP CP - BOQ_TENDER Rev. 03 Page 1 of 4 Bill No. 4 - Concrete Work
BILL OF QUANTITIES BILL NO.
JUMEIRAH BEACH RESIDENCE (JBR)
EMPOWER
DISTRICT COOLING PLANT CONTAINMENT PROJECT
CONCRETE WORK 4
UNIT TOTAL PRICE
ITEM ITEM DESCRIPTION QTY UNIT
RATE AED

CONCRETE WORK [CONT'D]

SUBSTRUCTURE [CONT'D]

Reinforcement

Reinforcement hot rolled deformed high yield bond steel bar


reinforcement, FY=460 MPA in any diameter as specified and
as shown on drawings.

A In isolated footings 2 t 750


B In pile caps 25 t 750
C In tie beams 0.5 t 750
D In Slab on Grade (S.O.G.) 85 t
750
E In column necks 8 t 750

Shuttering

F Sides of isolated footings 80 m²


40
G Sides of pile caps 610 m² 40
H Sides of S.O.G. 225 m² 45
J Sides of tie beams 40 m² 45
K Sides of column necks 175 m² 45

To Collection

TR-361 - JBR DCP CP - BOQ_TENDER Rev. 03 Page 2 of 4 Bill No. 4 - Concrete Work

You might also like