Date as of March 7, 2015

Subject : ACTUAL ACCOMLISHMENT


REPORT
PACK HOUSE EXTENSION PROJECT

Duration : (Completion March 15, 2015)


CONTRACTOR : RBR Ready Mix

STRUCTURAL STRUCTURAL STRUCTURAL


PACKHOUSE EXTENSION PROJECT (DEPT. % INSTALLED
16) Delivered at site Actual Installed nedeed to be ACCOMPLISHEMENT REMARKS
(tons) (tons) Installed (tons)
A. STRUCTURAL WORKS (INTALLATION)

Elevation 1.40 m 9.76 9.76 0.00 100.00% DONE / PUNCHLIST


Elevation 5.00 m 28.67 27.25 1.42 95.04% PARTIAL INSTALLED
Elevation 6.60 m 2.24 2.24 0.00 100.00% PARTIAL INSTALLED
Elevation 7.20 m 2.39 2.39 0.00 100.00% DONE / PUNCHLIST
Elevation 10.00 m 33.50 31.25 2.25 93.29% PARTIAL INSTALLED
Elevation 13.85 m 26.76 23.17 3.59 86.57% PARTIAL INSTALLED
Elevation 18.00 m 23.94 17.05 6.88 71.25% PARTIAL INSTALLED
Elevation 20.60 m 8.63 7.77 0.86 90.03% PARTIAL INSTALLED
Elevation 22.43 m 7.99 7.99 0.00 100.00% DONE / PUNCHLIST
Elevation 25.97 m 9.56 9.12 0.44 95.36% PARTIAL INSTALLED
Elevation 26.30 m 0.96 0.11 0.85 11.58% PARTIAL INSTALLED
Elevation 27.30 m 12.52 12.52 0.00 100.00% DONE / PUNCHLIST
Elevation 29.50 m 4.84 0.54 4.30 11.14% PARTIAL INSTALLED
Elevation 33.30 m 11.51 10.87 0.65 94.38% PARTIAL INSTALLED
Elevation 36.70 m 2.90 0.31 2.59 10.66% PARTIAL INSTALLED
Elevation 37.85 m 29.04 23.97 5.07 82.55% PARTIAL INSTALLED
Elevation 46.30 m 5.30 1.83 3.47 34.57% PARTIAL INSTALLED
Box Column 17.54 17.54 0.00 100.00% DONE / PUNCHLIST
Planted Column Extension 55.14 43.25 11.89 78.44% PARTIAL INSTALLED
Extension Box Column 29.25 28.00 1.25 95.72% PARTIAL INSTALLED
Retrofitting & Doubler Plate 88.18 18.64 69.53 21.14% PARTIAL INSTALLED
Wide Flange (Rail Hoist) 1.95 1.95 0.00 100.00% PARTIAL INSTALLED
Purlins 7.99 6.00 1.99 75.10% PARTIAL INSTALLED
Sagrods 0.29 0.29 0.00 100.00% DONE / PUNCHLIST
Floor Beam/Joist 55.48 17.80 37.68 32.08% PARTIAL INSTALLED
Checkered Plate 90.00 46.42 43.58 51.58% PARTIAL INSTALLED

TOTAL WEIGHT 566.32 368.02 198.29


CONTRACT WEIGHT 583.00

TOTAL % WEIGHT 63.13%

Submitted by: Noted by: Noted by:

Leove D. Cortez F. R. Mancenido F. N. Flores


Project In-Charge/Mechanical Inspector Construction Supervisor Construction Manager
Date as of NOVEMBER 16, 2014
Subject : ACTUAL ACCOMLISHMENT
REPORT
PACK HOUSE EXTENSION PROJECT

Duration : (Completion NOVEMBER 30, 2014)


CONTRACTOR : RBR Ready Mix Contractor

TOTAL WEIGHT STRUCTURAL STRUCTURAL STRUCTURAL


PACKHOUSE EXTENSION PROJECT nedeed to be
(DEPT. 16) Delivered at site already REMARKS
(TONS) Delivered/Inst
(tons) installed (tons)
alled

A. STRUCTURAL WORKS (INTALLATION)

Elevation 1.40 m 56.79 11.59 3.86 45.19 DONE

Elevation 5.00 m 62.70 14.87 4.96 47.83 DONE

Elevation 6.60 m 9.45 2.22 0.74 7.23 DONE

Elevation 7.20 m 16.03 3.15 1.05 12.88 DONE

Elevation 10.00 m 90.17 22.03 7.34 68.14 DONE

Elevation 13.85 m 69.99 16.84 5.61 53.14 DONE

Elevation 18.00 m 67.87 15.62 5.21 52.25 DONE

Elevation 20.60 m 9.47 0.31 0.00 9.17 NOT YET INSTALLED

Elevation 22.43 m 20.38 20.38 6.79 0.00 ON GOING WORKS

Elevation 25.97 m 16.95 13.78 4.59 3.17 ON GOING WORKS

Elevation 26.30 m 1.63 1.63 0.00 0.00 ON GOING WORKS

Elevation 27.30 m 16.27 0.00 0.00 16.27 NOT YET INSTALLED

Elevation 29.50 m 9.86 10.18 0.00 -0.31 NOT YET INSTALLED

Elevation 33.30 m 22.70 4.10 0.00 18.60 NOT YET INSTALLED

Elevation 36.70 m 7.32 2.51 0.00 4.81 NOT YET INSTALLED

Elevation 37.85 m 24.01 5.22 0.00 18.79 NOT YET INSTALLED

Elevation 46.30 m 7.35 0.00 0.00 7.35 NOT YET INSTALLED

Planted Column Extension 62.00 15.03 1.88 46.97 ON GOING WORKS

TOTAL WEIGHT 471.24 159.45 42.04 311.79

TOTAL % WEIGHT 33.84% 26.36% 66.16%

Submitted by: Noted by: Noted by:

Leove D. Cortez F. R. Mancenido F. R. Flores


Project In-Charge/Mechanical Inspector Construction Supervisor Construction Manager
Date as of NOVEMBER 19, 2014

Subject : ACTUAL ACCOMLISHMENT REPORT


PACK HOUSE EXTENSION PROJECT
ROTO PACKER NO.5
Duration : (Completion NOVEMBER 25, 2014)
CONTRACTOR : RBR Ready Mix Contractor

TOTAL WEIGHT STRUCTURAL STRUCTURAL WT.


PACKHOUSE EXTENSION % INSTALLED REMARKS
PROJECT (DEPT. 16) to be installed (tons)
actual Installed Not yet delivered ACCOMPLISHEMENT
(tons) (tons)

STRUCTURAL WORKS (INTALLATION)

Elevation 1.40 m 18.93 18.93 0.00 100.00% DONE / PUCHLIST

Elevation 5.00 m 20.90 20.90 0.00 100.00% DONE / PUCHLIST

Elevation 6.60 m 3.15 3.15 0.00 100.00% DONE / PUCHLIST

Elevation 7.20 m 5.34 5.34 0.00 100.00% DONE / PUCHLIST

Elevation 10.00 m 30.06 30.06 0.00 100.00% DONE / PUCHLIST

Elevation 13.85 m 23.33 23.33 0.00 100.00% DONE / PUCHLIST

Elevation 18.00 m 22.62 22.62 0.00 100.00% DONE / PUCHLIST

Elevation 22.43 m 6.79 5.78 1.01 85.10% 1.01 tons waiting for Delivery

Elevation 25.97 m 5.65 4.76 0.89 84.29% 0.89 tons floor joist not yet deliver

Elevation 26.30 m 9.50 3.00 6.49 31.60% 6.50 tons waiting for Delivery

Elevation 29.50 m 3.28 0.00 3.28 0.00% 3.28 tons arrived at site but not yet installed

Elevation 33.30 m 7.57 0.00 3.17 0.00% 4.40 tons waiting for Delivery

Elevation 37.85 m 8.00 2.67 5.33 33.36% 5.33 tons waiting for Delivery

137.86 137.86
TOTAL 165.11 20.18 83.50%
installed Weight

Submitted by: Noted by: Approved by:

Leove D. Cortez F. R. Mancenido F. N. Flores


Project In-Charge/Mechanical Inspector Construction Supervisor Construction Manager
Date as of March 7, 2015
Subject : ACTUAL ACCOMLISHMENT
REPORT
PACK HOUSE EXTENSION PROJECT

Duration : (Completion March 15, 2015)


CONTRACTOR : RBR Ready Mix

STRUCTURAL STRUCTURAL STRUCTURAL


PACKHOUSE EXTENSION PROJECT (DEPT. % INSTALLED
16) Delivered at site Actual Installed nedeed to be ACCOMPLISHEMENT REMARKS
(tons) (tons) Installed (tons)
A. STRUCTURAL WORKS (INTALLATION)

Elevation 1.40 m 9.76 9.76 0.00 100.00% DONE / PUNCHLIST


Elevation 5.00 m 28.67 27.25 1.42 95.04% PARTIAL INSTALLED
Elevation 6.60 m 2.24 2.24 0.00 100.00% PARTIAL INSTALLED
Elevation 7.20 m 2.39 2.39 0.00 100.00% DONE / PUNCHLIST
Elevation 10.00 m 33.50 31.25 2.25 93.29% PARTIAL INSTALLED
Elevation 13.85 m 26.76 23.17 3.59 86.57% PARTIAL INSTALLED
Elevation 18.00 m 23.94 17.05 6.88 71.25% PARTIAL INSTALLED
Elevation 20.60 m 8.63 7.77 0.86 90.03% PARTIAL INSTALLED
Elevation 22.43 m 7.99 7.99 0.00 100.00% DONE / PUNCHLIST
Elevation 25.97 m 9.56 9.12 0.44 95.36% PARTIAL INSTALLED
Elevation 26.30 m 0.96 0.11 0.85 11.58% PARTIAL INSTALLED
Elevation 27.30 m 12.52 12.52 0.00 100.00% DONE / PUNCHLIST
Elevation 29.50 m 4.84 0.00 4.84 0.00% NOT YET STARTED
Elevation 33.30 m 11.51 10.87 0.65 94.38% PARTIAL INSTALLED
Elevation 36.70 m 2.90 0.31 2.59 10.66% PARTIAL INSTALLED
Elevation 37.85 m 29.04 23.97 5.07 82.55% PARTIAL INSTALLED
Elevation 46.30 m 5.30 1.83 3.47 34.57% PARTIAL INSTALLED
Box Column 17.54 17.54 0.00 100.00% DONE / PUNCHLIST
Planted Column Extension 55.14 43.25 11.89 78.44% PARTIAL INSTALLED
Extension Box Column 29.25 28.00 1.25 95.72% PARTIAL INSTALLED
Retrofitting & Doubler Plate 88.18 18.64 69.53 21.14% PARTIAL INSTALLED
Wide Flange (Rail Hoist) 1.95 1.95 0.00 100.00% PARTIAL INSTALLED
Purlins 7.99 6.00 1.99 75.10% PARTIAL INSTALLED
Sagrods 0.29 0.18 0.11 63.02% PARTIAL INSTALLED
Floor Beam/Joist 55.48 17.80 37.68 32.08% PARTIAL INSTALLED
Checkered Plate 90.00 47.25 42.75 52.50% PARTIAL INSTALLED

TOTAL WEIGHT 566.32 368.21 214.79


CONTRACT WEIGHT 583.00
TOTAL % WEIGHT 63.16%

Submitted by: Noted by: Noted by:

Leove D. Cortez F. R. Mancenido F. N. Flores


Project In-Charge/Mechanical Inspector Construction Supervisor Construction Manager
Date as of March 14, 2015
Subject : ACTUAL ACCOMLISHMENT
REPORT
PACK HOUSE EXTENSION PROJECT

Duration : (Completion March 15, 2015)


CONTRACTOR : RBR Ready Mix

STRUCTURAL STRUCTURAL STRUCTURAL


PACKHOUSE EXTENSION PROJECT (DEPT. % INSTALLED
16) Delivered at site Actual Installed nedeed to be ACCOMPLISHEMENT REMARKS
(tons) (tons) Installed (tons)
A. STRUCTURAL WORKS (INTALLATION)

Elevation 1.40 m 9.76 9.76 0.00 100.00% DONE / PUNCHLIST


Elevation 5.00 m 28.67 27.25 1.42 95.04% PARTIAL INSTALLED
Elevation 6.60 m 2.24 2.24 0.00 100.00% PARTIAL INSTALLED
Elevation 7.20 m 2.39 2.39 0.00 100.00% DONE / PUNCHLIST
Elevation 10.00 m 33.50 31.25 2.25 93.29% PARTIAL INSTALLED
Elevation 13.85 m 26.76 23.17 3.59 86.57% PARTIAL INSTALLED
Elevation 18.00 m 23.94 17.05 6.88 71.25% PARTIAL INSTALLED
Elevation 20.60 m 8.63 7.77 0.86 90.03% PARTIAL INSTALLED
Elevation 22.43 m 7.99 7.99 0.00 100.00% DONE / PUNCHLIST
Elevation 25.97 m 9.56 9.12 0.44 95.36% PARTIAL INSTALLED
Elevation 26.30 m 0.96 0.46 0.49 48.42% PARTIAL INSTALLED
Elevation 27.30 m 12.52 12.52 0.00 100.00% DONE / PUNCHLIST
Elevation 29.50 m 4.84 0.00 4.84 0.00% NOT YET STARTED
Elevation 33.30 m 11.51 10.87 0.65 94.38% PARTIAL INSTALLED
Elevation 36.70 m 2.90 0.31 2.59 10.66% PARTIAL INSTALLED
Elevation 37.85 m 29.04 23.97 5.07 82.55% PARTIAL INSTALLED
Elevation 46.30 m 5.30 1.83 3.47 34.57% PARTIAL INSTALLED
Box Column 17.54 17.54 0.00 100.00% DONE / PUNCHLIST
Planted Column Extension 55.14 45.69 9.45 82.86% PARTIAL INSTALLED
Extension Box Column 29.25 28.25 1.00 96.58% PARTIAL INSTALLED
Retrofitting & Doubler Plate 88.18 18.64 69.54 21.14% PARTIAL INSTALLED
Wide Flange (Rail Hoist) 1.95 1.95 0.00 100.00% PARTIAL INSTALLED
Purlins 7.99 7.87 0.12 98.51% PARTIAL INSTALLED
Sagrods 0.29 0.18 0.11 63.02% PARTIAL INSTALLED
Floor Beam/Joist 55.48 19.70 35.78 35.51% PARTIAL INSTALLED
Checkered Plate 90.00 65.30 24.70 72.56% PARTIAL INSTALLED

TOTAL WEIGHT 566.32 393.06 189.94


CONTRACT WEIGHT 583.00
TOTAL % WEIGHT 67.42%

Submitted by: Noted by: Noted by:

Project In-Charge/Mechanical Inspector Construction Supervisor Construction Manager


Date as of March 21, 2015
Subject : ACTUAL ACCOMLISHMENT
REPORT
PACK HOUSE EXTENSION PROJECT

Duration : (Completion March 30, 2015)


CONTRACTOR : RBR Ready Mix

STRUCTURAL STRUCTURAL STRUCTURAL


PACKHOUSE EXTENSION PROJECT (DEPT. % INSTALLED
16) Delivered at site Actual Installed nedeed to be ACCOMPLISHEMENT REMARKS
(tons) (tons) Installed (tons)
A. STRUCTURAL WORKS (INTALLATION)

Elevation 1.40 m 9.76 9.76 0.00 100.00% DONE / PUNCHLIST


Elevation 5.00 m 28.67 27.25 1.42 95.04% PARTIAL INSTALLED
Elevation 6.60 m 2.24 2.24 0.00 100.00% DONE / PUNCHLIST
Elevation 7.20 m 2.39 2.39 0.00 100.00% DONE / PUNCHLIST
Elevation 10.00 m 33.50 31.25 2.25 93.29% PARTIAL INSTALLED
Elevation 13.85 m 26.76 23.17 3.59 86.57% PARTIAL INSTALLED
Elevation 18.00 m 23.94 17.05 6.88 71.25% PARTIAL INSTALLED
Elevation 20.60 m 8.63 7.77 0.86 90.03% PARTIAL INSTALLED
Elevation 22.43 m 7.99 7.99 0.00 100.00% DONE / PUNCHLIST
Elevation 25.97 m 9.56 9.12 0.44 95.36% PARTIAL INSTALLED
Elevation 26.30 m 0.96 0.46 0.49 48.42% PARTIAL INSTALLED
Elevation 27.30 m 12.52 12.52 0.00 100.00% DONE / PUNCHLIST
Elevation 29.50 m 4.84 0.00 4.84 0.00% NOY YET STARTED
Elevation 33.30 m 11.51 10.87 0.65 94.38% PARTIAL INSTALLED
Elevation 36.70 m 2.90 1.25 1.65 43.14% PARTIAL INSTALLED
Elevation 37.85 m 29.04 23.97 5.07 82.55% PARTIAL INSTALLED
Elevation 46.30 m 5.30 2.85 2.45 53.78% PARTIAL INSTALLED
Box Column 17.54 17.54 0.00 100.00% DONE / PUNCHLIST
Planted Column Extension 55.14 46.35 8.79 84.06% PARTIAL INSTALLED
Extension Box Column 29.25 28.25 1.00 96.58% PARTIAL INSTALLED
Retrofitting & Doubler Plate 88.18 18.64 69.54 21.14% PARTIAL INSTALLED
Wide Flange (Rail Hoist) 1.95 1.95 0.00 100.00% DONE / PUNCHLIST
Purlins 14.16 7.87 6.29 55.59% PARTIAL INSTALLED
Sagrods 0.29 0.18 0.11 63.02% PARTIAL INSTALLED
Floor Beam/Joist 55.48 19.70 35.78 35.51% PARTIAL INSTALLED
Checkered Plate 90.00 66.95 23.05 74.39% PARTIAL INSTALLED

TOTAL WEIGHT 572.48 397.33 185.67


CONTRACT WEIGHT 583.00
TOTAL % WEIGHT 68.15%

Submitted by: Noted by: Noted by:

Leove D. Cortez F. R. Mancenido F. N. Flores


Project In-Charge/Mechanical Inspector Construction Supervisor Construction Manager
Date as of March 28, 2015
Subject : ACTUAL ACCOMLISHMENT
REPORT
PACK HOUSE EXTENSION PROJECT

Duration : (Completion March 30, 2015)


CONTRACTOR : RBR Ready Mix

STRUCTURAL STRUCTURAL STRUCTURAL


PACKHOUSE EXTENSION PROJECT (DEPT. % INSTALLED
16) Delivered at site Actual Installed nedeed to be ACCOMPLISHEMENT REMARKS
(tons) (tons) Installed (tons)
A. STRUCTURAL WORKS (INTALLATION)

Elevation 1.40 m 9.76 9.76 0.00 100.00% DONE / PUNCHLIST


Elevation 5.00 m 28.67 27.25 1.42 95.04% PARTIAL INSTALLED
Elevation 6.60 m 2.24 2.24 0.00 100.00% DONE / PUNCHLIST
Elevation 7.20 m 2.39 2.39 0.00 100.00% DONE / PUNCHLIST
Elevation 10.00 m 33.50 31.25 2.25 93.29% PARTIAL INSTALLED
Elevation 13.85 m 26.76 23.17 3.59 86.58% PARTIAL INSTALLED
Elevation 18.00 m 23.94 17.05 6.88 71.23% PARTIAL INSTALLED
Elevation 20.60 m 8.63 7.77 0.86 90.03% PARTIAL INSTALLED
Elevation 22.43 m 7.99 7.99 0.00 100.00% DONE / PUNCHLIST
Elevation 25.97 m 9.56 9.12 0.44 95.36% PARTIAL INSTALLED
Elevation 26.30 m 0.96 0.46 0.49 48.42% PARTIAL INSTALLED
Elevation 27.30 m 12.52 12.52 0.00 100.00% DONE / PUNCHLIST
Elevation 29.50 m 4.84 0.00 4.84 0.00% NOT YET STARTED
Elevation 33.30 m 11.51 10.87 0.65 94.38% PARTIAL INSTALLED
Elevation 36.70 m 2.90 2.90 0.00 100.00% DONE / PUNCHLIST
Elevation 37.85 m 29.04 23.97 5.07 82.53% PARTIAL INSTALLED
Elevation 46.30 m 5.30 2.85 2.45 53.78% PARTIAL INSTALLED
Box Column 17.54 17.54 0.00 100.00% DONE / PUNCHLIST
Planted Column Extension 55.14 51.05 4.09 92.58% PARTIAL INSTALLED
Extension Box Column 29.25 28.25 1.00 96.58% PARTIAL INSTALLED
Retrofitting & Doubler Plate 88.18 18.64 69.53 21.14% PARTIAL INSTALLED
Wide Flange (Rail Hoist) 1.95 1.95 0.00 100.00% DONE / PUNCHLIST
Purlins 14.16 7.87 6.29 55.58% PARTIAL INSTALLED
Sagrods 0.29 0.18 0.11 63.02% DONE / PUNCHLIST
Floor Beam/Joist 55.48 19.70 35.79 35.50% PARTIAL INSTALLED
Checkered Plate 90.00 66.95 23.05 74.39% PARTIAL INSTALLED

TOTAL WEIGHT 572.48 403.67 179.33


CONTRACT WEIGHT 583.00
TOTAL % WEIGHT 69.24%

Prepared by: Reviewed by:

Bryan J. Fabro Leove D. Cortez


Associate Eng'r. Project In-Charge/Mechanical Inspector

Noted by: Approved by:

Francis. R. Mancenido Florante. N. Flores


Construction Supervisor Construction Manager
Date as of April 4, 2015
Subject : ACTUAL ACCOMLISHMENT
REPORT
PACK HOUSE EXTENSION PROJECT

Duration : (Completion April 15, 2015)


CONTRACTOR : RBR Ready Mix

STRUCTURAL STRUCTURAL STRUCTURAL


PACKHOUSE EXTENSION PROJECT (DEPT. % INSTALLED
16) Delivered at site Actual Installed nedeed to be ACCOMPLISHEMENT REMARKS
(tons) (tons) Installed (tons)
A. STRUCTURAL WORKS (INTALLATION)

Elevation 1.40 m 9.76 9.76 0.00 100.00% DONE / PUNCHLIST


Elevation 5.00 m 28.67 27.25 1.42 95.04% PARTIAL INSTALLED
Elevation 6.60 m 2.24 2.24 0.00 100.00% DONE / PUNCHLIST
Elevation 7.20 m 2.39 2.39 0.00 100.00% DONE / PUNCHLIST
Elevation 10.00 m 33.50 32.61 0.89 97.36% PARTIAL INSTALLED
Elevation 13.85 m 26.76 23.38 3.38 87.37% PARTIAL INSTALLED
Elevation 18.00 m 23.94 17.62 6.32 73.61% PARTIAL INSTALLED
Elevation 20.60 m 8.63 7.77 0.86 90.03% PARTIAL INSTALLED
Elevation 22.43 m 7.99 7.99 0.00 100.00% DONE / PUNCHLIST
Elevation 25.97 m 9.56 9.12 0.44 95.36% PARTIAL INSTALLED
Elevation 26.30 m 0.96 0.46 0.49 48.42% PARTIAL INSTALLED
Elevation 27.30 m 12.52 12.52 0.00 100.00% DONE / PUNCHLIST
Elevation 29.50 m 4.84 0.00 4.84 0.00% NOT YET STARTED
Elevation 33.30 m 11.51 10.87 0.65 94.38% PARTIAL INSTALLED
Elevation 36.70 m 2.90 2.90 0.00 100.00% DONE / PUNCHLIST
Elevation 37.85 m 29.04 28.38 0.67 97.70% PARTIAL INSTALLED
Elevation 46.30 m 5.30 4.89 0.41 92.19% PARTIAL INSTALLED
Box Column 17.54 17.54 0.00 100.00% DONE / PUNCHLIST
Planted Column Extension 55.14 51.05 4.09 92.58% PARTIAL INSTALLED
Extension Box Column 29.25 28.25 1.00 96.58% PARTIAL INSTALLED
Retrofitting & Doubler Plate 88.18 18.64 69.53 21.14% PARTIAL INSTALLED
Wide Flange (Rail Hoist) 1.95 1.95 0.00 100.00% DONE / PUNCHLIST
Purlins 14.16 7.87 6.29 55.59% PARTIAL INSTALLED
Sagrods 0.29 0.18 0.11 63.02% PARTIAL INSTALLED
Floor Beam/Joist 55.48 19.70 35.78 35.51% PARTIAL INSTALLED
Checkered Plate 90.00 66.90 23.10 74.33% PARTIAL INSTALLED

TOTAL WEIGHT 572.48 412.21 170.79


CONTRACT WEIGHT 583.00
TOTAL % WEIGHT 70.71%

Prepared by: Reviewed by:

Bryan J. Fabro Leove D. Cortez


Associate Eng'r. Project In-Charge/Mechanical Inspector

Noted by: Approved by:

Francis. R. Mancenido Florante. N. Flores


Construction Supervisor Construction Manager
Date as of April 11, 2015
Subject : ACTUAL ACCOMLISHMENT
REPORT
PACK HOUSE EXTENSION PROJECT

Duration : (Completion April 15, 2015)


CONTRACTOR : RBR Ready Mix

STRUCTURAL STRUCTURAL STRUCTURAL


PACKHOUSE EXTENSION PROJECT (DEPT. % INSTALLED
16) Delivered at site Actual Installed nedeed to be ACCOMPLISHEMENT REMARKS
(tons) (tons) Installed (tons)
A. STRUCTURAL WORKS (INTALLATION)

Elevation 1.40 m 9.76 9.76 0.00 100.00% DONE / PUNCHLIST


Elevation 5.00 m 28.67 27.25 1.42 95.04% PARTIAL INSTALLED
Elevation 6.60 m 2.24 2.24 0.00 100.00% DONE / PUNCHLIST
Elevation 7.20 m 2.39 2.39 0.00 100.00% DONE / PUNCHLIST
Elevation 10.00 m 33.50 32.61 0.89 97.36% PARTIAL INSTALLED
Elevation 13.85 m 26.76 23.38 3.38 87.37% PARTIAL INSTALLED
Elevation 18.00 m 23.94 17.62 6.32 73.61% PARTIAL INSTALLED
Elevation 20.60 m 8.63 7.77 0.86 90.03% PARTIAL INSTALLED
Elevation 22.43 m 7.99 7.99 0.00 100.00% DONE / PUNCHLIST
Elevation 25.97 m 9.56 9.12 0.44 95.36% PARTIAL INSTALLED
Elevation 26.30 m 0.96 0.46 0.49 48.42% PARTIAL INSTALLED
Elevation 27.30 m 12.52 12.52 0.00 100.00% DONE / PUNCHLIST
Elevation 29.50 m 4.84 0.00 4.84 0.00% NOT YET STARTED
Elevation 33.30 m 11.51 10.87 0.65 94.38% PARTIAL INSTALLED
Elevation 36.70 m 2.90 2.90 0.00 100.00% DONE / PUNCHLIST
Elevation 37.85 m 29.04 28.38 0.67 97.70% PARTIAL INSTALLED
Elevation 46.30 m 5.30 5.30 0.00 100.00% DONE / PUNCHLIST
Box Column 17.54 17.54 0.00 100.00% DONE / PUNCHLIST
Planted Column Extension 55.14 53.31 1.83 96.69% PARTIAL INSTALLED
Extension Box Column 29.25 28.25 1.00 96.58% PARTIAL INSTALLED
Retrofitting & Doubler Plate 88.18 18.64 69.53 21.14% PARTIAL INSTALLED
Wide Flange (Rail Hoist) 1.95 1.95 0.00 100.00% DONE / PUNCHLIST
Purlins 14.16 7.99 6.17 56.43% PARTIAL INSTALLED
Sagrods 0.29 0.18 0.11 63.02% PARTIAL INSTALLED
Floor Beam/Joist 55.48 20.70 34.79 37.30% PARTIAL INSTALLED
Checkered Plate 90.00 67.00 23.00 74.44% PARTIAL INSTALLED

TOTAL WEIGHT 572.48 416.11 166.89


CONTRACT WEIGHT 583.00
TOTAL % WEIGHT 71.37%

Prepared by: Reviewed by:

Bryan J. Fabro Leove D. Cortez


Associate Eng'r. Project In-Charge/Mechanical Inspector

Noted by: Approved by:

Francis. R. Mancenido Florante. N. Flores


Construction Supervisor Construction Manager
Date as of April 18, 2015
Subject : ACTUAL ACCOMLISHMENT
REPORT
PACK HOUSE EXTENSION PROJECT

Duration : (Completion April 30, 2015)


CONTRACTOR : RBR Ready Mix

STRUCTURAL STRUCTURAL STRUCTURAL


PACKHOUSE EXTENSION PROJECT (DEPT. % INSTALLED
16) Delivered at site Actual Installed nedeed to be ACCOMPLISHEMENT REMARKS
(tons) (tons) Installed (tons)
A. STRUCTURAL WORKS (INTALLATION)

Elevation 1.40 m 9.76 9.76 0.00 100.00% DONE / PUNCHLIST


Elevation 5.00 m 28.67 27.72 0.95 96.69% PARTIAL INSTALLED
Elevation 6.60 m 2.24 2.24 0.00 100.00% DONE / PUNCHLIST
Elevation 7.20 m 2.39 2.39 0.00 100.00% DONE / PUNCHLIST
Elevation 10.00 m 33.50 32.88 0.62 98.15% PARTIAL INSTALLED
Elevation 13.85 m 26.76 23.38 3.38 87.37% PARTIAL INSTALLED
Elevation 18.00 m 23.94 17.89 6.05 74.73% PARTIAL INSTALLED
Elevation 20.60 m 8.63 7.77 0.86 90.03% PARTIAL INSTALLED
Elevation 22.43 m 7.99 7.99 0.00 100.00% DONE / PUNCHLIST
Elevation 25.97 m 9.56 9.12 0.44 95.36% PARTIAL INSTALLED
Elevation 26.30 m 0.96 0.46 0.49 48.42% PARTIAL INSTALLED
Elevation 27.30 m 12.52 12.52 0.00 100.00% DONE / PUNCHLIST
Elevation 29.50 m 4.84 0.00 4.84 0.00% NOT YET STARTED
Elevation 33.30 m 11.51 10.87 0.65 94.38% PARTIAL INSTALLED
Elevation 36.70 m 2.90 2.90 0.00 100.00% DONE / PUNCHLIST
Elevation 37.85 m 29.04 28.38 0.67 97.70% PARTIAL INSTALLED
Elevation 46.30 m 5.30 5.30 0.00 100.00% DONE / PUNCHLIST
Box Column 17.54 17.54 0.00 100.00% DONE / PUNCHLIST
Planted Column Extension 55.14 53.31 1.83 96.69% PARTIAL INSTALLED
Extension Box Column 29.25 28.25 1.00 96.58% PARTIAL INSTALLED
Retrofitting & Doubler Plate 88.18 20.15 68.03 22.85% PARTIAL INSTALLED
Wide Flange (Rail Hoist) 1.95 1.95 0.00 100.00% DONE / PUNCHLIST
Purlins 14.16 12.87 1.28 90.94% PARTIAL INSTALLED
Sagrods 0.29 0.18 0.11 63.02% PARTIAL INSTALLED
Floor Beam/Joist 55.48 25.86 29.63 46.60% PARTIAL INSTALLED
Checkered Plate 90.00 69.00 21.00 76.67% PARTIAL INSTALLED

TOTAL WEIGHT 572.48 430.66 152.34


CONTRACT WEIGHT 583.00
TOTAL % WEIGHT 73.87%

Prepared by: Reviewed by:

Bryan J. Fabro Leove D. Cortez


Associate Engineer Project In-Charge/Mechanical Inspector

Noted by: Approved by:

Francis. R. Mancenido Florante. N. Flores


Construction Supervisor Construction Manager
Date as of April 25, 2015
Subject : ACTUAL ACCOMLISHMENT
REPORT
PACK HOUSE EXTENSION PROJECT

Duration : (Completion April 30, 2015)


CONTRACTOR : RBR Ready Mix

STRUCTURAL STRUCTURAL STRUCTURAL


PACKHOUSE EXTENSION PROJECT (DEPT. % INSTALLED
16) Delivered at site Actual Installed nedeed to be ACCOMPLISHEMENT REMARKS
(tons) (tons) Installed (tons)
A. STRUCTURAL WORKS (INTALLATION)

Elevation 1.40 m 9.76 9.76 0.00 100.00% DONE / PUNCHLIST


Elevation 5.00 m 28.67 27.72 0.95 96.69% PARTIAL INSTALLED
Elevation 6.60 m 2.24 2.24 0.00 100.00% DONE / PUNCHLIST
Elevation 7.20 m 2.39 2.39 0.00 100.00% DONE / PUNCHLIST
Elevation 10.00 m 33.50 32.88 0.62 98.15% PARTIAL INSTALLED
Elevation 13.85 m 26.76 23.38 3.38 87.37% PARTIAL INSTALLED
Elevation 18.00 m 23.94 18.93 5.00 79.11% PARTIAL INSTALLED
Elevation 20.60 m 8.63 7.83 0.81 90.67% PARTIAL INSTALLED
Elevation 22.43 m 7.99 7.99 0.00 100.00% DONE / PUNCHLIST
Elevation 25.97 m 9.56 9.12 0.44 95.36% PARTIAL INSTALLED
Elevation 26.30 m 0.96 0.46 0.49 48.42% PARTIAL INSTALLED
Elevation 27.30 m 12.52 12.52 0.00 100.00% DONE / PUNCHLIST
Elevation 29.50 m 4.84 0.00 4.84 0.00% NOT YET STARTED
Elevation 33.30 m 11.51 10.87 0.65 94.38% PARTIAL INSTALLED
Elevation 36.70 m 2.90 2.90 0.00 100.00% DONE / PUNCHLIST
Elevation 37.85 m 29.04 28.38 0.67 97.70% PARTIAL INSTALLED
Elevation 46.30 m 5.30 5.30 0.00 100.00% DONE / PUNCHLIST
Box Column 17.54 17.54 0.00 100.00% DONE / PUNCHLIST
Planted Column Extension 55.14 53.31 1.83 96.69% PARTIAL INSTALLED
Extension Box Column 29.25 28.25 1.00 96.58% PARTIAL INSTALLED
Retrofitting & Doubler Plate 88.18 20.15 68.03 22.85% PARTIAL INSTALLED
Wide Flange (Rail Hoist) 1.95 1.95 0.00 100.00% DONE / PUNCHLIST
Purlins 14.16 12.97 1.18 91.65% PARTIAL INSTALLED
Sagrods 0.29 0.20 0.09 70.08% PARTIAL INSTALLED
Floor Beam/Joist 55.48 36.86 18.63 66.43% PARTIAL INSTALLED
Checkered Plate 90.00 70.50 19.50 78.33% PARTIAL INSTALLED
Di

TOTAL WEIGHT 572.48 444.39 138.61


CONTRACT WEIGHT 583.00
TOTAL % WEIGHT 76.22%

Prepared by: Reviewed by:

Bryan J. Fabro Leove D. Cortez


Associate Engineer Project In-Charge/Mechanical Inspector

Noted by: Approved by:

Francis. R. Mancenido Florante. N. Flores


Construction Supervisor Construction Manager
Date as of April 25, 2015
Subject : ACTUAL ACCOMLISHMENT
REPORT
PACK HOUSE EXTENSION PROJECT

Duration : (Completion April 30, 2015)


CONTRACTOR : RBR Ready Mix

STRUCTURAL STRUCTURAL STRUCTURAL


PACKHOUSE EXTENSION PROJECT (DEPT. % INSTALLED
16) Delivered at site Actual Installed nedeed to be ACCOMPLISHEMENT REMARKS
(tons) (tons) Installed (tons)
A. STRUCTURAL WORKS (INTALLATION)

Elevation 5.00 m 28.67 27.72 0.95 96.69% PARTIAL INSTALLED


Elevation 10.00 m 33.50 32.88 0.62 98.15% PARTIAL INSTALLED
Elevation 13.85 m 26.76 23.38 3.38 87.37% PARTIAL INSTALLED
Elevation 18.00 m 23.94 18.93 5.00 79.11% PARTIAL INSTALLED
Elevation 20.60 m 8.63 7.83 0.81 90.67% PARTIAL INSTALLED
Elevation 25.97 m 9.56 9.12 0.44 95.36% PARTIAL INSTALLED
Elevation 26.30 m 0.96 0.46 0.49 48.42% PARTIAL INSTALLED
Elevation 29.50 m 4.84 0.00 4.84 0.00% NOT YET STARTED
Elevation 33.30 m 11.51 10.87 0.65 94.38% PARTIAL INSTALLED
Elevation 37.85 m 29.04 28.38 0.67 97.70% PARTIAL INSTALLED
Planted Column Extension 55.14 53.31 1.83 96.69% PARTIAL INSTALLED
Extension Box Column 29.25 28.25 1.00 96.58% PARTIAL INSTALLED
Retrofitting & Doubler Plate 88.18 20.15 68.03 22.85% PARTIAL INSTALLED
Purlins 14.16 12.97 1.18 91.65% PARTIAL INSTALLED
Sagrods 0.29 0.20 0.09 70.08% PARTIAL INSTALLED
Floor Beam/Joist 55.48 36.86 18.62 66.43% PARTIAL INSTALLED
Checkered Plate 90.00 70.50 19.50 78.33% PARTIAL INSTALLED
Dismanting of Existing Structural Materials 10.52 3.50 7.02 33.27% PARTIAL DISMANTLED

TOTAL WEIGHT 583.00 447.89 135.11


CONTRACT WEIGHT 583.00
TOTAL % WEIGHT 76.82%

Prepared by: Reviewed by:

Bryan J. Fabro Leove D. Cortez


Associate Engineer Project In-Charge/Mechanical Inspector

Noted by: Approved by:

Francis. R. Mancenido Florante. N. Flores


Construction Supervisor Construction Manager
Date as of May 2, 2015
Subject : ACTUAL ACCOMLISHMENT
REPORT
PACK HOUSE EXTENSION PROJECT

Duration : (Completion May 15, 2015)


CONTRACTOR : RBR Ready Mix

STRUCTURAL STRUCTURAL STRUCTURAL


PACKHOUSE EXTENSION PROJECT (DEPT. % INSTALLED
16) Delivered at site Actual Installed nedeed to be ACCOMPLISHEMENT REMARKS
(tons) (tons) Installed (tons)
A. STRUCTURAL WORKS (INTALLATION)

Elevation 1.40 m 9.76 9.76 0.00 100.00% DONE / PUNCHLIST


Elevation 5.00 m 28.67 27.72 0.95 96.69% PARTIAL INSTALLED
Elevation 6.60 m 2.24 2.24 0.00 100.00% DONE / PUNCHLIST
Elevation 7.20 m 2.39 2.39 0.00 100.00% DONE / PUNCHLIST
Elevation 10.00 m 33.50 32.88 0.62 98.15% PARTIAL INSTALLED
Elevation 13.85 m 26.76 23.38 3.38 87.37% PARTIAL INSTALLED
Elevation 18.00 m 23.94 18.93 5.00 79.11% PARTIAL INSTALLED
Elevation 20.60 m 8.63 7.83 0.81 90.67% PARTIAL INSTALLED
Elevation 22.43 m 7.99 7.99 0.00 100.00% DONE / PUNCHLIST
Elevation 25.97 m 9.56 9.12 0.44 95.36% PARTIAL INSTALLED
Elevation 26.30 m 0.96 0.46 0.49 48.42% PARTIAL INSTALLED
Elevation 27.30 m 12.52 12.52 0.00 100.00% DONE / PUNCHLIST
Elevation 29.50 m 4.84 0.00 4.84 0.00% NOT YET STARTED
Elevation 33.30 m 11.51 10.87 0.65 94.38% PARTIAL INSTALLED
Elevation 36.70 m 2.90 2.90 0.00 100.00% DONE / PUNCHLIST
Elevation 37.85 m 29.04 28.38 0.66 97.71% PARTIAL INSTALLED
Elevation 46.30 m 5.30 5.30 0.00 100.00% DONE / PUNCHLIST
Box Column 17.54 17.54 0.00 100.00% DONE / PUNCHLIST
Planted Column Extension 55.14 53.31 1.83 96.69% PARTIAL INSTALLED
Extension Box Column 29.25 28.25 1.00 96.58% PARTIAL INSTALLED
Retrofitting & Doubler Plate 88.18 20.15 68.03 22.85% PARTIAL INSTALLED
Wide Flange (Rail Hoist) 1.95 1.95 0.00 100.00% DONE / PUNCHLIST
Purlins 14.16 12.97 1.18 91.65% PARTIAL INSTALLED
Sagrods 0.29 0.20 0.09 70.08% PARTIAL INSTALLED
Floor Beam/Joist 55.48 41.86 13.63 75.44% PARTIAL INSTALLED
Checkered Plate 90.00 75.00 15.00 83.33% PARTIAL INSTALLED

TOTAL WEIGHT 572.48 453.89 129.11


CONTRACT WEIGHT 583.00
TOTAL % WEIGHT 77.85%

Prepared by: Reviewed by:

Bryan J. Fabro Leove D. Cortez


Associate Engineer Project In-Charge/Mechanical Inspector

Noted by: Approved by:

Francis. R. Mancenido Florante. N. Flores


Construction Supervisor Construction Manager