Professional Documents
Culture Documents
A 12
A 12
75
75
BENDING SCHEDULE
75
75
2
Beams/Slab/Staircase must be fcu -25N/mm
1800
3850
3100
4150
3100
2
Reinforcement TO BEAMS Fy - 250N/mm
Fy - 400N/mm
75
75
2
Columns/Walls must be fcu -30N/mm
MARK DIA. LENG. QTY.
288
108
120
72
16
Reinforcement TO COLUMNS
3175
3850
1600
1950
4150
3175
Cover to reinforcement
Concrete to frames
T20
T20
Foundations -50mm
T16
T16
R12
R16
NOTE 1 :
Columns -40mm
T2002
T1602
T1603
T2001
R1201
R1601
Beams -25mm
BAR
slab - 25mm
ROOF L.
450
B B
3150
2700
4T2002 + 8T1603
6th F.L
450
B B
3150
2700
R1201@ 150c/c
4T2001 + 8T1602 1500
5th F.L
T16 T16 T16 T16
450
250
B 2T20 2T20
B
3150
2700
4th F.L
22050
SECT. B - B
450
2x72R1201@ 150c EF
B
3150
B
2700
4T2001 + 8T1602
3rd F.L
450
H H
3150
2700
8T2001 +12T1602
2nd F.L
450
H
3150
H
2700
8T2001 +12T1602
1st F.L
450
2x54R1601@ 150c EF
3150
H
2700
APPROVED BY
8T2001 +12T1602
H
G.L
SIGNED BY
client
SYLVIA OTUO -
ACHEAMPONG
project & location