Title: Project PRYM ( Plant and Reap for You and ME)

Goal: Build at least 50 % of Gualayn sa Paaralan Facility

Outcome: The Gulayan sa Paaralan Facility were 50% in progress.

IMPLEMENTATION PLAN 2022-2023


Responsible/Accountable
Critical Action Timeframe Estimated Budget Budget Source
Unit (FD)
Where will the
What actions/activities When must the How much will it funding come from?
Who is responsible for the
must be completed to action/activity be cost to implement (internal and
action/activity?
implement the policy? completed? the action? external funding
source)
OUTPUT 1 Conduct Data Analysis on the Area for Gulayan

Check the soil and the School Head, School GULAYAN


Activity 1 August 2022 None N/A
Area to be covered sa Paaral Coordinator

School Head, School GULAYAN


Activity 2 Look for Man power August 2022 None N/A
sa Paaral Coordinator, SGC

OUTPUT 2 Identifying the Plants and Remedy for Acidic soil

Conduct Root Cause School Head, School GULAYAN


Activity 1 August 2022
Analysis sa Paaral Coordinator
Listing of Possible School Head, School GULAYAN
Activity 2
Solutions to the problem sa Paaral Coordinator

Construct Project School Head, School GULAYAN


Activity 3 August 2022
Proposal sa Paaral Coordinator

School Head, School GULAYAN


Activity 4 Create Action Plan August 2022
sa Paaral Coordinator

OUTPUT 3 Implementation ofProject PRYM ( Plant and Reap for You and ME)

School Head, School GULAYAN


Activity 1 Conduct SPTA meeting September 2022
sa Paaral Coordinator

School Head, School GULAYAN MOOE/ Donations


Activity 2 Look for Donations September 2022 30,000.00
sa Paaral Coordinator from stakeholders

School Head, School GULAYAN


Activity 3 Build the Facility September 2022
sa Paaral Coordinator

OUTPUT 4 Monitoring and Provision of Technical Assistance

School Head, School GULAYAN


Activity 1 Checking of attendance November 2022 None N/A
sa Paaral Coordinator
Monitoring the Progress School Head, School GULAYAN
Activity 2 March 2023 None N/A
of Project PRYM sa Paaral Coordinator

Conduct frequent visit


Activity 3 School Head July 2023 None N/A
to school Gulayan

Provide Technical
Activity 4 School Head July 2023 None N/A
assistance

OUTPUT 5 Communicated Results of Project PRYM

Activity 1 Implementation Review School Head July 2023 None N/A